CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Brentwood Borough Council
Policy, Projects and Resources Committee, Monday 12 March 2018 at 7.00pm

Preparation for General Data Protection Regulation - GDPR

Approved Committee 6 papers

Policy, Projects and Resources Committee approved this item on Monday 12 March 2018. Below is the council's own wording, with the papers it was decided on.

Item306

Resolved

RESOLVED UNANIMOUSLY . 1. That the attached updated compliance action plan (Appendix A), be approved to enable officers to roll out effective GDPR compliance across the Council by 25 May 2018. 2. That Members note and approve the following additional revised and updated policy documents: • Data Protection Policy; • Data Breach Policy; • Consents Policy; • Data Processing Impact Assessments Policy; • Privacy Notices Policy; and • Clear Desk Policy, with delegated authority granted jointly to the Head of Legal Services and the Senior Information Risk Officer to revise and update once the details of the new Data Protection Act are known. Reasons for Recommendation Members have approved a compliance action plan and project plan. This is a complex, council wide project so that some dates for action/completion under the project plan are subject to change for operational reasons. In addition, the law in terms of a new Data Protection Act is not yet enacted and further changes to the detail may be possible. This will not affect the overall projected completion date of 25 May 2018, though some on-going work will be necessary. Specific work flows will be developed following receipt of council-wide responses to a questionnaire which has been sent out to all departments, along with guidance notes and other documents. This is vital to capture all information necessary to ensure compliance in all areas in due course, both hard copy and electronic. The deadline for responses is 12th March. After that we will analyse the information and categorise it. A programme of review and deletion of outdated material will then follow. Specific GDPR training will be put in place for both officers and Members to complete ... view the full minutes text for item 306.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Policy, Projects and Resources Committee

Executive summary

1.1On 25 May 2018, the General Data Protection Regulation (GDPR) will come into full force. In addition, the Data Protection Bill 2017 will effectively adopt GDPR directly into English law. The new Act will therefore have three main themes:

 Extending the scope of data regulation  Empowering individuals to have greater control over their own data  Building privacy into products and services  Imposing big sanctions for non-compliance

1.2Members considered a report on progress at the January meeting and this report provides a further update. The Council has continued to make progress towards introducing GDPR compliant measures in time for the new law coming into effect in three months’ time.

1.3Members are asked to consider and adopt a raft of policies to ensure compliance with new data protection legislation. 2. Recommendations

2.1That the attached updated compliance action plan (Appendix A), be approved to enable officers to roll out effective GDPR compliance across the Council by 25 May 2018.

2.2That Members note and approve the following additional revised and updated policy documents:

 Data Protection Policy;  Data Breach Policy;  Consents Policy;  Data Processing Impact Assessments Policy;  Privacy Notices Policy; and  Clear Desk Policy,

with delegated authority granted jointly to the Head of Legal Services and the Senior Information Risk Officer to revise and update once the details of the new Data Protection Act are known.

3. Introduction and Background

3.1Data protection law requires individuals’ personal data we hold to be processed securely, with severe and newly increased penalties for non- compliance. For this purpose, as part of the Council’s general review of information governance, the Council is developing a new suite of data protection policies and procedures.

3.2All relevant staff have been engaged to complete an online data protection training module based on these policies, during November and December 2017. This training module has now been made available to all Members.

3.3The General Data Protection Regulation (GDPR) entered into force on 24 May 2016. However, enforcement of the GDPR will not begin until 25 May. Organisations therefore have a limited window in which to ensure that their data processing activities are compliant with the requirements of the GDPR. The national laws implementing the Directive in each Member State will continue to apply until the GDPR Effective Date. However, the process of becoming compliant with the GDPR will take much planning and a significant amount of time. A Data Protection Bill is currently before Parliament and this will effectively adopt GDPR when enacted in due course. At the time of writing, the bill is awaiting its second reading in the House of Commons (5th March), having completed all stages in the House of Lords. The bill is substantial, containing nearly 200 sections and 18 schedules.

3.4The Council has therefore commenced work on its strategy for introducing GDPR compliant measures in time for the new law coming into full effect in May 2018.

4. Issue, Options and Analysis of Options

4.1The main issue continues to be achieving effective buy-in from all staff across the Council. To this end, the Chief Executive has published on the Council’s intranet a message to all staff explaining GDPR is coming and that all staff need to cooperate with actions as directed by the GDPR senior officer steering group, established to oversee the project. GDPR is a mandatory statutory requirement so the only available option is to comply with the new legislation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Updated GDPR Compliance PlanAppendix A 52 KB Download
PDF
Data Protection PolicyAppendix B 78 KB Download
PDF
Data Breach PolicyAppendix C 74 KB Download
PDF
Information Security PolicyAppendix D 60 KB Download
PDF
Consents PolicyAppendix E 74 KB Download
PDF
Preparation for General Data Protection Regulation: GDPRReport 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 21 attended
ML
Councillor Mrs Louise McKinlayChair, present
JK
Councillor John KerslakeVice-Chair, present
GB
Councillor Gareth BarrettCommittee Member, present
PF
Councillor Paul FaragherCommittee Member, present
CH
Councillor Chris HossackCommittee Member, present
RK
Councillor Roger KeebleCommittee Member, present
DK
Councillor David KendallCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
KP
Councillor Keith ParkerCommittee Member, present
RH
Councillor Roger HirstSubstitute, in attendance
MJ
Councillor Mrs Jill HubbardSubstitute, in attendance
ML
Councillor Ms Louise RowlandsSubstitute, in attendance

All 21 on the meeting page

On this subject at Brentwood

Search all
  1. Preparation for General Data Protection Regulation - GDPRThis decision
  2. Preparation for General Data Protection Regulation - GDPRApproved

More from Brentwood Policy, Projects and Resources Committee

All decisions
MeetingDecisionOutcome
18 Sep 2018 2018/19 General Fund Revenue, Housing Revenue Account, Capital Budget Monitoring and Treasury Activity UpdateRESOLVED UNANIMOUSLY: 1. To agree the projected outturn position for 2018/19 of the Council’s General Fund Revenue bu... Agreed Open
18 Sep 2018 Department for Communities and Local Government (MHCLG) Pilot Programme for 75% Business Rates Retention - 2019/20RESOLVED UNANIMOUSLY: 1. Members note the content of the report and its potential implications for the forthcoming bu... Agreed Open
18 Sep 2018 Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on... Approved Open
18 Sep 2018 Feasibility Study for Parking on Housing GreensRESOLVED UNANIMOUSLY: 1. To instruct officers to identify possible sites for parking on Housing Greens and undertake ... Decided Open
18 Sep 2018 Leisure StrategyThat Members agree the and action plan at Appendix A. Reasons for Recommendation As part of the Council’s due diligen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies