Bristol City Council
Transport & Connectivity Policy Committee, Thursday 5 February 2026 at 5.00pm

City Regional Sustainable Transport Settlement Update

Noted Committee 6 papers

AI summaryBristol Transport Committee approves CRSTS programme rebaseline with scope cuts to four schemes, Portway budget rise of £1.359m, and temporary reallocations to East and South Bristol Liveable Neighbourhoods.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPortway budget raised, schemes reduced, kiosks authorised
Money£179.31m total CRSTS programmePlus £13.3m for Park St/Triangle from other funds
What happens nextNot stated
Who it affectsFour CRSTS schemes reduced in scopeBroadmead/Union St, Redcliffe Roundabout, Bedminster Bridges, Portway

What was decided

The committee approved scope reductions for the Broadmead/Union St, Redcliffe Roundabout, Bedminster Bridges and Portway Main Corridor schemes, and approved reallocating unused funds to cover any reduced scope where budget allows. Report P9

The committee approved a £1.359m increase to the Portway Main Corridor scheme, taking its budget to £23.1m, and approved temporary allocations of £1.82m of CAZ CRSTS match and £0.6m of CAZ Local Transport funding to East Bristol Liveable Neighbourhood pending an MCA change request. Report P9, P10

The committee approved a £1.32m increase to South Bristol Liveable Neighbourhood, raising its allocation from £0.6m to £1.92m to complete the full business case, plus a temporary £0.57m of CAZ Local Transport funding if needed. Report P10

Why

The changes follow a rebaselining exercise by the West of England Mayoral Combined Authority; the council could not secure further funding to cover original scope, so removed scope will largely be paused for future projects. Report P2, P25

Officers say the Park St/Triangle scheme is needed to meet the legal requirement to achieve nitrogen dioxide compliance in the shortest possible time and by 2027, otherwise the council is unlikely to comply until 2028 to 2029. Report P4, P34

What happens next

The Executive Director for Growth and Regeneration, with the committee chair, is authorised to secure vacant possession of a further kiosk on Merchant Street and to take procurement and contract award steps for the Park St/Triangle scheme within the budget envelope. Report P9, P12

Further papers will come to the committee seeking approval of full business cases and budget allocations for South Bristol Liveable Neighbourhood, East Bristol Liveable Neighbourhood, Streetspace 2, Concorde Way, WP4, WP5 and the Regional Cycling Hub when ready. Report P9

The committee noted that the A4018/A37 WP3 full business case no longer needs Combined Authority approval because the remainder of the scheme will be funded by Financial Assistance Scheme and Clean Air Zone income. Report P12, P27

The money

  • £1.359m Increase to Portway Main Corridor scheme budget Report P9
  • £23.1m New Portway Main Corridor scheme budget Report P9
  • £1.82m Temporary CAZ CRSTS match funding for East Bristol Liveable Neighbourhood Report P10
  • £0.6m Temporary CAZ Local Transport funding for East Bristol Liveable Neighbourhood Report P10
  • £1.32m Increase to South Bristol Liveable Neighbourhood allocation Report P10
  • £0.57m Temporary CAZ Local Transport funding for South Bristol Liveable Neighbourhood if needed Report P10
  • £179.31m Updated total CRSTS programme Report P26, P21
  • £36.1m CRSTS match funding (25%) Report P26
  • £5.3m FAS funding for bus gate elements of Park St/Triangle scheme Report P12, P27
  • £1.04m CRSTS grant for WP3 early works already in delivery Report P27
  • £0.6m Existing SBLN allocation before increase Report P10
  • £1.92m New SBLN allocation after increase Report P10

Options considered

  • Rejected: Withdraw projects in full from the CRSTS programme. Would reduce benefits and risk revenue reversion on developed projects Report P2
  • Rejected: Seek further funding to cover removed scope. No further funding could be secured; removed scope will largely be paused for future projects Report P2
  • Rejected: Do not deliver Park St scheme. Would breach air quality Direction compliance duty and risk legal challenge; around £1m revenue reversion risk Report P4
  • Rejected: Peak hour bus gates 7am-10am and 4pm-7pm weekdays only. Peak traffic only 30-35% of total; insufficient air quality benefit; off-peak and weekend benefits lost Report P4, P6
  • Rejected: 12 hour bus gates 7am-7pm every day. Air quality compliance by 2027 at significant risk; benefits reduced after 7pm; signage less clear Report P6

