Early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC)

Decided Committee 3 papers

AI summaryBristol City Council accepts WECA funding of £2,354,677.92 to install 28 early-works bus stops on routes 5 and 36 along the A4 Bristol to Bath corridor, with the Executive Director authorised to procure and award contracts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedExecutive Director to procure and award all contracts
Money£2,354,677.92 capitalFunded by WECA's CRSTS1 allocation, no financial risk to BCC
What happens nextProcure contracts and awardIn consultation with the Committee Chair, within budget envelopes
Who it affects28 bus stops on A4 routesRoutes 5 and 36 between Bristol and Bath

What was decided

The Committee accepted £2,354,677.92 of WECA funding for the early delivery bus stop scheme on the A4 Bristol to Bath Strategic Corridor, noting WECA has confirmed no financial risk to Bristol City Council from any overspend. Report P3, P30

The Executive Director for Growth and Regeneration was authorised, in consultation with the Chair of the Transport and Connectivity Committee, to procure and award all necessary contracts and spend the funding within the maximum budget envelopes set out in the report. Report P4

Why

The 28 bus stops need to be installed before the main Bristol to Bath Strategic Corridor works to reduce the risk of abortive works, and Bristol City Council has the capacity and existing framework to deliver them quickly. Report P1

The scheme supports the council's Corporate Strategy priorities of inclusive and sustainable growth, climate and environmental sustainability, healthy and connected communities, and innovation and efficiency. Report P5, P6, P7, P8, P9

What happens next

The Executive Director will procure and award contracts under the Procurement Act 2023 and the council's own procurement rules, with legal services preparing the contract documentation. Report P34

Officers must get written confirmation from WECA before starting any work that all costs will be fully recovered, and any overspend must be agreed by the joint BBSC project team and funded only from WECA's CRSTS allocation. Report P30

Public engagement will take place as part of the statutory process for bus stop upgrades, including Traffic Regulation Orders and planning permissions where needed, plus letter drops to residents and properties near each affected stop. Report P22, P23

The money

  • £2,354,677.92 Total capital cost of the early delivery bus stop scheme Report P26
  • £2.355 million Capital spend approved for delivery of 28 bus stops on routes 5 and 36 Report P28
  • £1.625 million Estimated base cost of the bus stop works Report P28
  • £0.730 million Risk and optimism bias provision within the budget Report P28
  • £45% Risk pot as a share of the estimated base cost Report P28

Options considered

  • Chosen: Bristol City Council accepts the funding and procures the works through its own framework, as recommended by officers. Council has the capacity to deliver, and using the council's framework avoids the long timeframes of WECA running a separate procurement Report P1, P3, P4
  • Rejected: WECA leads the installation of the early works bus stops. Required providers are not on WECA's framework, which would vastly increase delivery timeframes and risk abortive overlap with the main corridor works Report P1

Implications

  • Financial: WECA has confirmed there is no financial risk to Bristol City Council from any overspend, and the council will only spend within limits confirmed by WECA. Report P30
  • Financial: External risks such as market price volatility, contractor availability, design changes after consultation and unforeseen groundworks must be covered by project contingencies and managed with WECA. Report P32
  • Legal: Contracts must be procured under the Procurement Act 2023 and the council's own procurement rules, with legal services preparing the documentation. Report P34
  • Equalities: Shelters and concrete pads will improve accessibility for passengers with mobility challenges, older adults, and parents with children, and reduce barriers for communities reliant on public transport. Report P12
  • Climate: The scheme is designed to encourage a shift from private car use to public transport and active travel, supporting carbon reduction and better air quality. Report P7, P15, P16
  • Staffing: Officers advise there are no direct HR implications from the recommendations. Report P37

Who and where

  • Bus passengers on routes 5 and 36 along the A4 between Bristol and Bath Report P28
  • Residents and properties directly affected by the proposed bus stop adjustments, who will receive a letter drop Report P23
  • Passengers with mobility challenges, older adults, parents with children, and disadvantaged communities reliant on public transport Report P12
  • Local contractors and suppliers involved in delivering the works Report P18

Timeline

  • 28 November 2025: Head of Human Resources confirmed there are no direct HR implications Report P38
  • 2 December 2025: Legal Services confirmed contracts must comply with the Procurement Act 2023 Report P35
  • 10 December 2025: Lead Enterprise Architect confirmed IT work would be handled through the existing work request process with the CCTV and BNET team Report P36
  • January 2026: Discussions scheduled with Bristol City Council Engineering Design team on delivery timelines and resource allocation Report P21
  • 15 January 2026: Finance Business Partner signed off the financial advice on the capital spend Report P33
  • 5 February 2026: Transport and Connectivity Policy Committee took the decision to accept funding and authorise procurement

