Housing & Consumer Standards Programme and Compliance Update

Noted Committee 5 papers

AI summaryBristol City Council's Homes and Housing Delivery Committee noted six reports covering the Housing Consumer Standards Programme, with the programme remaining at RED status pending a re-assessment in May and June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgramme stays at RED status, awaiting reassessment
MoneyNot stated
What happens nextProgramme reassessment in May and June 2026Further update due to July 2026 committee
Who it affectsCouncil tenants in BristolFourteen percent of Bristol homes are council owned

What was decided

The committee noted the Housing Consumer Standards Programme update, which remains at RED status, mainly because some milestone two actions are only partially complete and milestones three and four are at AMBER. Report 1.1, 1.2, P7

The committee noted the external Consumer Standards Review by Savills, which found the council has significantly improved its housing service over the last two years but still has weaknesses in data, systems and capacity. Report 2.1, 2.3, 2.4

The committee noted the March 2026 landlord compliance figures, the residents voice update and the feedback from the most recent meeting with the Regulator of Social Housing. Report 4.1, 4.2, 5.1, 6.1

Why

The reports track progress against the Regulator of Social Housing's C3 judgement from July 2024 and the council's self-referral. Report 2.1, P78

The committee is being asked to note progress so it can comment on the programme and on any proposed changes to the improvement plan. Report 1.3, P9, P11

The Corporate Strategy sets objectives on the safety and quality of existing council homes and on delivering new affordable housing, which the programme supports. Report P68

What happens next

During May and June 2026 the Housing Consumer Standards project team will re-assess milestone two, review the Savills findings, and consider what changes are needed to the improvement plan. Report 1.3

The Housing Scrutiny Panel considered the reports on 12 May 2026; the programme board will consider proposed changes on 4 June 2026. Report P9, P10

An updated improvement plan and strategy will come to the July 2026 Homes and Housing Delivery Committee, the Housing Scrutiny Panel and the Corporate Transformation Board. Report 1.1, 2.6, P11

Options considered

  • Rejected: Continue with the existing improvement plan without changes. Programme remains at RED and the external reviews identified new actions Report 1.2, 1.3, 2.5
  • Chosen: Reassess the improvement plan and strategy during May and June 2026. To respond to the Consumer Standards Review, the Lessons Learned Review and outstanding milestone two actions Report 1.3, 2.6

Implications

  • Risk: The Housing Consumer Standards Programme is at RED status, partly because of unresolved NEC phase one issues and compliance performance challenges in some areas. Report 1.2, P7
  • Legal: The committee is being kept informed so it can assess progress against the Regulator of Social Housing's consumer standards and other statutory duties. Report P85, P86
  • Financial: Accelerated spend was reported during 2025/26 on fire alarm and sprinkler installation, funded by underspends from other projects. Report P82
  • Staffing: Plans are in place to fill the full senior and extended housing leadership structure and to develop a culture workstream within the programme. Report 3.4, 3.5, P91
  • Other: Work continues on resolving remaining issues after the NEC housing system launch, including gas servicing testing and data links with the C365 compliance system. Report P87, P88

Who and where

  • Council tenants and leaseholders in Bristol Report P71, P75
  • The fourteen percent of Bristol households in council owned housing Report P71, P72
  • Housing Scrutiny Panel and Resident and Community Panel members Report 5.1, 5.2, 5.3

Timeline

  • 21 April 2026: Savills held a follow up lessons learned session with senior council officers Report 3.2
  • 23 April 2026: Council held a meeting with the Regulator of Social Housing Report 6.1
  • 12 May 2026: Housing Scrutiny Panel considered the Savills reviews Report 5.1, P9
  • May and June 2026: Programme team to reassess milestone two and review improvement plan Report 1.3
  • 4 June 2026: Housing Consumer Standards Programme Board to consider proposed changes Report P10
  • July 2026: Homes and Housing Delivery Committee to receive updated improvement plan Report 1.1, 2.6
  • March 2027: Target completion date for milestone four of the strategy Report 2.1

Plain English for the jargon

  • HCSP: Housing Consumer Standards Programme, the council's improvement programme
  • RSH: Regulator of Social Housing, the UK regulator of social housing providers
  • HHDC: Homes and Housing Delivery Committee, the council committee that considered this report
  • HSP: Housing Scrutiny Panel, a member panel that oversees housing matters
  • NEC: The council's new housing IT system
  • C3 grading: The lowest consumer compliance grade issued by the Regulator of Social Housing
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

The Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the external Consumer Standards Review report findings (see section 2). To note the external Strategic Root Cause & Lessons Learned Review - 12 months on report findings (see section 3). To note the March 26 landlord compliance performance report (see section 4). To note the residents voice update (see section 5). To note the update from the latest regulatory review meetings with the RSH (see section 6).
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

To present to the Homes & Housing Delivery Committee (HHDC) the; latest Housing Consumer Standards Programme (HCSP) update, external consumer standards review, external strategic root cause and lessons learned review, March 26 landlord compliance performance report, residents voice update and feedback on the last meeting with the Regulator of Social Housing (RSH).