Implications

  • Financial: Total CRSTS programme revised to £179.31m with £36.1m match funding, including £19.2m Economic Development Fund, £12.8m section 106, £3.5m historic land receipt and £0.7m CAZ operational surplus. Report P26
  • Financial: WP3 A4018/A37 removed from CRSTS except £1.04m of early works, with delivery using £5.3m reappropriated CAZ Financial Assistance Scheme funding and about £8m CAZ operational surplus. Report P27
  • Legal: Procurement must follow the Procurement Act 2023 and the council's own procurement rules. Report P33
  • Legal: The Air Quality Direction 2021 requires the council to achieve NO2 compliance in the shortest possible time; the Park St/Triangle scheme is needed to meet compliance by 2027, otherwise 2028-29 is anticipated. Report P34
  • Legal: The Secretary of State could issue further Directions if legislative powers are available; the Office of Environmental Protection is monitoring progress on roadside NO2 exceedance. Report P35, P36
  • Equalities: All projects covered have individual Equality Impact Assessments which are updated regularly and where scope changes are proposed have been provided and updated. Report P44
  • Climate: Infrastructure improvements are intended to encourage modal shift from cars to public transport, walking and cycling, reducing congestion and vehicle emissions. Report P14
  • Risk: Officers note a potential revenue reversion of around £1m if the Park St scheme were not delivered, and that a minimum of 24-hour bus gates provides clearer signage and better compliance. Report P4, P6

Who and where

  • Pedestrians and cyclists, especially at weekends and between peaks, who would lose benefits under shorter bus gate operating hours Report P4, P6
  • Residents and businesses in Broadmead/Union St, Redcliffe Roundabout, Bedminster Bridges and Portway corridors where scheme scope is reduced Report P9
  • East Bristol and South Bristol communities served by the Liveable Neighbourhoods programmes Report P9, P10
  • Merchant Street kiosk occupier(s), as further vacant possession is being sought Report P9
  • West of England Mayoral Combined Authority, which must resolve change requests for EBLN and SBLN funding Report P10, P29, P30

Timeline

  • December 2021: Original Cabinet decisions on the programme Report P21
  • 23 January 2024: Cabinet consideration of Clean Air Zone evaluation and net proceeds application Report P21
  • February 2025: Earlier Transport and Connectivity Committee approval to begin procurement for the Park St/Triangle scheme Report P12
  • October 2025: Joint West of England Combined Authority and Joint Committee meeting on the rebaselining exercise Report P21
  • 2026-02-05: Committee approval of CRSTS rebaseline, scope reductions, budget changes and Park St/Triangle funding approach
  • By 2027: Target date for NO2 legal limit compliance if Park St/Triangle scheme is delivered Report P34
  • 2028 to 2029: Anticipated compliance date if Park St/Triangle scheme is not brought forward and no alternative is identified Report P34

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a Department for Transport capital funding programme for major transport schemes, delivered locally through the West of England Mayoral Combined Authority.
  • MCA / WECA: West of England Mayoral Combined Authority, the regional body overseeing CRSTS and other strategic transport funding.
  • CAZ: Clean Air Zone, a Bristol charging zone established to reduce roadside nitrogen dioxide concentrations, with surplus income used to support transport schemes.
  • FAS: Financial Assistance Scheme, funding linked to the Clean Air Zone used to support affected road users and here reappropriated to deliver bus gate elements.
  • WP3 / WP4 / WP5: Work Packages 3, 4 and 5 within the A4018/A37 Stockwood to Henbury Strategic Corridor scheme.
  • SBLN / EBLN: South Bristol and East Bristol Liveable Neighbourhoods, programmes aimed at improving streets for walking, cycling and public transport.
  • FBC: Full Business Case, the detailed document required before a major scheme can be approved and funded.
  • NO2: Nitrogen dioxide, the pollutant covered by the Air Quality Direction 2021 requiring Bristol to achieve compliance with legal limit values.
  • JAQU: Joint Air Quality Unit, the government body overseeing local authority compliance with air quality directions.
  • OEP: Office for Environmental Protection, the body that has received a complaint on continued exceedance of NO2 legal limits.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the Committee for Transport and Connectivity: Regarding CRSTS Rebaseline 1. Noted the contents of the CRSTS Rebaseline Change Request (Appendices A1 and A2, paras 1-9) and associated documents as submitted to the Combined Authority including changes to budget allocations and project/programme completion dates 2. Noted further papers will come to the Transport and Connectivity Committee seeking approval for full business cases and associated budget allocations for South Bristol Liveable Neighbourhood, East Bristol Liveable Neighbourhood, Streetspace 2, Concorde Way, WP4, WP5 and the Regional Cycling Hub when ready. See paragraphs 7e and 7f of the report. For Decision 3. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to take all steps required to secure vacant possession of a further kiosk on Merchant St as per paragraph 11 of the report. 4. Approved an increase to the budget for the Portway Main Corridor scheme of £1.359m to £23.1m as set out in paragraph 7b of the report. 5. Approved the proposed scope reductions for the Broadmead/Union St scheme as set out in the report, paragraph 7a and Appendices A1 and A2. 6. Approved the proposed scope reductions for the Redcliffe Roundabout scheme as set out in Appendices A1 and A2 of the report. 7. Approved the proposed scope reductions for the Bedminster Bridges scheme as set out in Appendices A1 and A2 of the report. 8. Approved the proposed scope reductions for the Portway Main Corridor scheme as set out in Appendices A1 and A2 of the report. 9. Approved reallocation of unused funds to cover any scope reduced as above should budget be available Regarding EBLN 10. Approved the temporary allocation to EBLN of £1.82m of the £10m CAZ CRSTS match funding and £0.6m of £10m CAZ Local Transport funding until the EBLN change request is resolved with the MCA as set out in paragraph 7e of the report. Regarding SBLN 11. Approved a £1.32m increase to the current allocation for SBLN from £0.6m to £1.92m to enable completion of the FBC as set out in paragraph 7f of the report and the temporary allocation of £0.57m of CAZ Local Transport funding should this be needed. Regarding Bus Route 2 WP3/Park St/Triangle Noting only 12. Noted that committee approved the submission of a Full Business Case for A4018/A37 WP3 to the West of England Mayoral Combined Authority (MCA) but that, as the remainder of the scheme will be funded by FAS and CAZ income, approval of the MCA is no longer required as per paragraph 12 of the report. 13. Noted the legal requirement for Bristol to achieve air quality compliance in the shortest time possible and the contribution of the Park St/Triangle Scheme to achieving this as per paragraphs 13-15 of the report. 14. Noted that approval to begin the procurement process was already given by Transport and Connectivity committee in February 2025 so no further approval is required here. Recommendations 15 to 20, with recommendation 21 added as ...
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Committee Report

