Resolved
The Committee
Transport & Connectivity Policy Committee decided this item on Thursday 11 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee
1. The Council Revenue and Capital budget for 2024/25 was agreed by Full Council on 21 February 2023. This report presents to the Transport and Connectivity Committee the transport financial forecast at period 2 / quarter 1 against the budget as at the end of May 2024. Evidence Base:
2. The Transport function is divided between Highways and Traffic within the Management of Place division, City Transport within Economy of Place. City Transport includes both Strategic City Transport and Local and Sustainable Transport.
3. General Fund
Revenue Budget Monitor
Revised Forecast Outturn Budget Outturn Variance P02 (£14.9m) (£14.9m) £0.0m
May Jun Jul Aug Sept Oct Nov Dec Jan Feb 0.0 Position by Division
1 Version January 2024 % Revised Revised Quarter 1/ Period 2 Budget Approved Revised Budget vs Forecast Budget vs Monitoring - Summary Budget Budget Forecast Forecast Variance Variance £'000 £'000 £'000 £'000 % Transport and Connectivity 46 - Economy of Place 100 (20) (20) 0 0.0% 47 - Management of Place (12,783) (15,035) (15,035) (0) 0.0% 4B - Property, Assets and Infrastructure 120 120 120 0 0.0% Total Transport and Connectivity (12,563) (14,935) (14,935) (0) 0.0%
Position by Service
% Revised Revised Period 2/ Quarter 1 Budget Approved Revised Budget vs Forecast Budget vs Monitoring - Summary Budget Budget Forecast Forecast Variance Variance £'000 £'000 £'000 £'000 % Transport and Connectivity 433 - Strategic City Transport 1,773 1,773 1,773 0 0.0% 434 – Local & Sustainable Transport (1,673) (1,794) (1,794) 0 0.0% 432 – Highways and Traffic (12,783) (15,035) (15,035) 0 0.0% Maintenance 444 – Major Projects 120 120 120 0 0.0% Total Transport and Connectivity (12,563) (14,935) (14,935) (0) 0.0%
3.1For revenue, the Transport and Connectivity committee is reporting a breakeven position against a revised budget of (£14.9) million. The tables above show those budgets by Directorate and Service.
3.2At P2 there is a forecast £3.8 million overspend for Growth and Regeneration driven by the costs of providing accommodation to those experiencing homelessness. Both Strategic Transport and Highways and Traffic Maintenance have contributed opportunities to offset risk within the wider directorate and hold the overspend to that level and will be required to deliver more in order to achieve a balanced budget across the directorate cash limit.
3.3The table below shows latest delivery against savings within this Committee.
2 Version January 2024 Savings Delivery
3.4The largest revenue challenge within these two areas is delivering increasing income targets. The Council Revenue and Capital budget for 2024/25 included policy that income targets would, in general, be increased by 6.7% (representing the 2023/24 rate of inflation). For parking incomes this equated to an increase of just over £1 million, which is particularly challenging given there was a deficit against previous income targets in 2023/24. Proposals are being developed to increase parking income through adjusting multi-story and residential parking scheme tariffs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2023-24 P12 Finance Outturn ReportReport | 317 KB | DownloadRead as text |
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... | Approved | Open |
| 17 Sep 2026 | Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... | Decided | Open |
| 17 Sep 2026 | Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... | Agreed | Open |
| 17 Sep 2026 | Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. | Noted | Open |
| 17 Sep 2026 | 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.