Evidence Base

1. HCSP Improvement Plan update summary – Appendix Ai

1.1The latest update summary included in appendix Ai outlines the end of February 26 position of the HCSP. The highlight report includes: • Page 2 - The ‘programme overview summary’ showing the overall programme status. • Page 3 to 5 – A high level summary of progress to date on the outstanding milestone two actions. A full reassessment of these actions will be included in the July 26 Homes & Housing Delivery Committee (HHDC) update report. • Pages 6-11 – Charts illustrating progress against the tasks within milestones three and four. Including exception commentary and improvement plans for any actions not on-target.

1.2The overall programme delivery status remains at RED for the last and current period due to: • The partial completion of milestone two • Milestone 3 and 4 delivery being at an AMBER status

Template approved October 25

OFFICIAL • The ongoing resolution a small number of outstanding issues related to the NEC phase one implementation • Some performance challenges in some landlord compliance areas (see section 4 and appendix Aiv) The RED status for the next period is due to the ongoing re-assessment of the outstanding milestone 2 actions (see update in the highlight report in Appendix Ai). The programme will be re-assessed following consideration of the outstanding milestone 2 actions alongside the recent external Consumer Standards Review (section 3 and Appendix Aii) and the external Lessons Learned Review (section 4 and Appendix Aiii). The timeline for the re-assessments is outlined in item 1.3.

1.3A significant review of the improvement plan and Housing Consumer Standards Improvement Strategy will take place during Q1 26/27. This will include: • The re-evaluation of the HCS programme taking place in May / June 26 where the HCS programme team will: o Re-assess the status of milestone 2 o Assess the findings of the Consumer Standards review, and any additional improvement plan actions required o Assess the outcome of the lessons learned session that took place on 21 April with Housing EDM o Consider consumer standards related enhancements / development required to the NEC programme. Any additional actions will be developed alongside the Housing IT Transformation Programme. o Consider the impact of the reviews on the improvement plan and Housing Consumer Standards Improvement strategy milestones and propose any revisions to the improvement plan and strategy milestones if required.

• On 12 May 26, the Housing Scrutiny Panel will consider and comment on the external Consumer Standards Review report and any proposed changes to the HCSP improvement plan and strategy milestones.

• On 4 June 26, an update on the proposed changes to the programme improvement plan and strategy milestones will be presented to the Housing Consumer Standards Programme Board for consideration and approval.

• In June 26, the Corporate Transformation board and Homes & Housing Delivery Committee will also be asked to consider and comment on the Consumer Standards Review report and any changes to the programme improvement plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HCSP Highlight Report (March 2026)Appendix Ai 576 KB Download
PDF
Consumer Standards Review ReportAppendix Aii 4.6 MB Download
PDF
Strategic Root Cause and Lessons Learned Update (May 2026)Appendix Aiii 2.8 MB Download
PDF
Landlord Compliance Performance Report (March 2026)Appendix Aiv 1.4 MB Download
PDF
Housing & Consumer Standards Programme and Compliance UpdateReport 259 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
KB
Councillor Kerry BailesCommittee Member, present
PG
Councillor Paul GogginCommittee Member, present
CG
Councillor Caroline GoochCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, apologies, sent representative
JT
Councillor Jerome ThomasCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
JS
John SmithOfficer, expected
CG
Clare GibbOfficer, expected
FL
Fiona LesterOfficer, expected

All 16 on the meeting page

On this subject at Bristol

Search all
  1. Housing & Consumer Standards Programme and Compliance UpdateThis decision
  2. Housing & Consumer Standards Programme and Compliance UpdateNoted
  3. Housing & Consumer Standards Programme and Compliance UpdateDecided
  4. Housing & Consumer Standards Programme and Compliance UpdateNoted
  5. Housing & Consumer Standards Programme and Compliance UpdateNoted
  6. Housing & Consumer Standards Programme and Compliance UpdateApproved

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Annual Cladding Remediation UpdateThe Committee Decided Open