That Cabinet: 1. Approved the Temple Quarter Development Framework at Appendix A, that will help facilitate the delivery of the Temple Quarter Regeneration Programme and note that the Framework will become a material planning consideration. 2. Noted the outcome of the Temple Quarter Development Framework consultation, full report included at Appendix B. 3. Noted the update and progress on the Temple Quarter Programme including grant funding, the Temple Island Enabling Works, the Northern Entrance and Southern Gateway Project. 4. Noted ongoing work taking place in relation to the Temple Quarter Delivery Vehicle and that a further update on this will be provided to Cabinet in Autumn 2023.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Windmill Hill, Lawrence Hill, Southville and Central. Author: Lowri Hughson-Smith Job title: Senior Project Manager Cabinet lead: Mayor Executive Director lead: John Smith, Interim Executive Director Growth and Regeneration Proposal origin: Mayor Decision maker: Mayor Decision forum: Cabinet Purpose of Report:
To present the Temple Quarter Development Framework to Cabinet for endorsement. The Temple Quarter Development Framework sets out the vision for Temple Quarter and will help facilitate the delivery of the programme. If endorsed, will become a material planning consideration in the determination of planning applications promoted in the Temple Quarter regeneration area.
A wider Temple Quarter programme update is also provided to update Cabinet on key projects and workstreams, including an update on the Temple Island Enabling Works project.
1. Temple Quarter Development Framework
Background On the 7 November 2017, approval was given for the receipt and use of grant funding to support the delivery of a Development Framework for Temple Quarter. The Development Framework was commissioned by the Temple Quarter Joint Delivery Team on behalf of Bristol City Council, Network Rail, Homes England and West of England Combined Authority to reflect the combined aspirations and objectives of these parties through evidence-based proposals for the future development of the area.
From the Summer of 2018, Mott MacDonald led a consultant team to progress the Framework to provide a new, holistic vision for Bristol Temple Quarter. The Framework examines and reimagines the use of the area, responding to the needs and aspirations of the city and West of England region.
Planning Policy Context The Bristol Local Plan Review (July 2019) set out draft strategic planning policies for the Temple Quarter and St Philip’s Marsh areas. Those were subject to consultation in March 2019 and the feedback has been published. For Bristol Temple Quarter the draft policies are an update to the policies in the adopted local plan (Bristol Central Area Plan Policy BCAP35) and set out the vision for a new city quarter with a wide range of uses. At St Philip’s Marsh, the draft policies propose redesignating this area from a Principal Industrial and Warehousing Area (Site Allocations and Development Management Policy DM13) to an area of growth and regeneration. The Bristol Local Plan Review is on- going and will be subject to its own consultation and separate report to Cabinet. The Development Framework aligns with emerging Local Plan policies.
1 Version April 2021 Purpose of the Development Framework The purpose of the Development Framework is to set out the vision for Temple Quarter, as well as provide guidance and influence future developments that come forward in the Temple Quarter Area and, subject to Cabinet endorsement, would be a material planning consideration in the determination of planning applications. It is anticipated that the Temple Quarter Development Framework will be the basis of further planning policy and guidance documents in the future and will be used to guide decisions on planning applications. Any future documents will be subject to public consultation.
Development Framework Summary The emerging Framework seeks to identify opportunities for the future and proposes a set of principles and concept designs to guide their development. A place-making approach has been adopted throughout to embed sustainable and inclusive urban design principles with people at the centre. A degree of flexibility has been incorporated to create a framework with clear objectives while still being responsive to new information and direction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.