KEY DECISION OR FOR INFORMATION: Key decision over £500k spend/save & impacts more than 2 wards

COMMITTEE: Transport and Connectivity Committee

DATE: 05 February 2026

TITLE: City Region Sustainable Transport Settlement Update

Ward(s): Citywide

Officer presenting the report: Adam Crowther Job title: Head of City Transport

Committee Chair: Councillor Ed Plowden

Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: This report sets out the current position of the City Region Sustainable Transport Settlement (CRSTS) programme referencing the recent rebaselining exercise undertaken by the West of England Mayoral Combined Authority and the Bristol City Council input into that process. The Park St Triangle scheme is funded through other funding streams to reduce pressure on the programme and approval is also sought for that approach.

Evidence Base

CRSTS Rebaseline:

1. The West of England Mayoral Combined Authority was required to set out a rebaselined CRSTS programme (2022-2027) to the Department for Transport. The budget envelope for this was set out in a report to the 17th October 2025 WECA Committee ((Public Pack)Agenda Document for Joint meeting - West of England Combined Authority Committee and West of England Joint Committee, 17/10/2025 13:00). As part of this process the MCA allocated £140.78m of Transforming City Regions funding (2027-2032) to increase the total budget allocated to CRSTS projects to £584.63m from £443.85m (of which £67.68m is match funding and £376.17m is DfT funding) 2. The increased budget was enabled by updated guidance issued by the DfT relating to the regional TCR allocation and how it could be allocated as well as revisions to the programme end date enabling extensions of time for CRSTS projects beyond the original March 2027 deadline up to March 2029. 3. The BCC allocation was set at £179.31m made up of £143.21m of DfT CRSTS funding and £36.1m of match funding 4. As a result of this process and allocation BCC was required to rebaseline its programme to set out budget allocations to each scheme and expected end dates Template approved October 25

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BCC CRSTS Prog Rebaselining CR V3 Jan 2026Appendix A1 167 KB Download
PDF
BCC CRSTS Delivery plan & change request v3 Jan 2026 BudgetsAppendix A2 226 KB Download
PDF
BCC CRSTS Delivery plan & change request v3 Jan 2026 MilestonesAppendix A2 125 KB Download
PDF
Park Street Air Quality Modelling resultsAppendix A3 98 KB Download
PDF
Air Quality Note: Park Street Re-routingAppendix A4 960 KB Download
PDF
City Regional Sustainable Transport Settlement UpdateReport 424 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
EP
Councillor Ed PlowdenChair, present
GM
Councillor Graham MorrisVice-Chair, apologies
RB
Councillor Rob BryherCommittee Member, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present
JS
John SmithOfficer, expected
PM
Patsy MellorOfficer, expected
AH
Alex HearnOfficer, expected

All 16 on the meeting page

On this subject at Bristol

Search all
  1. City Regional Sustainable Transport Settlement UpdateThis decision
  2. Using City Regional Sustainable Transport Settlement (CRSTS) Liveable Neighbourhood funding to complete Streetspace and related schemesApproved
  3. City Regional Sustainable Transport Settlement (CRSTS) 2022-27Noted

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies