That Cabinet: 1. Noted the progress which has been made on the future provision of the City’s cemetery and cremation service as outlined in this report. 2. Approved the use of Strategic Community Infrastructure Levy in relation to Phase 1 of South Bristol Cemetery Expansion. 3. Authorised the Executive Director Growth and Regeneration in consultation with the Cabinet Member Public Health and Communities to take all steps required to spend the Strategic CIL (Community Infrastructure Levy) allocation and procure and award the contracts for the Phase 1 works to deliver the South Bristol Cemetery Expansion project. 4. Noted that a further report will be brought back in accordance with the decision pathway in relation to the Phase 2 development for Bristol Cemetery Expansion Works.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Proposal title: Cemetery Expansion Capital Programme – EIA to support the Cabinet Paper for South Bristol Cemetery Expansion Project. Project stage and type: ☐ Initial Idea Mandate ☐ Outline Business Case ☒ Full Business Case ☐ Policy ☐ Strategy ☐ Function ☒ Service ☐ New ☐ Changing ☐ Other [please state] ☒ Already exists / review Directorate: Growth & Regeneration Lead Officer name: Jon James Service Area: Natural and Marine Environment Lead Officer role: Head of Service for N & M Env.
Step 1: What do we want to do? The purpose of this Environmental Impact Assessment is to help you develop your proposal in a way that is compliant with the council’s policies and supports the council’s strategic objectives under the One City Climate Strategy, the One City Ecological Emergency Strategy and the latest Corporate Strategy. This assessment should be started at the beginning of the project proposal process by someone with a good knowledge of the project, the service area that will deliver it, and sufficient influence over the proposal to make changes as needed. It is good practice to take a team approach to completing the Environmental Impact Assessment. See further guidance on completing this document. Please email [email protected] early for advice and feedback.
1.1What are the aims and objectives/purpose of this proposal? Briefly explain the purpose of the proposal and why it is needed. Please use plain English, avoiding jargon and acronyms. Expand burial provision at South Bristol Cemetery to meet the future need for burials, baby burial, ash interment and to accommodate specific belief / faith burial requirements.
1.2Will the proposal have an environmental impact? Could the proposal have either a positive or negative effects for the environment now or in the future? If ‘No’ explain why you are sure there will be no environmental impact, then skip steps 2-3 and request review by sending this form to [email protected]
If ‘Yes’ complete the rest of this assessment. ☒ Yes ☐ No [please select]
1.3If the proposal is part of an options appraisal, has the environmental impact of each option been assessed and included in the recommendation-making process? If ‘Yes’ please ensure that the details of the environmental impacts of each option are made clear in the pros and cons section of the project management options appraisal document.
☒ Yes ☐ No ☐ Not applicable [please select]
If ‘No’ explain why environmental impacts have not been considered as part of the options appraisal process. Step 2: What kinds of environmental impacts might the project have? Analysis of impacts must be rigorous. Please demonstrate your analysis of any impacts of the proposal in this section, referring to evidence you have gathered. See detailed guidance documents for advice on identifying potential impacts. Does the proposal create any benefits for the environment, or have any adverse impacts? Outline any potential benefits of the proposal and how they can be maximised. Identify how the proposal will support our corporate environmental objectives and the wider One City Climate and Ecological Emergency strategies. Consider how the proposal creates environmental impacts in the following categories, both now and in the future. Reasonable efforts should be made to quantify stated benefit or adverse impacts wherever possible.
Where the proposal is likely to have a beneficial impact, consider what actions would enhance those impacts. Where the proposal is likely to have a harmful impact, consider whether actions would mitigate these impacts.
Enhancements or mitigation actions are only required when there is a likely impact identified. Remember that where enhancements or mitigation actions are listed, they should be assigned to staff and appropriately resourced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.