Housing & Consumer Standards Programme and Compliance Update
NotedCommittee3 papers
AI summaryCommittee noted updates on the Housing Consumer Standards Programme, landlord compliance and the housing IT transformation. Overall programme status remains amber, with the new NEC system linked to around 20,000 reported outstanding repairs that are largely believed closed.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new decisions taken; programme updates only
MoneyNo new money in this decisionExisting Housing Investment Plan funding; 26/27 budget approval due 12 February 2026
What happens nextMilestone 2 sign-off reviewProgramme team reviewing completion in January and February 2026
Who it affectsBristol City Council housing tenantsAbout 14% of Bristol homes are owned and managed by the council
What was decided
The committee noted the Housing Consumer Standards Programme update, showing overall amber status with milestone two about 93% complete and milestone four green at the end of December 2025. Report 1.2, P6
The committee noted the landlord compliance report: communal gas 100%, electrical inspections 67%, asbestos re-inspections 98.5%, domestic gas 98.9%, smoke detection 72%, decent homes 72.8%, and around 20,000 reported outstanding response repairs. Report P21, P22, P23, P27
The committee also noted the Housing IT Transformation Programme update, residents voice feedback, the upcoming Competence and Conduct Standard, and the latest engagement with the Regulator of Social Housing. Report P54, 3.1, 3.3, 3.6, 5.1, P49
Why
Overall delivery status remains amber because of ongoing evaluation of milestone two and post go-live problems with the new NEC housing IT system, which has inflated the reported outstanding repairs figure. Report 1.3, 1.8, P23, 3.7
Landlord compliance performance has been affected by the transition to NEC and the new C365 system, leading to a temporary drop in reported smoke detection and response repairs data. Report P22, P23, P27
The Regulator of Social Housing last met the council on 15 January 2026 and the meeting covered IT systems, asbestos, damp and mould, electrical safety, and the stock condition survey programme. Report P49, 5.1
What happens next
The programme team will review milestone two completion in January and February 2026, with a full completion report going to the March 2026 HCSP Board and April 2026 Homes and Housing Delivery Committee. Report 1.6
A refreshed Housing IT Transformation Programme Business Case for the second stage is targeted for committee approval in April 2026, with full implementation estimated to complete by December 2026. Report 3.2, 3.9
A draft action plan for the new Competence and Conduct Standard, effective from October 2026, will be shared with the committee after approval by the HCSP Board.
The money
26/27 budget approval Anticipated on 12 February 2026 to fund the accelerated electrical inspection programme aiming for full compliance by April 2027 Report P21
Options considered
Chosen: Continue with amber status and review milestone two completion evidence in January and February 2026. To validate 93% completion before signing off milestone two Report 1.6
Chosen: Bring forward electrical inspection compliance to April 2027 via an accelerated programme. To meet new government five-year inspection cycle requirements due April 2026 Report P21
Chosen: Use C365 as a medium-term landlord compliance and reporting solution until NEC asset management is available in late 2026 or 2027. To bridge the gap while NEC modules are completed Report 3.4
Implications
Risk: New NEC housing IT system has post go-live issues affecting repairs logging, gas servicing visibility and the ability of some tenants to use one login for rent and housing applications. Report 1.8, 3.7, P23, P39
Staffing: Temporary staff are being used to manually review and close completed jobs, and a second stock condition survey contractor has been brought in to improve survey quality. Report P26, P47
Legal: Council must prepare for the new Competence and Conduct Standard effective from October 2026, covering skills, qualifications, codes of conduct and contractor competence. Report 5.1
Other: Around 14% of Bristol homes are owned and managed by the council, so programme delivery directly affects a significant share of households. Report P59, P60
Who and where
Bristol City Council tenants and leaseholders Report P59, P60, P63
Housing Scrutiny Panel and new Resident and Community Panel Report P47
Barton House residents and stakeholders involved in the lessons learnt review Report P47
Council staff in housing management, repairs, gas servicing and asset management teams Report 5.1, P22
October 2025: First stage of Housing IT Transformation Programme went live with NEC housing modules Report 3.3
End of December 2025: Latest reported position: milestone two about 93% complete, milestone four green Report 1.2
31 December 2025: Target completion date for milestone two of the Housing Consumer Standards Programme Report 1.2
January 2026: Housing Options module went live in NEC; service unavailable for 18 days during transition Report 3.6
13 January 2026: Housing Scrutiny Panel last met to discuss NEC challenges, response repairs and damp and mould Report P47
15 January 2026: Last regulatory engagement meeting with the Regulator of Social Housing Report P49
27 January 2026: Resident and Community Panel reviewed a draft resident engagement model Report P47
12 February 2026: Anticipated approval of the 26/27 budget, including the accelerated electrical inspection programme Report P21
March 2026: Full milestone two completion report due at the HCSP Board Report 1.6
April 2026: Milestone two report and refreshed Housing IT Transformation Programme Business Case due at committee Report 1.6, 3.2
October 2026: Competence and Conduct Standard takes effect Report 5.1
December 2026: Current estimate for full Housing IT Transformation Programme implementation completion Report 3.1
Plain English for the jargon
HCSP: Housing Consumer Standards Programme, the council's improvement programme responding to the Regulator of Social Housing judgement.
