Transport and Connectivity Policy Committee approved £819,785 for the Denmark Street closure scheme and accepted £2,354,677.92 of regional funding to install 28 bus stops on the A4 Bristol to Bath corridor. It noted £1.359m extra for the Portway and reallocations to East and South Bristol Liveable Neighbourhoods within the £179.31m transport settlement.
What the committee will consider, in order, with every paper attached to its item. Streetspace 2: Denmark St and Rosemary Lane is the main business.
To note any declarations of interest from councillors. They are asked to indicate the relevant agenda item, the nature of the interest and in particular whether it is a disclosable pecuniary interest. Any declaration of interest made at the meeting which is not on the register of interests should be notified to the Monitoring Officer for inclusion.
To receive any announcements from the Chair.
Decision: Decision Notices have been published on the Council’s website. The East Bristol Liveable Neighbourhood data pack, along with the associated survey results, has been published since the last meeting. The statutory consultation on proposed changes to the Residents’ Parking Schemes has concluded. Proposals relating to the number and cost of visitor permits will be paused to allow further consideration of the feedback received. Other proposed changes — including charges for business e?vehicles and... Decision page
Up to 30 minutes is allowed for this item. Any member of the public or councillor may participate in . items must relate to the remit of the committee and should be addressed to the Chair of the committee. Members of the public who plan to attend a public meeting at City Hall are advised that you will be required to sign in when you arrive. Please note that you will be issued with a visitor pass which you will need...
To present to the Transport and Connectivity Committee Bristol Council’s progress made towards the key themes raised in the Inclusive Transport Vision, produced by the Bristol Climate and Nature Partnership, as well as future direction towards them.
Decision: That the Committee for Transport and Connectivity 1. Endorsed the continued work towards fulfilling aims outlined within the Inclusive Transport Vision, as part of the Golden Motion to make Bristol the UK’s most accessible city. 2. Noted City Transport’s progress towards implementing the recommendations within the report. 3. Endorsed the commitment to report back in December 2026 on further progress made. This recommendation was supported by the Committee Chair. Decision page
This report sets out the current position of the City Region Sustainable Transport Settlement (CRSTS) programme referencing the recent rebaselining exercise undertaken by the West of England Mayoral Combined Authority and the Bristol City Council input into that process. The Park St Triangle scheme is funded through other funding streams to reduce pressure on the programme and approval is also sought for that...
Decision: That the Committee for Transport and Connectivity: Regarding CRSTS Rebaseline 1. Noted the contents of the CRSTS Rebaseline Change Request (Appendices A1 and A2, paras 1-9) and associated documents as submitted to the Combined Authority including changes to budget allocations and project/programme completion dates 2. Noted further papers will come to the Transport and Connectivity Committee seeking approval for full business cases and associated budget allocations for South Bristol Liveable... Decision page
To seek approval to submit the Full Business Case (FBC) for Streetspace 2: Denmark Street and Rosemary Lane. To seek approval to accept and spend funding for Streetspace 2 and to award any contracts required to construct the approved schemes
Decision: The Transport & Connectivity Policy Committee: 1. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to submit the FBC for Denmark Street to WECA and accept and spend the funding should it be approved, in-line with the procurement routes and maximum budget envelope outlined in the report. 2. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and... Decision page
To seek approval to accept funding from WECA for the early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC) and seek approval to procure and award contracts for the scheme, in line with the necessary procurement routes and maximum budget envelopes outlined in this report and conditional on WECA’s confirmation to proceed following receipt of market pricing.
Decision: The Committee for Transport and Connectivity: 1. Accepted the funding from WECA for the Early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC), noting that WECA have confirmed that there is no financial risk to BCC resulting from an overspend. 2. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to procure and award all necessary contracts and to spend the funding associated with the ‘Early... Decision page
To update Transport & Connectivity (T&C) Committee on the latest quarterly performance measures – with a focus on Tier 1 measures (including Business Plan metrics and actions) plus selected Tier 2 metrics.
Decision: The Transport and Connectivity Committee noted the Performance progress report. Decision page
The report provides an update on current significant strategic risks, relevant to the Transport and Connectivity Committee, to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q3 2025-26.
Decision: The Transport and Connectivity Committee noted the report. Decision page
The Council Revenue and Capital budget for 2025/26 was agreed by Full Council on 25 February 2025. This report presents to the Transport and Connectivity Committee the financial forecast at Period 8 (P8) against the budget as at the end of November 2025.
Decision: The Committee for Transport and Connectivity noted the contents of the report on the P8 forecast. </AI11> <TRAILER_SECTION> Decision page
Item 9 is where most of this meeting's papers sit: 6 papers, about 16 MB.
To seek approval to submit the Full Business Case (FBC) for Streetspace 2: Denmark Street and Rosemary Lane. To seek approval to accept and spend funding for Streetspace 2 and to award any contracts required to construct the approved schemes
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 29 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 11 September 2025. 5 of its items lead into this meeting; 5 items are new. Point at any item to follow a thread. Procedural items are left out.
Road Safety Task and Finish Group, Active Travel Fund tranche 5 and 6 bid, Avon Fixed Bridge, Policy Committee Work Programme Setting - Outcome Report do not return this time.
See the 11 September meetingEvery Transport & Connectivity Policy Committee meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Bristol, Transport & Connectivity Policy Committee
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Transport & Connectivity Policy Committee, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.