Bus Deal - Strategic Corridors update

Noted Executive 6 papers

Cabinet noted this item on Tuesday 2 May 2023. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That Cabinet: 1. Noted the previous Cabinet approvals on 5 October 2021 and the revised approach as outlined in this report. 2. Authorised the Executive Director Growth and Regeneration, in consultation with the Cabinet Member Transport, to take all steps required to accept and spend additional WECA funding to complete Business Cases for the Strategic Corridors Programme, including procuring and awarding appropriate contracts (which may be over the key decision threshold), up to a total expenditure of £6.5m. 3. Authorised the Executive Director Growth and Regeneration, in consultation with the Cabinet Member Transport, to proceed with separate full business case development for the central and southern sections of the A37/A4018 corridor and to continue with the development of the OBC for the whole corridor. 4. Noted the consultation details and responses as outlined in Appendix A1 and B.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 02 May 2023

TITLE Bus Deal - Strategic Corridors update

Ward(s) Citywide Author: Pete Woodhouse Job title: Transport Strategy Manager Cabinet lead: Cllr Donald Alexander, Cabinet Executive Director lead: John Smith, Interim Executive Director Member Transport Growth and Regeneration Proposal origin: Mayor Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:

1. To approve the receipt and expenditure of additional funding to deliver the development and submission to WECA of Business Cases for projects in the Strategic Corridors Programme, of up to £3.0m. 2. To seek approval of a revised approach to the delivery of the A37/A4018 corridor scheme to accelerate the project and deliver benefits earlier.

Evidence Base:

1. A report was taken to Cabinet on 5 October 2021 to secure approval for the development of business cases for projects within the Bus Deal/Strategic Corridors Programme. As stated in that report, the development of the Strategic Corridors Programme brings together a number of strands of local and national policies and plans. The Programme builds on the adopted City Centre Framework to focus on providing high levels of bus priority, segregation or operation in low traffic streets. These aspirations feature strongly in both the adopted West of England Combined Authority (WECA) Bus Strategy and Bus Back Better, the National Bus Strategy for England.

2. These routes will be designed to provide a high degree of segregation, either on dedicated infrastructure or running freely with traffic. In principle this will seek to deliver high quality rapid transit. Through Bus Back Better, the Government sought to engage with local authorities with ambitious rapid transit proposals. The Strategic Corridors were subsequently included in the successful bid submitted by WECA for funding under the City Region Sustainable Transport Settlement (CRSTS).

3. In line with the requirements of funding from the West of England Combined Authority, business cases for our schemes will include engagement, options assessment, economic assessment, consultation and detailed design. These are being delivered with in house expertise, engagement of the Strategic Partner and through procurement of consultant support for some elements. Each project’s scheme design and business case will be presented to Cabinet for approval before submission.

4. At Cabinet on 5 October, approval was given to receive and spend funding on the delivery of Business Cases for the Strategic Corridor projects. This approval was for spending up to £3.5m, the estimated amount to complete relevant business cases.

1 Version April 2021 5. Following further development of these schemes, additional funding is required to complete the business cases, and approval is sought for this additional funding amount. The Strategic Corridors Programme is funded by WECA entirely through CRSTS. Changes to funding requirements are managed through agreed change control processes at WECA.

6. WECA is in the process of making an Enhanced Partnership Scheme (EPS) aimed at developing and improving bus services in the region. The EPS includes a process by which benefits to bus operators of our bus corridor schemes are evaluated to negotiate correspondent bus operator reinvestment into services, such as providing increased frequency.

7. The projects within the Strategic Corridors programme have been progressing since the previous Cabinet report. In most cases, the scale and complexity of the projects has changed and resulted in additional funding requirements to complete the business case process. The requested additional funds are contained within the nominal overall budget for each project with the CRSTS programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A37.A4018 Public Consultation ReportAppendix A 4 MB Download
PDF
A37.A4018 Victoria Street Colston AvenueAppendix A2 1.7 MB Download
PDF
A37.A4018 south section proposalsAppendix A3 24 KB Download
PDF
Equality Impact Assessment: Bus Deal.Strategic Corridors update March 2023.FINALAppendix E 201 KB Download
PDF
Eco Impact Assessment: Strategic Corridors update.May2023Appendix F 86 KB Download
PDF
Bus Deal: Strategic Corridors updateReport 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
MR
Marvin ReesCommittee Member, present
DA
Councillor Donald AlexanderCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, apologies
KD
Councillor Kye DuddCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
HS
Hannah SmithCouncil Staff, expected
SC
Sarah ChodkiewiczCouncil Staff, expected
RL
Ravi LakhaniCouncil Staff, expected

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Bus Deal - Strategic Corridors updateThis decision
  2. Bus Deal - Strategic Corridors updateApproved
  3. Bristol Bus Deal UpdateAgreed

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies