That Cabinet: 1. Approved the submission of a bid for £5.2m of CRSTS LN funding to WECA and, if successful, to use the funding to complete the eight schemes detailed in this report and Appendix A. 2. Authorised the Executive Director Growth and Regeneration, in consultation with the Cabinet Member for Transport, and S151 Officer, to take all steps required to submit the bid (including the provision of a full business case to WECA) and if successful, to accept and spend the funding to procure and award the contract(s) necessary for the implementation of the eight schemes, in-line with the procurement routes and maximum budget envelopes outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Using City Regional Sustainable Transport Settlement (CRSTS) Liveable Neighbourhood funding to complete Streetspace and related schemes Ward(s) Ashley, Central, Clifton, Clifton Down, Easton, Eastville Author: Steve Riley Job title: Programme Manager Cabinet lead: Cllr Don Alexander, Cabinet Member Executive Director lead: Stephen Peacock, Executive Director for Transport Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To seek approval for £5.2m of City Regional Sustainable Transport Settlement (CRSTS) Liveable Neighbourhood (LN) funding to be used to complete five Streetspace Active Travel Fund (ATF) schemes and three schemes of a very similar type that have emerged through other projects. Evidence Base:
The Emergency Active Travel Fund (EATF), as it was in May 2020, provided funding for schemes responding to the Covid-19 pandemic such as pavement widening at The Triangle and temporary cycles lanes on Counterslip and Lewins Mead. As the funding evolved, and dropped the ‘emergency’ title, it was used to deliver trial phases of well-known and popular schemes such as the closure of Cotham Hill and part pedestrianisation of the Old City.
However, when the Active Travel Fund (ATF) money ended in March 2022, five schemes had been worked on but had not been completed. Many of these schemes have developed to a high level, including being in place under an ETRO or having good local support, but do not have sufficient funding to be completed. Because all of these schemes involve a reallocation of traffic movements in some way or another, it is logical that they use of a proportion of the CRSTS Liveable Neighbourhood (LN) funding that has not yet been applied to an identified scheme(s). Alongside these schemes, a further three that have come about from development through other funding streams are now seeking a budget to complete their construction phase.
A full description of each scheme and the overall situation is provided in Appendix A. In summary, there are eight schemes that could be completed to a high quality with the use of just under £5.2m of CRSTS (City Region Sustainable Transport Settlement) Liveable Neighbourhood (LN) funding: 1. Princess Victoria Street. Engage with local residents and businesses to seek ideas to integrate in making the timed road closure look and feel more permanent. £124-550k (Do Min to Do More). 2. Overton Road. Provide a road closure to encourage sustainable transport and place making by Gloucester Road. £204k. 3. Rosemary Lane. Provide a road closure to encourage sustainable transport through a green area on the route to the local primary school. £237-650k (Do Min to Do More). 4. Denmark Street. Engage with local businesses to seek ideas to make the timed road closure look and feel more permanent. £650k. 5. Chandos Road. Provide a road closure to encourage sustainable transport and place making as sought (and trialled) by local residents and businesses. £650k.
1 Version Feb 2022 6. Old City-King Street. Construct the scheme that has already had an OBC approved by WECA but has missed the funding window. £1.7m. 7. Cotham Hill. Provide the full amount of funding for the highly popular scheme that it was thought had been agreed with Active Travel England. £295k. 8. St Mark’s Road. Provide a contribution for cycling improvements to a project being progressed by City Design and Highway Maintenance. £10k.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.