NEC: New housing IT system that went live in stages from October 2025, replacing legacy housing management and repairs systems.
C365: Asset management system introduced as a medium-term landlord compliance and reporting solution until full NEC asset management is available.
RSH: Regulator of Social Housing, the body that issued the July 2024 Regulatory Judgement on Bristol City Council.
HSP: Housing Scrutiny Panel, which provides resident and councillor oversight of the HCSP and service delivery.
HHDC: Homes and Housing Delivery Policy Committee, the council committee that received this report.
Awaab's Law: Legal requirements relating to hazards in social housing, referenced as a high-risk area in milestone two.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
The Committee RESOLVED : To note the Housing Consumer Standards Programme (HCSP) update (Appendix Ai). To note the latest landlord compliance performance report (Appendix Aii). To note the Housing IT Transformation Programme update. To note the resident’s voice actions and feedback from the Housing Scrutiny Panel (HSP). To note the upcoming Competence & Conduct Standard. To note the update from the latest regulatory review meetings with the Regulator of Social Housing (RSH).
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Homes and Housing Delivery Policy Committee
Purpose of report
1. To note and comment on the Housing Consumer Standards Programme (HCSP) update (Appendix Ai). 2. To note and comment on the latest landlord compliance performance report (Appendix Aii) 3. To note and comments on the Housing IT Transformation Programme update 4. To note and comment on the resident’s voice actions and feedback from the Housing Scrutiny Panel (HSP) 5. To note and comment on the update on the upcoming Competence & Conduct Standard 6. To note and comment on the update from the latest regulatory review meetings with the Regulator of Social Housing (RSH)
Evidence Base
1. HCSP Improvement Plan update summary – Appendix Ai
1.1The latest update summary included in appendix Ai outlines the end of December 2025 position of the HCSP. The ‘programme overview summary’ on slide 2 shows the overall programme status. The charts on pages 3-7 of appendix Ai illustrate the overall percentage progress against the tasks within milestones two to four and provides exception commentary on progress and any improvement plans.
1.2The charts show that overall progress against milestones two and three was ‘amber’ at the end of December 2025 with both milestones slightly behind target. However, solid progress continues to be made against the milestones. Milestone four has a ‘green’ status with all actions on target. Milestone 2 had a target completion date of 31 December 2025. The Template approved March 25
OFFICIAL December 2025 assessment of progress against milestone 2 suggests c.93% of activities have been completed. The programme team are currently reviewing completion evidence for milestone 2 activities to provide assurance on progress against the milestone. More information on what is included in milestone 2 and progress to date is provided in items 1.4 to 1.7.
1.3The overall programme delivery status remains at AMBER due to an ongoing evaluation of delivery against milestone 2 (see items 1.4 to 1.7) and the impact of ongoing work on resolving some post ‘go live’ NEC system issues. Further detail on the new housing IT system (NEC) challenges is explored in item 1.8 and section 3.
1.4In the strategy we set out the following ambition for the second phase of improvements (milestone 2 of the Housing Consumer Standards Improvement Strategy), to achieve the following: We have completed the high-risk actions associated with the failings identified in the Regulator of Social Housing’s Regulatory Judgement and can evidence consistent improvement in line with our improvement plans.
• Work is being delivered in line with the improvement plan, and our performance reporting is evidencing consistent improvement. • We have completed the actions that present the highest risk to residents and robust risk mitigation measures are in place for the lower risk actions. • An improved approach to resident engagement, that includes learning from and acting on resident feedback, is in place.
• We have made good progress against the ‘significant failures’ identified in the Regulator of Social Housing’s Regulatory Judgement. We are responding to the remaining weaknesses and can demonstrate the improvements to residents and the Regulator of Social Housing
How we would like residents to feel: The council is taking health and safety issues seriously and focusing on the highest risks first.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Housing Delivery Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.