Policy, Projects and Resources Committee approved this item on Monday 12 March 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED . That the Committee recommends to Council: 1. That a Competitive Dialogue Procedure under the Public Contracts Regulations 2015, to procure a joint venture partner commences. 2. That the procurement documentation set out in the appendices be approved. 3. That Delegated Authority is given to the Chief Executive, after consultation with the Leader of the Council, to finalise all documentation required to support the procurement process. Reasons for Recommendation To commence a Competitive Dialogue Procedure under the Public Contracts Regulations 2015, approval by Council is required.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Policy, Projects and Resources Committee
Executive summary
1.1This report seeks approval to commence a procurement process under the Public Contracts Regulations 2015 using the Competitive Dialogue procedure to procure a joint venture partner.
1.2A joint venture partner is required to enable the Council to further its asset development programme.
Recommendations
That the Committee recommends to Council:
2.1That a Competitive Dialogue Procedure under the Public Contracts Regulations 2015, to procure a joint venture partner commences.
2.2That the procurement documentation set out in the appendices be approved.
2.3That Delegated Authority is given to the Chief Executive, after consultation with the Leader of the Council, to finalise all documentation required to support the procurement process.
3. Introduction and Background
3.1The Council’s Asset Development Programme has now progressed to a point where it is necessary to seek a development partner to enable it to achieve its objectives.
3.2Through utilising specialised consultants, use of soft market testing and reporting to Policy, Projects and Resources Committee it became apparent that a joint venture partner would be the best delivery option. 3.3 On 19th September 2017 the Policy, Projects and Resources Committee agreed the joint venture approach, and on the 6th February 2018 the Committee agreed that a decision to formally tender for a partner be brought for decision.
3.4Due to the potential value of the projects that maybe taken forward under a joint venture a full Competitive Dialogue Procedure under the Public Contracts Regulations 2015 is required.
4. Procurement Process
4.1To ensure an effective procurement process the Council has engaged the services of: East of England Local Government Association (EELGA) 31ten Consulting (via EELGA) Sharpe Pritchard J C Gill and Co Limited
4.2These consultants are familiar with public sector joint venture partnerships, the Competitive Dialogue Procedure and have been involved in similar procurements before. Their knowledge will be highly beneficial in securing the right partner.
4.3The procurement process is outlined in the following paragraphs:
4.4Qualification Stage – This is the first sift of bidders and aims to identify early those who are most likely to be selected as a partner. Bidders will respond to the Selection Questionnaire and be evaluated in accordance with their response (Appendix A). Following this, it is likely that five bidders will be selected to go through to the next stage. Restricting the number to five will provide the Council with a strong selection of partners and keep the assessment resources required at the next stage reasonable. The bidders will also remain engaged knowing the competition has decreased when they progress to the detailed solution stage.
4.5Detailed Solution Stage – The successful five bidders will be invited to submit their detailed solutions in accordance with the Council’s instructions (Appendix B). Solutions are discussed through dialogue sessions with the Council and then submitted through answering a series of evaluation questions (Appendix C). A shortlist of three bidders will then be drawn up based on how well their solutions meet the Council’s requirements, as determined by the scoring methodology outlined in the instructions.
4.6Final Stage – The final three bidders have an opportunity to refine their solutions in line with the Council’s detailed requirements as articulated in the bid documents. Solutions are further discussed through dialogue sessions and then their final bids are submitted. A Preferred Bidder is then selected based on how well their solutions meet the Council’s requirements, as in the detailed solution stage. Full Council will be required to approve the successful partner and a period of contract refinement will take place before the contracts are signed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Projects and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.