That Cabinet: 1. Noted the submission of the transport funding bid submitted in partnership with South Gloucestershire Council Contractual: 2. Authorised the Executive Director for Growth and Regeneration in consultation with the s151 Officer and the Cabinet Member for Transport to take all steps required to accept and spend the funding including to procure and award the contract(s) to undertake safety improvements on the A432 Bristol as outlined in this report. 3. Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report. 4. Authorised the Head of Strategic Procurement & Supplier Relations to approve appropriate procurement routes to market where these are not yet fully defined in this report, or if changes to procurement routes are subsequently required.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Frome Vale, Eastville, Easton, Lawrence Hill Author: Jacob Pryor Job title: Transport Policy, Bidding and Strategic Projects Team Manager Cabinet lead: Cllr Donald Alexander, Cabinet Executive Director lead: John Smith, Interim Executive Director Member for Transport Growth and Regeneration Proposal origin: Other Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:
1. To note the bid for transport funding with the bid partner South Gloucestershire Council and to seek approval to accept and spend the funding. Appendix I (exempt).
2. To delegate authority to the Executive Director for Growth and Regeneration in consultation with the s151 officer and Cabinet Member for Transport to receive funding and implement the scheme including entering into any necessary contracts and legal agreements and arrangements with our bid partner South Gloucestershire Council.
Evidence Base:
1. The A432 is a major distributor route which runs from Bristol city centre to Old Sodbury in South Gloucestershire – a length of approximately 22km.
2. Between 1 August 2020 and 1 August 2023 there have been 140 collisions on this section of the A432, comprised of 1 fatal, 11 serious and 128 slight collisions. This resulted in 149 casualties including 1 fatal, 6 serious and 26 slight pedestrian casualties, and 3 serious and 32 slight cycle casualties.
3. The bid includes an 8.8km section of the A432 starting at the intersection with the A4174 in South Gloucestershire and heading south-west through three busy shopping areas of Downend, Fishponds and Easton. The northern 3.4 kilometres lie within South Gloucestershire with the remainder in the City of Bristol.
4. The Bristol section is predominantly 20mph with some sections of 30mph. It includes sections of both peak hour and 24 hour bus lanes. The South Gloucestershire section is all 30mph and includes lengths of cycle lane (mostly southbound).
5. The Bristol and South Gloucestershire A432 scheme is based on introducing speed reducing measures and improving pedestrian crossing facilities which will help to improve active travel by reducing the risk to pedestrians and cyclists.
1 Version May 2023 6. Bristol’s section focuses on introducing raised speed tables at several of its existing pedestrian crossing locations, hard strips to reprofile running lanes and improvements to signing and lining.
7. The proposed scheme is expected to have the main benefit of preventing 65.8 fatal and serious injuries over the 20-year appraisal period, a 30.8% reduction compared with the baseline figure of 213.8 without intervention. This will realise an expected saving of £35,834.333 for the community over the 20-year period, resulting in an overall road safety BCR of 17.81.
8. The Bristol section of the scheme will be delivered using the BCC Highways and Associated Works Framework 2021-2025. The total scheme value sits within LOT 6 of the contract, Highways and Associated Works over £150,000, within which approved contractors would be invited to tender bids and undergo a mini competition. Contractors have been through a strict procurement and selection process before being appointed to the framework through the authority’s relevant governance procedures and will be appointed based on a combination of price, social value and quality through the mini competition.
Cabinet Member / Officer Recommendations:
That cabinet:
1. Notes the submission of the transport funding bid submitted in partnership with South Gloucestershire Council
Contractual:
2. Authorises the Executive Director for Growth and Regeneration in consultation with the s151 Officer and the Cabinet Member for Transport to take all steps required to accept and spend the funding including to procure and award the contract(s) to undertake safety improvements on the A432 Bristol as outlined in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.