2.1That Audit & Standards Committee note the content of the report.
3. CONTEXT/ BACKGROUND INFORMATION
3.1The Council and Mears entered into a long term partnership agreement in 2010 for the provision of a full range of property maintenance services and other associated works primarily but not exclusively for those properties held within the Council’s Housing Revenue Account. This report relates solely to domestic rewire activities undertaken as part of the planned maintenance programme set out in that Contract.
3.2In 2016/17 finance officers raised queries about the charges relating to domestic rewires undertaken under the Contract. These queries were initially investigated as a desktop exercise by Housing who reviewed contract and works order information stored within the Mears job management system (“MCM”). The results were flagged up with Internal Audit colleagues who carried out a small number of site visits alongside Housing surveyors to verify the accuracy of the data.
3.3The audit review identified nine areas for further investigation.
59 3.4 Of the nine categories some relate to the interpretation of the specification and the application of the contract schedule of rates as amended and updated since the commencement of the contract in 2010. The issues in respect of each are set out in the confidential Appendix 1 together with recommendations as to specific aspects of the claims arising in relation to electrical work streams.
Contract provisions relating to dispute resolution procedures
3.5The Contract in the Standard Form of Contract for Term Partnering 2008 as amended provides that the parties “shall work together and individually in the spirit of trust, fairness and mutual co-operation”. As such, it is the expectation that the parties shall act reasonably, adopting the partnering ethos. The Contract sets out an initial hierarchical methodology of problem solving involving discussion and consultation in relation to issues arising under the Contract, followed by a reference to a chosen Alternative Dispute Resolution (ADR) procedure to be agreed by the parties if the matter has not been resolved locally.
3.6There are a number of ADR options available. The Contract terms promote flexibility in accordance with the partnering ethos and it is open to the parties to agree, possibly with the advice of the Partnering Advisor named in the Contract (Trowers & Hamlin LLP), the form that procedure will take. Each has its own cost implications but generally they are usually cheaper and quicker than submitting disputes to the jurisdiction of the courts. In any event, the courts will expect that the dispute resolution procedures have been complied with, before court proceedings are commenced.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Electrical WorksReport | 240 KB | DownloadRead as text |
PDF |
View item 54. as HTML 52 KBReport | 52 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.