AI summaryBristol's housing committee noted that milestone 2 of the Housing Consumer Standards Improvement Strategy is only partially complete, with the overall programme rated red due to compliance and data gaps.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOverall programme RAG rating is red
MoneyNot stated
What happens nextReviews scheduled March to May 2026Savills Consumer Standards review and lessons learnt session
Who it affectsCouncil housing tenants in BristolAround 14% of Bristol homes are owned and managed by the council

What was decided

The committee noted the status of milestone 2 of the Housing Consumer Standards Improvement Strategy, covering the work in sections 1 to 5 of the report. Report P5, P63

The committee noted the overall programme status update, including the red RAG rating and the position on milestones 3 and 4. Report 6.1, 6.2, P49

The committee noted the latest landlord compliance performance report covering areas such as gas, electrical, smoke detection and decent homes. Report 7.1, 7.2, P56

Why

The council received a C3 Regulatory Judgement from the Regulator of Social Housing in July 2024 and set up the Housing Consumer Standards Programme to become compliant with the consumer standards. Report P1, P74

The external critical friend Savills concluded that milestone 2 is partially achieved, with good progress on safety governance but limited assurance on fire door, smoke detection, damp and mould inspections and damp and mould remedial works for vulnerable tenants. Report P32, P33, P34, P35, 2.1

The Housing Scrutiny Panel felt the council is taking health and safety seriously but noted inefficiency in delivery and weak data management that limits the ability to evidence work done. Report P17, 2.3

What happens next

Services will re-assess the milestone 2 data position and evidence in March 2026, and Savills will carry out a Consumer Standards review in March and April 2026. Report 6.3

A Savills facilitated 'lessons learnt 12 months on' session, including a revisit of the root cause report, is planned for April 2026. Report 6.3

The HCS programme will review the status of milestone 2, the Consumer Standards review findings and the lessons learnt outcome in May 2026, and consider any re-baselining of the improvement plan. Report 6.3, 6.4

Implications

  • Legal: The council must prepare for compliance with Awaab's Law, made up of the Hazards in Social Housing (Prescribed Requirements) Regulations 2025 and the Social Housing (Regulation) Act 2023. Report P80
  • Risk: Programme RAG rating is red because milestone 2 is only partially complete, milestone 3 is behind target, NEC system post 'go live' issues are still being resolved, and the January 2026 landlord compliance report shows challenges in gas, smoke detection, repairs and decent homes. Report 6.2, P49, 7.2, P56, P57, P58, P59, P60
  • Staffing: David McNulty started as permanent Executive Director of Housing in March 2026 and will lead delivery and oversight of the key strategic actions needed for long term change. Report 6.4

Who and where

  • Tenants and leaseholders of Bristol City Council social housing Report P68, P69, P72
  • Bristol City Council Housing and Landlord Services teams Report 1.2, 1.4
  • The Housing Scrutiny Panel resident group Report P17, 2.3

Timeline

  • 9 July 2024: RSH Regulatory Judgement issued against Bristol City Council Report P74
  • End of October 2025: Milestone 1 of the Housing Consumer Standards Improvement Strategy completed Report P1
  • December 2025: Internal assessment found around 93% of milestone 2 activities completed Report 1.3
  • 30 December 2025: Target completion date for milestone 2 Report P1
  • March 2026: Services to re-assess milestone 2 data and evidence, and Savills Consumer Standards review to begin Report 6.3
  • 10 March 2026: HCSP Board and Housing Scrutiny Panel considered milestone 2 and agreed it is partially complete Report P5, P17, 2.3
  • April 2026: Remaining NEC post 'go live' issues expected to be fully resolved and Savills lessons learnt review to take place Report 6.2, 6.3
  • May 2026: Programme board to review milestone 2 status, Consumer Standards review and lessons learnt findings, and complete the Residents Voice strategy Report 6.3, P43
  • April 2027: Revised target date for completing electrical safety inspections programme Report 7.2

Plain English for the jargon

  • RSH: Regulator of Social Housing, the national regulator of registered providers of social housing in England
  • HCSP: Housing Consumer Standards Programme, the council's improvement programme responding to the RSH judgement
  • C3 judgement: The most serious RSH consumer grading, indicating significant failings and a need for the landlord to make major improvements
  • BAU: Business as usual, meaning an action is complete and is now managed through normal service operations
  • Awaab's Law: New legal duties on social landlords, set out in the Hazards in Social Housing (Prescribed Requirements) Regulations 2025 and the Social Housing (Regulation) Act 2023, requiring prompt action on hazards such as damp and mould
  • HITT programme: Housing IT Transformation programme, a related programme that is implementing the NEC housing management system
  • FRA: Fire Risk Assessment, a required assessment of fire safety in blocks of flats
  • LOLER: Lifting Operations and Lifting Equipment Regulations, covering items such as passenger lifts
  • LGSR: Landlord Gas Safety Record, the annual gas safety check required in rented homes
  • HSP: Housing Scrutiny Panel, a resident group that reviews the council's housing improvement work
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

It was RESOLVED that the Committee for Homes and Housing Delivery: 1. Noted the status of the Housing Consumer Standards Improvement Strategy milestone 2 (see section 1 to 5) as set out in this report. 2. Noted the status update for the programme as a whole (see section 6). 3. Noted the latest landlord compliance performance report (see section 7).
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

In response to the Regulator of Social Housing’s (RSH) C3 Regulatory Judgement against the social housing consumer standards, the council has implemented the Housing Consumer Standards Improvement strategy that outlines how the council will become compliant with the RSH’s Consumer Standards. The strategy includes four key milestones. Milestone 1 was completed at the end of October 2025. Milestone 2 has a target completion date of 30 December 2025. This report considers whether milestone 2 has been achieved and summarises any outstanding or follow-on work required. The Housing Consumer Standards Strategy outlines what the council plans to achieve in milestone 2 and this is summarised below in italics:

Milestone 2 – We have completed the high-risk actions associated with the failings identified in the Regulator of Social Housing’s Regulatory Judgement and can evidence consistent improvement in line with our improvement plans.

• Work is being delivered in line with the improvement plan and our performance reporting is evidencing consistent improvement. • We have completed the actions that present the highest risk to residents and robust risk mitigation measures are in place for the lower risk actions. • An improved approach to resident engagement, that includes learning from and acting on resident feedback, is in place. • We have made good progress against the ‘significant failures’ identified in the Regulator of Social Housing’s Regulatory Judgement. We are responding to the remaining weaknesses and can demonstrate the improvements to residents and the Regulator of Social Housing.

How we would like residents to feel: The council is taking health and safety issues seriously and focusing on the highest risks first.

OFFICIAL On the 10 March 2026, the Housing Consumer Standards Programme (HCSP) Board considered progress against milestone 2 and agreed that the milestone is partially complete with some further work needed to fully satisfy the requirements. The Homes & Housing Delivery Committee (HHDC) is asked to consider and comment on this report that summarises progress achieved against milestone 2.

Section 6 summaries progress against the other Housing Consumer Standards Improvement Strategy milestones 3 and 4.

Background

Evidence base

1. Summary of milestone 2 progress and the action sign off quality assurance process

1.1A huge amount of work has been completed to respond to the milestone 2 actions. Below is a summary of progress achieved against the high-level objectives outlined within the Housing Consumer Standards Improvement Strategy (identified in bold text). The summaries are based on the findings provided by Savills as part of an external Stocktake of milestone 2 which is available in appendix Ai. An assessment on progress with the individual actions is summarised in item 1.2 and explored in more detail in sections 3-5. The status of each action has been given a RAG rating as outlined below.

Action status Key: Substantial Assurance – Task completed Partial Assurance - Task substantially complete with some work remaining and/or some evidence weaknesses Limited Assurance - Not completed and/or poor evidence provided

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Savills Milestone 2 Stocktake Report v2 (3) (1)Appendix Ai 429 KB Download
PDF
HCSP Highlight Report (Jan 26) (1)Appendix Aii 386 KB Download
PDF
Landlord Comp Report (Jan 26): HHDC (2)Appendix Aiii 701 KB Download
PDF
Housing & Consumer Standards Programme and Compliance UpdateReport 292 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
PG
Councillor Paul GogginCommittee Member, apologies
CG
Councillor Caroline GoochCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
AA
Councillor Al Al-MaghrabiCommittee Member, present as substitute
ST
Councillor Sibusiso TshabalalaCommittee Member, apologies
KB
Councillor Kerry BailesCommittee Member, present as substitute
DM
David McNultyOfficer, in attendance

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Housing & Consumer Standards Programme and Compliance UpdateThis decision
  2. Housing & Consumer Standards Programme and Compliance UpdateNoted
  3. Housing & Consumer Standards Programme and Compliance UpdateDecided
  4. Housing & Consumer Standards Programme and Compliance UpdateNoted
  5. Housing & Consumer Standards Programme and Compliance UpdateNoted
  6. Housing & Consumer Standards Programme and Compliance UpdateApproved

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Annual Cladding Remediation UpdateThe Committee Decided Open