Resolved
View the decision text for item 40.
Audit & Standards Committee decided this item on Tuesday 9 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 40.
2.1That Audit & Standards Committee note the contents of the report.
3. CONTEXT/ BACKGROUND INFORMATION
3.1Mears Ltd. provide a comprehensive responsive repairs, planned maintenance and major works service for council homes across the city under a 10-year contract. Around 20% of the annual contract is responsive repairs and the remainder of the contract is for planned work and major works. This review relates solely to some domestic rewire activities.
3.2At Audit & Standards Committee on 19 September 2017, recommendations were made that the Housing service should review and resolve (in conjunction with the contractor) possible discrepancies between work carried out and the charges for electrical work under the housing repairs contract.
3.3Our key focus has been to address any health & safety concerns that may have arisen where there are any discrepancies arising in relation to any electrical
1 works not being completed as charged. We have undertaken significant work to identify any properties affected by this type of potential shortfall and no health and safety concerns have been identified in relation to any of the jobs subject to review.
3.4Audit recommendations required further investigation by both Mears and Brighton & Hove City Council to test the findings of some possible discrepancies against the contract, going back to contract commencement in 2010. The Housing service and Mears have undertaken a detailed analysis of potential discrepancies between work carried out and application of the schedule of rates for electrical work under the housing repairs contract. Inspection visits, validation of data and other information has been undertaken
3.5In a few areas differences in interpretation have been identified in terms of how a schedule of rate has been applied. A final piece of work needs to be completed to reach a shared agreement between the parties in relation to the areas which have been interpreted differently to avoid any uncertainty in the future. This agreement will be reflected in a formal amendment to the contract.
3.6There are some jobs where minor errors have been identified and explained. These will be dealt with through the standard contract invoice review process.
3.7There are a number of learning points and recommendations that have been identified through this review. These include:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Electrical WorksReport | 237 KB | DownloadRead as text |
PDF |
View item 40. as HTML 48 KBReport | 48 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.