Resolved
That Cabinet 1. Noted the current strategic risks and mitigating actions being taken to reduce to within tolerance
Cabinet noted this item on Tuesday 23 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet 1. Noted the current strategic risks and mitigating actions being taken to reduce to within tolerance
Decision Pathway – Report
PURPOSE: For reference
MEETING: Cabinet
DATE: 23 January 2024
TITLE Corporate Risk Management Report – Q3 2023/24
Ward(s) City wide Author: Joachim Adenusi Job title: Senior Risk and Insurance Officer Cabinet lead: Cllr C Cheney - Deputy Mayor and Executive Director lead: Stephen Peacock - Chief Executive Cabinet member for City Economy, Finance and (Head of Paid Service) Performance Proposal origin: BCC Staff Decision maker: For noting Decision forum: For noting Purpose of Report: The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2022-2027 and summarises progress in managing the risks and actions being taken as at Quarter 3_2023-24. Evidence Base: Context 1. The Corporate Risk Report (CRR) is a key document in the council’s approach to the management of risk; it captures strategic risks set out in the Corporate Strategy 2022-2027. It also provides a context through which Directorates construct their own high-level risk assessments and is used to inform decision making about business planning, budget setting, transformation, and service delivery.
2. The CRR provides assurance to management and Members that Bristol City Council’s significant risks have been identified and arrangements are in place to manage those risks within the tolerance levels agreed. It should be noted that ‘risk’ by definition includes both threats and opportunities, which is reflected in the CRR.
3. The Accounts and Audit Regulations 2015 require that the council to have in place effective arrangements for the management of risk. These arrangements are reviewed each year and reported as part of the Annual Governance Statement (AGS). Ensuring that the Service Risk Registers (SRR), Directorate Risk Reports (DRR) and the Corporate Risk Reports (CRR) are soundly based will help the council to ensure it is anticipating and managing key risks to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
4. The registers and reports are a management tool. They need regular review to ensure that the occurrence of obstacles or events that may put individual’s safety at harm, impact upon service delivery and the council’s reputation are minimised, opportunities are maximised and when risks happen, they are managed effectively to minimise the impact.
5. The CRR summary of risks is attached to this report at Appendix A and is the latest position following a review by managers and Directors. The risks in Appendix A are presented in the order of severity, starting with the highest scoring risks followed by lower scoring risks.
Summary of Corporate Risks: 6. Cabinet members are asked to note the CRR as a working summary report of the critical and significant risks from the Service Risk Registers as of December 2023.
1 Version December 2023 7. The CRR sets out the critical, significant, and high rated threats and opportunity risks. All other business risks reside on the Service Risk Registers.
8. Further programme of work with clear instructions to colleagues was undertaken to review and revise each CRR/DRR risk description, internal controls and mitigation plans and governance. The scope of this work included where possible the identification of new risks and a fresh look to confirm ongoing risks are current along with the actions to mitigate the risks.
9. Members of EDM’s reviewed the current CRRs and the DRRs in November/December 2023 to form the current CRR risks was reviewed by CLB on the 19th of December 2023. Cabinet members are asked to accept the attached CRR as a working summary report of the critical and significant risks from the Service Risk Registers.
10. The Q3 23-24 Corporate Risk Report (CRR) as at December 2023 contained:
Threat Risks Opportunity Risks External / Contingency Risks 1 Critical 25 High 1 High 1 High 5 Medium 2 Medium
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q3 2023_24 Corporate Risk Report1Appendix A1 | 778 KB | Download |
PDF |
Static Risks Q3 2023_24 Corporate Risk ReportAppendix A2 | 162 KB | Download |
PDF |
Risks Scoring 20 to 28 but not in Corporate Risk Register Q3 2023Appendix A3 | 94 KB | Download |
PDF |
Q3 Corporate Risk Report 2023/24Report | 181 KB | DownloadRead as text |
Follow Cabinet at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2024 | Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... | Decided | Open |
| 9 Apr 2024 | Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... | Approved | Open |
| 9 Apr 2024 | Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... | Noted | Open |
| 9 Apr 2024 | TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... | Approved | Open |
| 9 Apr 2024 | Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.