Bristol City Council
Cabinet, Tuesday 21 January 2020 at 4.00pm

South Bristol Sports Centre Reinstatement Tender - Phase 1

Approved Executive 1 paper

Cabinet approved this item on Tuesday 21 January 2020. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

Cabinet approved the variation to the existing contract to 21CBS to conclude the remaining works for Phase 1 estimated a cost of £750,000 (which includes a contingency); and, 2. Cabinet delegated authority to the Executive Director of Resources, (in consultation with the Deputy Mayor with responsibility for finance, governance and performance), to take all necessary steps to appoint 21CBS to complete the remaining works to rebuild the SBSC.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 21 January 2020

TITLE South Bristol Sports Centre – Reinstatement Tender – Phase 1

Ward(s) Stockwood Author: Penny Fell Job title: Director: Commercialisation, Citizens and Shareholder Liaison Cabinet lead: Cllr Craig Cheney Executive Director lead: Mike Jackson Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To seek approval for the award of a variation for the completion of the remainder of Phase 1 of the enabling and reinstatement works at South Bristol Sports Centre, to 21 Century Building Services (21CBS), the contractor already delivering Phase 2. Evidence Base: 1. A fire caused substantial damage to part of the South Bristol Sports Centre (SBSC) in May 2018. 2. The facility is owned by Bristol City Council (BCC) and operated by a Trust under a Community Asset Transfer Lease from BCC. 3. The terms of that Lease oblige the Landlord (BCC) to insure and, in the event of a claim, to apply insurance monies to the reinstatement of the building. 4. BCC’s insurers have agreed a settlement for reinstatement works; however, the level of costs has yet to be agreed. 5. The Tenant will suffer continued losses from protracted business interruption, but has an insurance policy to cover this that expires on 8 May 2020. 6. To reduce the business interruption a two Phase approach was taken to restoring the facilities and bring income streams online as soon as possible. 7. The first phase (enabling and reinstatement works to Sports Pavilion, including the reception area) was tendered and Dri-Build was commissioned to provide these works. 8. The second Phase was tendered and 21CBS was commissioned to undertake this work, comprising enabling and reinstatement works to the squash courts (Contract value £1,021,486.11) 9. In September 2019 Dri-Build went into administration, leaving Phase 1 unfinished. 10. The Council is contractually obliged to carry out the works the cost of which should be funded by the insurer. 11. It is proposed to use 21CBS to complete the Phase 1 works rather than retender as the delay to reinstatement works and additional costs associated with a retender would outweigh any savings. 12. Discussions are ongoing with the Loss Adjustors and Insurers and the full financial situation should be available for Cabinet in January.

Cabinet is therefore asked to approve the award of a variation to the existing contract to 21CBS for the completion of Phase 1. It is proposed that this is completed, in line with the Phase 2 programme of works, by 8 May 2020.

Cabinet Member / Officer Recommendations:

1 Version May 2019 That Cabinet: 1. Approve the variation to the existing contract to 21CBS to conclude the remaining works for Phase 1 estimated a cost of £750,000 (which includes a contingency); and, 2. Delegate authority to the Executive Director of Resources, (in consultation with the Deputy Mayor with responsibility for finance, governance and performance), to take all necessary steps to appoint 21CBS to complete the remaining works to rebuild the SBSC. Corporate Strategy alignment: 1. The Council as landlord is legally obliged to complete the reinstatement works. City Benefits: 1. The social and health outcomes of the Sports Centre are hugely positive to the local community and wider population. Consultation Details: 1. BCC is in weekly contact with the SBSC Trustees and SBSC representatives, including regular meetings to update them on progress on the project. Background Documents: 1. Cabinet Paper and approval 5 February 2018.

Revenue Cost £ Source of Revenue Funding Capital Cost £750,000 Source of Capital Funding Insurance* One off cost ☐ Ongoing cost ☐ Saving Proposal ☐ Income generation proposal ☐ *Please note: any shortfall to be met from Capital and tenant contribution which is to be confirmed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
South Bristol Sports Centre Reinstatement Tender: Phase 1Report 124 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, apologies
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, present
PS
Councillor Paul SmithCommittee Member, present
SP
Councillor Steve PearceCommittee Member, present
RA
Rachel AbbaOfficer, expected
SM
Sara ManixOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. South Bristol Sports Centre Reinstatement Tender - Phase 1This decision
  2. Bristol Operations Centre Inter Authority Agreement for South Gloucestershire Community Safety CCTV MonitoringDecided
  3. 23/00854/A - Land Adj To Waste Transfer Station Days Road Bristol BS2 0JE - Single sided illuminated landscape display facing South to show illuminated static images.Decided
  4. Renewal of existing shared Bristol, North Somerset and South Gloucestershire wide system – Connecting Care ContractApproved
  5. Cemetery and Crematorium Capital Programme – South Bristol Cemetery ExpansionNoted
  6. Bristol, North Somerset and South Gloucestershire (BNSSG) Integrated Care System (ICS) StrategyApproved

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies