Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew Cut bridges gets £2m now, £6m in February 2027
Money£8m in total£2m for bridges, £6m other areas delayed
What happens nextFebruary 2027 committeeAllocate remaining £6m at next meeting
Who it affectsRoads, bridges, buses, lightingMaintenance programmes and public transport
What was decided
Approved £2m of Clean Air Zone funding for the New Cut bridges project to complete repairs on nine bridges, including the Vauxhall Bridge refurbishment. Report P9, P20
Approved in principle the allocation of the remaining £6m to preventative maintenance programmes and public transport improvements, subject to further work and committee approval. Report P8, P11, P20
Delayed the spending of the £6m until further committee approval in February 2027, and authorised the Executive Director of Growth and Regeneration to procure and award contracts for the bridges work within the maximum budget. Report P13, P20
Why
The New Cut bridges project needs £2m more because the scope grew from six to nine bridges and over 80% of Vauxhall Bridge required replacement rather than demolition. Report P9
Finance raised concerns about pressures on Clean Air Zone income, including Joint Air Quality Unit fees doubling in 2026 and a trend of CAZ income reducing faster than expected. Report P7, P32, P33
There is ongoing uncertainty in the wider City Region Sustainable Transport Settlements programme budget, with construction cost pressures linked to conflict in the Middle East. Report P12, P16
What happens next
A further paper will come to the Transport and Connectivity Committee on 4 February 2027 to finalise allocation of the £6m for maintenance and public transport. Report P13
Officers will continue developing public transport proposals with the West of England Mayoral Combined Authority and operators, including bus frequency, fares, and a new orbital route. Report P11, P14, P15
A solar lighting trial in alleys and unlit areas is expected to start in September, integrated with the city's street lighting control system. Report P10
The money
£10m Original Clean Air Zone match funding allocated by Cabinet in January 2024 Report P2, P4
£2m Already allocated during February 2026 CRSTS rebaselining to bridge repairs, contingency, Union St match, and A38S bus operations Report P4
£1.82m Temporarily allocated to East Bristol Liveable Neighbourhood Full Business Case pending a change request Report P4
£8m Remaining Clean Air Zone funding under consideration in this report Report P4
£2m Approved for the New Cut bridges project to complete the programme Report P9, P20
£16m Existing New Cut bridges allocation from the CRSTS Challenge Fund Report P9
£750k Proposed additional funding towards completing the citywide gully cleansing project Report P9
£1.5m Existing capital allocation for 2026/27 carriageway patching following heavy rain Report P9
£750k Proposed additional funding for larger carriageway patch repairs of 10m2 or more Report P9
£200k Proposed uplift to the annual Public Right of Way and safer routes to schools budget from £100k Report P10
£500k Outstanding Public Right of Way schemes currently being designed Report P10
£300k Proposed funding for a new solar lighting trial in alleys and unlit areas Report P10
£4m Proposed allocation to public transport options, including frequencies, fares, and a new orbital route Report P11
Options considered
Chosen: Approve £2m for New Cut bridges now and delay the remaining £6m until February 2027 for further development. Addresses the immediate bridge funding pressure while leaving time to manage CAZ income risks and firm up other proposals Report P20
Rejected: Retain all funds as contingency or match funding for the CRSTS programme as per the January 2024 Cabinet approval. Would delay reinvestment if no further contingency is needed Report P17
Rejected: Allocate all £8m for spending immediately. Uncertainty over CRSTS projects could leave the council needing to find alternative funding, likely through prudential borrowing Report P17
Implications
Financial: Joint Air Quality Unit fees for managing the Clean Air Zone are set to double in 2026, and CAZ income is reducing faster than expected, creating pressure on available funds. Report P7, P32
Risk: Ongoing conflict in the Middle East may push up construction costs, and wider CRSTS programme budgets remain uncertain. Report P12, P16
Legal: Procurement must follow the Procurement Act 2023 and the council's own procurement rules, with legal services supporting the process. Report P35
Equalities: Construction may create negative environmental and equalities impacts that will need to be considered and mitigated through scheme-specific Equalities Impact Assessments. Report P23
Other: Works will be procured through the Highways Asset Management and Civils Framework 25-29, which carries social value requirements. Report P23
Climate: Investment is described as critical to the council's decarbonisation and transport strategies by improving sustainable travel options. Report P23
Who and where
Bus passengers across Bristol, who could see higher frequencies, lower fares, or a new orbital route Report P11
Users of the New Cut bridges, including pedestrians, cyclists, and motorists Report P9
Motorists affected by extensive carriageway damage after heavy rain in early 2026 Report P9
Residents and school children using Public Rights of Way and routes to schools Report P10
People in areas with no street lighting, particularly in alleys flagged as safety issues Report P10
Residents citywide benefiting from the gully cleansing and drainage programme Report P9
Council finances, given the pressure on Clean Air Zone income Report P32
Timeline
January 2024: Cabinet allocated £10m of Clean Air Zone income to support the CRSTS programme as match funding Report P2
February 2026: CRSTS programme re-baselined and approved by the West of England Mayoral Combined Authority; proposal to use CAZ funding for Park St was rejected by committee Report P2
12 February 2026: Full Council committed to bringing forward alternative plans for the Clean Air Zone funding Report P2
May 2026: Finance, Legal, IT, and HR comments finalised on the report Report P34, P36, P38, P40
September (year implied 2026): Trial of new solar lighting in alleys and unlit areas expected to begin Report P10
Post December 2026: Greater clarity expected on CRSTS programme outturn costs to inform the remaining allocation Report P12
4 February 2027: Next Transport and Connectivity Committee meeting to allocate the remaining £6m and seek approval for any reallocations Report P13
Plain English for the jargon
CAZ: Clean Air Zone, the Bristol charging zone whose income is being allocated
CRSTS: City Region Sustainable Transport Settlements, a funded transport programme covering Bristol and the West of England
JAQU: Joint Air Quality Unit, the government body that manages Clean Air Zone services and fees
MCA: West of England Mayoral Combined Authority, which approves the CRSTS programme
PROW: Public Right of Way, such as footpaths and bridleways
EBLN: East Bristol Liveable Neighbourhood, a programme temporarily using £1.82m of CAZ funding pending a change request
FBC: Full Business Case, the detailed case required for major scheme funding
S106: Section 106 planning obligation contributions from developers, used here as an alternative match funding source
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
That the Committee for Transport and Connectivity: 1. Approved the allocation of £2m of funding to the New Cut bridges project to enable delivery of the remainder of the programme as per projects detailed in Appendix A 2. Approved the allocation of the remaining £6m funding to the general areas set out in paragraphs 2, 4 and 5 to enable further works to firm up those proposals in consultation with committee members 3. Approved the delay to spending the £6m funding until further committee approval is given in February 2027 following consideration of the wider CRSTS programme budget 4. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport & Connectivity Committee and Section 151 officer to take all steps required to procure and award contracts and invest the funding to deliver the works to the New Cut bridges project as set out in paragraph 3a up to the maximum budget envelope outlined in this report. 5. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee and Section 151 officer to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report for the new cut bridges project.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To set out options for allocating Clean Air Zone (CAZ) income currently allocated to supporting the City Region Sustainable Transport Settlements (CRSTS) programme and seek approval for spending those allocations.
2. In January 2024, Cabinet allocated £10m of CAZ income to support the CRSTS programme. This funding was to be used as match funding. Other sources of match, notably S106, were found which enabled this funding to be retained as a contingency for the programme. When the CRSTS programme was re-baselined in February 2026, and approved by the West of England Mayoral Combined Authority (MCA), a proposal was brought forward to use CAZ match funding in part to support the delivery of the Park St scheme. Committee rejected this proposal. Subsequently, at February Budget Full Council a commitment was made to bring forward plans for alternative use of this funding. This paper will summarise latest position on forecast CAZ income and set out options for utilisation of CAZ income and proposals for allocating available funding.
Evidence Base
1. The allocation agreed by Cabinet in January 2024 was £10m. As part of the rebaselining process £2m was allocated to cover various items including increased costs on Sparke Evans Bridge repairs, a programme wide contingency, match funding for Union St and funding to facilitate bus operations on the A38S project. £1.82m of this £2m funding was temporarily allocated to East Bristol Liveable Neighbourhood (EBLN) to facilitate completion of the Full Business Case (FBC) until the change request, currently with the MCA, is resolved. The remaining £8m is the focus of this report.
Template approved October 25
OFFICIAL 2. While committee declined to take forward the Park St scheme, we still await a view from the government on our air quality position and potential actions to achieve compliance and it is possible that CAZ funding may be required to deliver further interventions should BCC be instructed to do so
3. Extract from Finance comments below in this report: “it is important to acknowledge the pressures and risks that have impacted the CAZ funding that might limit the funds available. More specifically, Bristol City Council was notified by the Joint Air Quality Unit (JAQU) that their fees for the management of the CAZ service, will double in 2026, which is expected to put a significant pressure on the CAZ funds….. Therefore, Finance’s advice is to review the ask in accordance with all these known and emerging pressures, to avoid overprogramming and ensure we will not have funding constrains that we will be unable to manage, once in delivery. Recommendation is to not commit to the full £8 million and a follow up report to be brought to the Committee to allow the Members to make an informed decision on the allocation of funds.”
4. CAZ funding can be allocated to maintenance as it can enable better walking and cycling options through improved surfaces and reduced flooding etc. Previously suggested options such as the cleansing and lining in the budget amendments are currently being actioned and funded by the amendment to bring forward the already agreed CAZ maintenance funding. The full city drainage cleanse project has started and the lining crews have increased to 4 across the city. Maintenance funds are proposed to be allocated in 2 distinct packages:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.