RESOLVED that; i) the Procurement Plan for the procurement of the works contract for the refurbishment / remodelling of Time Square attached at exempt Annex A, be approved. ii) the decision to award the construction contract for the Time Square refurbishment works be delegated to the Director of Corporate Services in consultation with the Executive Member for Transformation & Finance. This is in order to be able to move quickly to commence the contract in view of the need to deliver the savings from vacating Easthampstead House as quickly as possible.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1To approve the Procurement Plan for the procurement of the works contract for the refurbishment / remodelling of Time Square.
1.2To seek a delegation of the decision to award the construction contract for the Time Square refurbishment works to the Director of Corporate Services in consultation with the Executive Member for Transformation & Finance. This is in order to be able to move quickly to commence the contract in view of the need to deliver the savings from vacating Easthampstead House as quickly as possible.
Recommendation
2.1That the Procurement Plan for the procurement of the works contract for the refurbishment / remodelling of Time Square attached at annex A (restricted paper), is approved.
2.2That the decision to award the construction contract for the Time Square refurbishment works is delegated to the Director of Corporate Services in consultation with the Executive Member for Transformation & Finance. This is in order to be able to move quickly to commence the contract in view of the need to deliver the savings from vacating Easthampstead House as quickly as possible.
Reasons for recommendation
3.1That the decision to award the construction contract for the Time Square refurbishment works is delegated to the Director of Corporate Services in consultation with the Executive Member for Transformation & Finance.
Alternative options considered
4.1None, as it is a requirement of the Contract Standing orders that any contracts in excess of £100,000 are required to go out to a formal tendering process to ensure value for money and compliance with legislation.
5 SUPPORTING INFORMATION
5.1This project will enable the Council to consolidate it’s property portfolio and reduce the existing operational arrangements and budgets required in order to maintain both sites. Unrestricted
5.2It is expected that the tendering process will provide for an increase in the quality of provision whilst ensuring value for money.
5.3The works are below the OJEU threshold, notices will be placed on the South East Business Portal and Contracts Finder.
5.4The actual construction phase will be based on the successful tenderers submission in both cases.
Currently the programme dates are as follows:
Task DATE
Procurement Plan Sign Off 14 March 2017
Selection Questionnaire (SQ) Published / S.E 27 March 2017 Business Portal
Response deadline 15 May 2017
Evaluation complete 22 May 2017
ITT issued 14 June 2017
ITT response deadline 11 July 2017
Contract award (Time Square remodelling 12 September 2017 works only)
Construction starts 14 October 2017
Construction completion 06 February 2018
Handover 20 February 2018
The above project programme is based on the decision of award of the works contracts being delegated to the Director of Corporate Services in consultation with the Executive Member for Transformation and Finance.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1No significant legal issues arise from the matters discussed in this report.
Borough Treasurer
6.2The financial implications are contained in the Procurement Plan.
Equalities Impact Assessment
6.3Attached as appendix B. Unrestricted
Strategic Risk Management Issues
6.4Contained within the procurement plan.
Consultation
Principal Groups Consulted
7.1Council Officers including the Head of Procurement, Borough Solicitor and the Borough Treasurer were consulted in the drafting of this plan.
Contact for further information Kamay Toor – 01344 355183 [email protected]
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.