Plain English for the jargon

  • WECA: West of England Combined Authority, the regional body providing the funding
  • CRSTS: City Region Sustainable Transport Settlement, the government funding stream WECA is using
  • BBSC: Bristol to Bath Strategic Corridor, the wider A4 transport improvement scheme
  • BCC: Bristol City Council
  • TRO: Traffic Regulation Order, the legal order needed to change road traffic restrictions
  • BNET: Bristol's own council network, mentioned in relation to CCTV coordination
  • QA3: Quality assurance process being used by design partner AECOM
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

The Committee for Transport and Connectivity: 1. Accepted the funding from WECA for the Early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC), noting that WECA have confirmed that there is no financial risk to BCC resulting from an overspend. 2. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to procure and award all necessary contracts and to spend the funding associated with the ‘Early Works Bus Stops on BBSC’ project in-line with the maximum budget envelopes outlined in the report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Committee Report

KEY DECISION OR FOR INFORMATION: Key decision over £500k

COMMITTEE: Transport and Connectivity Committee

DATE: 05 February 2026

TITLE: Early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC)

Ward(s): Brislington East, Brislington West and Stockwood.

Officer presenting the report: Adam Crowther Job title: Head of City Transport

Committee Chair: Cllr Plowden

Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: 1. To seek approval to accept funding from WECA for the early delivery bus stop scheme - A4 Bristol to Bath Strategic Corridor (BBSC) 2. To seek approval to procure and award contracts for the scheme, in line with the necessary procurement routes and maximum budget envelopes outlined in this report and conditional on WECA’s confirmation to proceed following receipt of market pricing.

Evidence Base:

This report sets out the approach for delivering improvements to 28 bus stop locations along and around the A4 Bristol to Bath Strategic Corridor (BBSC), selected through an evidence-based process to ensure they are aligned with the wider transport programme. The stops chosen, as shown on the plan below, are used by the 5 and 36 bus services that use the A4 corridors for part of their routes but more importantly serve significant residential areas either side of it. By making these changes now, it is anticipated that users will have been encouraged to use these partially supported services and therefore provide larger benefits more quickly when the A4 corridor improvements are put in place. With only three stops on the A4 itself, it is being ensured that these works will not inhibit, or be disrupted by, the larger changes planned for the corridor itself.

Template approved October 25

OFFICIAL Closer view of x28 bus stop locations:

Template approved October 25

OFFICIAL Template approved October 25

OFFICIAL Template approved October 25

OFFICIAL List of 28 Bus Stops

Bus Route Bus Stop Number Name Stockwood Road 36 2 Southbound Stockwood Road 36 3 Northbound Brislington Square 36 8 Eastbound Hungerford Crescent 36 16 Northbound Hungerford Crescent 36 17 Southbound West Town Lane 36 18 Southbound 36 33 Church Parade West Town Park 36 42 Westbound West Town Park Bus 36 58 Stops Eastbound West Town Lane 36 61 Northbound The Rock 36 72 Southbound The Rock 36 73 Northbound Collin Road 36 78 Southbound Collin Road 36 79 Northbound Sunnydene 36 80 Northbound Sherwell Road 36 85 Eastbound Sherwell Road 36 86 Westbound Sunnydene 36 87 Southbound Arlington Road 5 and 36 89 Westbound Chapel Way/St 5 and 36 91 Anne's Road Eastbound

Template approved October 25

OFFICIAL Chapel Way/St 5 and 36 92 Anne's Road Westbound Wootton Crescent 5 and 36 93 Eastbound Wootton Crescent 5 and 36 94 Westbound Guildford Road 5 and 36 95 Northbound Guildford Road 5 and 36 96 Southbound

The bus stops are located along the 5 and 36 bus routes. The impetus of early delivery of these stops is to improve the quality of the 36 which has limited funding. This is with the aim of the improving the attractiveness of the route by making the stops higher quality, with the aim of improving ridership and making it more likely the 36 is commercially viable after the subsidized funding period is over.

The proposals use established and standardised, accessible design standards supported by a comprehensive Equalities Impact Assessment and incorporate features that promote sustainability and biodiversity where feasible. These enhancements will improve passenger experience, address local concerns, such as the provision of bins, and support inclusive travel. Following initial engagement, the next stage will involve consultation with frontages and individual stakeholders to ensure local needs are fully considered before implementation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment: early delivery bus stop schemeAppendix B 541 KB Download
PDF
Environmental Impact Assessment: Jan26Appendix C 295 KB Download
PDF
Early delivery bus stop scheme: A4 Bristol to Bath Strategic Corridor (BBSC)Report 832 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
EP
Councillor Ed PlowdenChair, present
GM
Councillor Graham MorrisVice-Chair, apologies
RB
Councillor Rob BryherCommittee Member, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present
JS
John SmithOfficer, expected
PM
Patsy MellorOfficer, expected
AH
Alex HearnOfficer, expected

All 16 on the meeting page

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies