AI summaryBristol City Council's Transport Committee approved the Denmark Street closure scheme and authorised submitting its Full Business Case to WECA, with a budget of £819,785.00, but did not approve the related Rosemary Lane pocket park scheme.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFBC and procurement approved for Denmark Street only
Money£819,785.00 (Denmark Street)Forecast cost for Denmark Street scheme
What happens nextSubmit FBC to WECA, procure contractsFor Denmark Street only, within maximum budget envelope
Who it affectsDenmark Street businesses and residentsIncluding Bristol Hippodrome and the local BID
What was decided
The committee authorised the Executive Director of Growth and Regeneration to submit the Full Business Case for Denmark Street to the West of England Combined Authority and accept and spend the funding if approved.
The committee authorised officers to take all steps required to procure and award any contracts needed to construct the Denmark Street scheme, up to the maximum budget envelope in the report.
The committee did not approve the equivalent recommendations to submit a Full Business Case for Rosemary Lane or to procure and award contracts for the Rosemary Lane scheme.
Why
Officers advised against not progressing the schemes, citing support from local businesses and residents and improved safety for pedestrians and cyclists. Report P25
The Denmark Street scheme is intended to stop traffic cutting through and enhance public safety, with the Business Improvement District and the Bristol Hippodrome consulted on access for HGV deliveries. Report P12, P13
Proposals link to the council's Corporate Strategy priority of making it easier, greener and safer to travel into and around Bristol. Report P30
What happens next
Officers will amend the Full Business Case to split it into two schemes and seek change approval from WECA on how the project is administered and funded. Report P3
A street lighting assessment will be carried out, and potential CCTV coverage explored, to improve safety on Denmark Street. Report P14
Further work with WECIL will look at improved accessibility from Frog Lane car park to Frogmore and Denmark Street, with revised parking for disabled bays on Gaunt's Lane to be included in the next set of designs. Report P15
The money
£819,785.00 Forecast cost of Denmark Street scheme Report P12
£480,215 Forecast cost of Rosemary Lane scheme Report P8
£1.3 million Notional capital allocation for the project Report P37, P41
£750,000 Approximate notional allocation for Denmark Street Report P41
£550,000 Approximate notional allocation for Rosemary Lane Report P41
£161k Spent to date on development costs (as authorised by Cabinet, 24 January 2023) Report P7
£180,000 Spent to date on development costs (per finance advice) Report P41
£224,800 Total development costs incurred on the project Report P41
£900,000 Estimated civils work as the main delivery cost Report P41
£153,000 Overall contingency allowance, approximately 13% Report P41
Options considered
Chosen: Progress the schemes as proposed. Support from local businesses and residents, and improvement in safety for pedestrians and cyclists Report P25
Rejected: Do not progress the schemes. Officers advised against this given support and safety benefits Report P25
Implications
Financial: Funded through the City Region Sustainable Transport Settlement with no council match funding proposed; WECA already approved a Grant Agreement for development costs in May 2023. Report P41
Legal: Procurement must be carried out in line with the Procurement Act 2023 and the council's own procurement rules, with legal services advising officers. Report P43
Equalities: A meeting with WECIL on 18 December reviewed the Denmark Street designs for disability access; suggested improvements including dropped kerbs, tactiles and disabled parking revisions on Gaunt's Lane will be included in construction designs. Report P15
Climate: The schemes are expected to contribute to the city's aspiration to be carbon neutral, improve air quality, and support more active and healthy travel. Report P32
Risk: The schemes are treated as low-risk transport schemes and so do not require a Benefit-Cost Ratio assessment. Report P16
The local Business Improvement District (BID) and businesses on Denmark Street Report P13, P14
WECIL (West of England Centre for Inclusive Living) Report P15
Residents and pupils near May Park Primary School (Rosemary Lane proposal, not approved) Report P8
Residents in Easton and Eastville wards (Rosemary Lane consultation area) Report P9
Timeline
24 January 2023: Cabinet authorised development costs for the project Report P7
22 January to 3 March 2024: Rosemary Lane consultation took place Report P34
June 2024: Local ward councillor meeting held to discuss Rosemary Lane consultation results Report P10
18 December: Meeting held with WECIL to review Denmark Street designs for disability access Report P15
22 August to 6 October 2025: Further business and public consultation for Denmark Street completed Report P34
5 February 2026: Transport and Connectivity Policy Committee considered the decision
Plain English for the jargon
FBC: Full Business Case, the detailed funding submission sent to WECA
