Resolved
Agree that the site is appropriated to the Housing Revenue Account for a capital receipt of up to £225,000 for the development of new housing.
Policy & Resources Committee (pre 2015) agreed this item on Thursday 22 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Agree that the site is appropriated to the Housing Revenue Account for a capital receipt of up to £225,000 for the development of new housing.
That the Policy & Resources Committee be recommended to agree that the site is appropriated to the Housing Revenue Account for a capital receipt of up to £225,000 for the development of new housing.
HOUSING COMMITTEE
4.00pm 12 NOVEMBER 2014
COUNCIL CHAMBER, HOVE TOWN HALL
DRAFT MINUTES
Present: Councillor Randall (Chair) Councillor Phillips (Deputy Chair), Barnett, Daniel, Meadows, Kennedy, Mears, Peltzer Dunn (Opposition Spokesperson), Rufus and Wilson (Group Spokesperson)
PART ONE
60 NEW HOMES FOR NEIGHBOURHOODS – KENSINGTON STREET – FINAL SCHEME APPROVAL
60.1The Committee considered the report of the Executive Director Environment, Development and Housing which informed Members that Housing Committee gave delegated authority in September 2012 to award a contract following completion of a procurement process for a delivery partner to take forward final feasibility design and development of new council homes to rent on four former garage and parking sites in
3 L HOUSING COMMITTEE 12 NOVEMBER 2014
the city. The Guinness Partnership was selected to take four sites forward including the car parking site at Kensington Street, Brighton. The report was presented by the Project Manager, Estate Regeneration Team.
60.2Councillor Mears commented that the units looked very small. The Housing Programme Manager replied that the scheme complied with national space standards.
60.3Councillor Peltzer Dunn asked for clarification around the financial implications in Section 6 of the report. The Housing Programme Manager explained that the project commenced with an indicative budget. Full costs would not be known until a contractor was procured. The project was in budget.
60.4Councillor Phillips stated that she was not comfortable with approving an 80% market rent. She asked if a working group could be established to consider alternative financial proposals to try to achieve a lower market rent level.
60.5The Principal Accountant stressed that the proposals in the report were based on the rent model being set at 80% market rent capped at LHA rate.
60.6Councillors Meadows and Wilson agreed that they did not want the scheme to be delayed.
60.7Councillor Peltzer Dunn asked if the development would be endangered if 80% market rent was not agreed. The Executive Director Environment, Development and Housing replied that under those circumstances, the scheme would not be viable unless there was a subsidy.
60.8The Housing Programme Manager emphasised that the report was recommending approval of the rent model set at 80% market rent capped at LHA rate. This was below the market rent level.
60.9Councillor Phillips suggested that a working group could be established to consider new information for future schemes.
60.10RESOLVED –
(1) That Option One is agreed for the scheme as set out in Table 1.
(2) That the design be noted.
(3) That the rent model set at 80% market rent capped at LHA rate be approved.
(4) That the estimated levels of subsidy required from the HRA for the chosen rent model be approved and that delegated authority be given to the Executive Director of Environment, Development and Housing and the Executive Director of Finance and Resources in consultation with the Estate Regeneration Member Board to agree reasonable amendments to that subsidy if changes arise.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New Homes for Neighbourhoods: Kensington Street: Final Scheme ApprovalReport | 71 KB | DownloadRead as text |
PDF |
New Homes for Neighbourhoods: Kensington Street developmentReport | 125 KB | Download |
PDF |
Site Briefing NoteReport | 3.3 MB | Download |
PDF |
View as HTML (122./2) 73 KBReport | 73 KB | Download |
PDF |
View item 122. as HTML 39 KBReport | 39 KB | Download |
Follow Policy & Resources Committee (pre 2015) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Apr 2016 | Procedural BusinessThat the press and public be excluded from the meeting during consideration of the items contained in part two of the... | Decided | Open |
| 28 Apr 2016 | Tower House1) That the Committee should read and consider the consultation outcome and the equalities impact assessment to infor... | Decided | Open |
| 28 Apr 2016 | Learning Disabilities Accommodation Services1) That the Policy & Resources Committee members should read and consider the full consultation outcome and equalitie... | Decided | Open |
| 28 Apr 2016 | Orbis Programme UpdateRESOLVED – That the Committee: 1) Notes the progress made in carrying out due diligence for Brighton & Hove City Coun... | Agreed | Open |
| 28 Apr 2016 | Senior Management Team Re-OrganisationRESOLVED – That the Committee: 1) Notes the proposed officer re-organisation as set out in the report; 2) Notes that ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.