Policy, Finance and Resources Committee approved this item on Tuesday 30 June 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. The Head of Paid Service be granted delegated authority to dispose of the Old House at best value (on the basis that planning approval being obtained and listed building consent had been granted). REASON FOR RECOMMENDATION To enable the creation of a capital receipt for the Council.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1This report considers the progress to date for the proposed refurbishment project for the Old House.
2. Recommendation(s)
2.1That the Head of Paid Service be granted delegated authority to dispose of the Old House at best value (on the basis that planning approval being obtained and listed building consent being granted).
3. Introduction and Background
3.1Members will recall the progress report to the March Asset and Enterprise Committee detailing the progress made on the refurbishment project. Since that meeting the tender process to select suitable contractors to carry out the works has now been completed with the tenders returned on 17th April 2015.
3.2Interviews with the three best contractors were held on 28th April 2015 where they were asked in addition to submit their best Guaranteed Maximum Price (GMP) to cover all risks for the Council with the exception of design changes.
3.3The three best returns are contained in Appendix A (exempt) which shows both the tender return as per the specification and also the best GMP. Members will see that the best GMP exceeds the budget available for the project. 3.4 Members will be aware that both the planning application and listed Buildings consent for the project have now been submitted and are awaiting determination. Being a Council owned property, the application is required to be reported to the Planning and Licensing Committee for determination.
3.5To date, £99,000 has been spent that has enabled the planning and listed building application to be submitted, which will help achieve the best sale price.
3.6This expenditure is made up of Architects, Heritage Assessment, Quantity Surveyors, Services, Structures, Ivey management CDM, Acoustics, Asbestos survey and utilities costs.
3.7Professional works still to be achieved are Bat survey and Damp surveys but not necessary for the planning application.
4. Issue, Options and Analysis of Options
4.1Members will be aware that the Councils approved Capital programme had included £ 1,080,000 for the Old House Redevelopment project before being revised by Ordinary Council on 10th June 2015.
4.2Given the age and complexity of the building, there is a significant risk to completing the project. Whilst some of this has been reduced through investigation and design in conjunction with Planning and Natural England, the risk still remains high and cannot be fully understood until the project is underway and Old House has been physically stripped out and all possible issues exposed.
4.3As part of the Contract, over estimation of repairs have been included in the specification together with a sizeable contingency sum of £100,000 to cover unforeseen design changes and any further additional works not accounted for.
4.4Officers are aware of the report to Ordinary Council on 10th June 2015 with amendments to the Capital Programme including the removal the capital allocation of £1,080,000 from the Capital Programme and now seek the direction of the Committee as regards this project.
4.5The GMP value indicates the 'no risk' cost to the Council and where the Contractor covers all risks to the project with the exception of any design changes. 5. Consultation
5.1No formal consultation has been undertaken regarding the proposed refurbishment
6. References to Corporate Plan
6.1Value for Money: policies that invest in key services to create opportunity for all, provide better value for Brentwood’s taxpayers and enhance the Borough’s infrastructure whilst modernising and transforming Brentwood Borough Council. We will re-prioritise and focus our resources and be innovative in our approach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.