WECA: West of England Combined Authority, the body providing the CRSTS funding
CRSTS: City Region Sustainable Transport Settlement, a government programme for sustainable transport
BID: Business Improvement District, a group of local businesses working together on the area
WECIL: West of England Centre for Inclusive Living, a disability rights organisation
QA3 designs: Quality Assurance stage 3 designs, a more developed design stage used before construction
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
The Transport & Connectivity Policy Committee: 1. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to submit the FBC for Denmark Street to WECA and accept and spend the funding should it be approved, in-line with the procurement routes and maximum budget envelope outlined in the report. 2. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to take all steps required to procure and award any contracts required to construct the approved Denmark Street scheme, including any contracts over the key decision threshold , and to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in the report. Recommendations 1 and 3 as outlined in the report were not approved: 1. Authorises the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to submit the FBC for Rosemary Lane to WECA and accept and spend the funding should it be approved, in-line with the procurement routes and maximum budget envelope outlined in this report. 3. Authorises the Executive Director of Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to take all steps required to procure and award any contracts required to construct the approved Rosemary Lane scheme, including any contracts over the key decision threshold , and to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To seek approval to submit the Full Business Case (FBC) for Streetspace 2: Denmark Street and Rosemary Lane 2. To seek approval to accept and spend funding for Streetspace 2 3. To seek approval to award any contracts required to construct the approved schemes
Evidence Base
1. This project has been established as one project containing two geographically distinct schemes that have one Grant Offer Letter from the West of England Combined Authority (WECA) which is expecting one FBC. However, the recommendations of this report have been written to allow the two schemes to be approved separately. If this decision is made, officers will amend the FBC to divide it into two and seek change approval from WECA as to how the scheme is administered and funded.
2. The City Region Sustainable Transport Settlement (CRSTS) programme is designed to deliver wide-ranging sustainable transport benefits across England’s city regions. Increased active travel, improved climate and air quality benefits, inclusive growth, network efficiency and road safety.
3. Among these schemes have been some small-scale restrictions of motorised traffic to improve and make safer the environment for active travel while also providing improved scope for hospitality businesses with outside space. To ensure a quicker route to delivering such small schemes, the proposals for Rosemary Lane and Denmark Street have been combined into one workstream, by both BCC and WECA, requiring just one business case. These two schemes therefore follow Princess Victoria Street and Overton Road in this
Template approved March 25
OFFICIAL respect. This project has spent £161k to date on development costs as authorised by Cabinet on 24 January 2023.
4. Rosemary Lane – The proposal is to implement a pocket park on Rosemary Lane to encourage sustainable transport on the route to May Park Primary School and stop traffic short cutting on small residential streets to make the area safer for residents and children going to school. This scheme using QA3 designs is forecast to cost £480,215.
5. Following consultation on the closure of Rosemary Lane, responses were 45/55% split between support and opposition (responses from Easton and Eastville wards only). This further analysis showed residents living in the area supported the closure, while many objections came from people outside the area, who may ultimately be using the road as a through route.
6. A local ward councillor meeting was held in June 2024 to discuss these results and to decide how to proceed. It was agreed that after reviewing the consultation report that the benefits of reducing through traffic, improving safety and enhancing local environment outweigh the potential drawbacks.
7. We will be carrying out a street lighting assessment to make improvements for safety and potentially any CCTV coverage.
8. Denmark Street – The proposal is to implement a full closure on Denmark Street to stop traffic cutting through and aim to enhance public safety. This scheme, using QA3 designs, is forecast to cost £819,785.00
9. We have worked closely with the Business Improvement District (BID) and local stakeholders and businesses in the area to fully understand what is essential for the businesses to successfully trade on Denmark Street. We have worked closely with Bristol Hippodrome and ensured they will always have access for HGV deliveries.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.