Upgrade of electrical power supplies on the Amphitheatre Event space
ApprovedCommittee4 papers
Transport & Connectivity Policy Committee approved this item on Thursday 11 July 2024. Below is the council's own wording, with the papers it was decided on.
The Committee RESOLVED (unanimously): 1. To approve the spend of the allocated capital funding of £800k to upgrade electrical power supplies and improve electrical installations on the Amphitheatre Event site as outlined in the report. 2. To authorise the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Policy Committee to procure and award the contract to deliver the proposals, in line with the procurement routes and maximum budget envelopes outlined in the report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
To seek approval to accept and spend capital funding to install a power supply and electrical equipment that will enable all outdoor events to operate on the Amphitheatre site safely and to reduce the reliance on the need to use air polluting generators.
Evidence Base:
1. The Amphitheatre is an established outdoor event site on the Harbourside. The area is designed for this purpose as part of the Lloyd Bank HQ development in 1991.
2. The current electrical infrastructure in use on the Amphitheatre has been subject to periodic repair and maintenance to ensure its safety and reliability and the HSE have recommended the electrical supply is upgraded as a matter of urgency to comply with the Electricity at Works Act. At a recent test and inspection of the electrical installation, the installation failed and subsequently required remedial works, which have been implemented, but only as a temporary solution. The Electricity at Works Act is a legal statutory requirement when installing, maintaining, and upgrading electrical Infrastructure. Failure to comply with this statutory requirement can lead to improvement notices, prohibition notices and prosecution. If this electricity supply is not upgraded, it will undoubtedly have to be isolated, locked off and removed.
3. For the reasons outlined above, the site requires significant investment in the event electrical
1 Version January 2024 installations to ensure the electrical supply remains fit for purpose for years to come significantly reducing reliance on generators and importantly compliance with the statutory regulations this electrical installation is subject to.
4. As an indication of the spaces purpose, use, social, economic, and environmental impact: Events scheduled to take place on the Amphitheatre this year:
i. Host 12 events, including our commissioned events (Harbour Festival and Bristol Run) ii. Events take place across 30 live event days iii. Combined daily licensed capacity for these events is over 86,000 people iv. These events use an estimated 83,902 kwhs of electricity per year v. Equivalent generator power uses an estimated 25,424 litres of diesel, creating 63,136kgs of CO2 vi. Annual economic impact from events in the amphitheatre is estimated to be around £2.75m vii. BCC generates around £60,000 per year in income from amphitheatre site fees.
5. Currently the power supply and electrical installations on the site do not offer the required capacity to run or facilitate larger music, food, cultural events and festivals without the provision of diesel generators to increase the level of power on-site to that required to deliver these events.
6. Diesel generators are polluting, generating particulate and nitrogen dioxide pollution that is harmful to health. They also generate CO2 emissions which are damaging to the environment and in the long term, to public health.
7. Many people are encouraged to spend time at events in locations where air pollution should be relatively good as they are away from roads. However, the diesel generators can impact significantly on-air pollution levels.
8. Bristol City Council will be able to secure renewably generated electricity to make the electricity supply zero carbon.
9. A charge will be levied on the power supplied, which will be lower than the cost of diesel generated power, but high enough to raise an income to maintain the infrastructure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.