Resolved
Cabinet
Cabinet decided this item on Tuesday 6 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet
1.1Brent’s building stock offers significant potential for improvement in energy efficiency. This report details a project which sets out to improve the energy efficiency of the selected Brent Council retained buildings with the highest energy consumption, creating energy and cost savings to the council.
1.2This project forms part of the wider Climate and Ecological Emergency delivery strategy, to reach net zero carbon emissions before 2030, and specifically in leading by example to decarbonise Brent’s own buildings.
1.3The project will be funded using £3,234,000 of Section 31 grant funding won through the Public Sector Decarbonisation Scheme (PSDS), via the Government department BEIS (Department for Business, Energy & Industrial Strategy), and administered by Salix Finance, a non-departmental public body. The breakdown of costs is included in 5.2, and the total includes funding for Project Management support.
1.4Forecast annual savings from all the measures in the application total £174k per annum. This figure is subject to improved accuracy of forecast in an Investment Grade Proposal.
1.5A condition of the PSDS grant scheme is that the works should be complete by September 2021 where possible, with the final date for completion of the works by March 2022.
2.0Recommendations for Cabinet
That Cabinet
2.1Approves the project to improve the energy efficiency of selected Brent Council retained buildings with the highest energy consumption as detailed in Table 1 at paragraph 3.8.
2.2Delegates authority to the Assistant Chief Executive, in consultation with the Lead Member for the Environment, to make further adjustments to the building and technology selection for the project referred to in 2.1 above to ensure best value for the reasons detailed in paragraph 3.7.
2.3Approves the Council entering into a grant agreement with the Department for Business, Energy & Industrial Strategy to fund the project referred to in 2.1 above in the sum of £3,234,000.
2.4Notes that Officers will undertake procurements to appoint a range of consultants and contractors using powers delegated under Part 3 of the Constitution to achieve the aims of the project referred to in 2.1 above.
3.0Detail
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
9a. Appendix 1: 2019-20 Brent total tCO2 by building and site (1)Appendix | 210 KB | Download |
PDF |
9c. Appendix 3: Example of measures for the proposed buildingsAppendix | 510 KB | Download |
PDF |
9d. Appendix 4: Risk MatrixAppendix | 483 KB | Download |
PDF |
Public Sector Decarbonisation Scheme: Energy Efficiency: Works in Brent Corporate BuildingsReport | 460 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.