Capital Investment into Bristol City Council Highway Infrastructure
ApprovedCommittee4 papers
AI summaryBristol's Transport and Connectivity Committee approved spending £21.725m of capital funding on highway infrastructure over 2026 to 2031, covering road maintenance, bridge and culvert repairs, retaining walls, vehicle safety systems and electrical upgrades.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCommittee approved Full Council capital allocation and delegated contract awards
Money£21.725m capitalFunded from existing approved Capital Programme and MTFP 2026/27 to 2030/31
What happens nextProcurement through existing frameworksHighways Asset Management and Civils Framework 2025-2029 and electrical assets term contract
Who it affectsHighway users and Bristol residentsRoads, bridges, culverts, retaining walls, street lighting and event electrical supply
What was decided
The committee approved the spend of the Full Council capital allocation set out in the report's table of nine workstreams running from 2026/27 to 2030/31. Report P5, P6
The committee authorised the Executive Director of Growth and Regeneration, in consultation with the committee chair, to procure and award the various contracts, which may be over the key decision threshold, through the named highways frameworks. Report P7
The committee authorised the Executive Director to invoke any subsequent extensions or variations defined in the awarded contracts, up to the maximum budget envelope in the report. Report P8
Why
The projects are critical to the council's decarbonisation and transport strategies, and maintain essential infrastructure such as statutory bridge and culvert inspections, legal safety requirements and flood risk assets. Report P14, P25
Officers say timely delivery reduces the risk of asset failure, third-party claims and higher future capital and revenue costs, while offering strong opportunities to reduce long-term financial exposure. Report P25, P26, P28
The investment aligns with the council's priorities on safe neighbourhoods, maintaining essential city infrastructure, and making travel easier, greener and safer. Report P10, P11, P12
What happens next
Procurement will use the Highways Asset Management and Civils Framework 25-29, which includes social value requirements, and the Highway electrical assets term contract. Report P7, P17
Scheme-specific Equality Impact Assessments will be carried out before delivery to mitigate any negative environmental or equalities impacts, particularly during construction. Report P16, P37, P38
Finance advice calls for robust cost monitoring, early procurement engagement and clear prioritisation to deliver within the approved capital envelope, with expenditure profiled to delivery plans and milestones. Report P26, P28
The money
£ 21,775 Total capital programme in table (figures shown in £'000) Report P6
£21.725m Capital cost stated in finance section, funded from BCC capital funding Report P22, P24
Rejected: Other proposals for different highway assets or works. Not as serious a health and safety risk, not urgent, alternative funding available, or team already under resource pressure such as signals delivery for the CRSTS programme Report P1
Chosen: Spend the Full Council capital allocation as set out in the report's table. Considered by senior technical officers as the highest critical elements for funding given the limited corporate funding available Report P1, P5, P6
Implications
Financial: Fully funded from existing approved Capital Programme and MTFP 2026/27 to 2030/31, with no direct revenue implications, though revenue resources may be reallocated to capital funding when applicable. Report P22, P26
Legal: Procurement must comply with the Procurement Act 2023 and the council's own procurement rules; legal services will advise on the process and resulting contracts. Report P30
Equalities: Potential negative equalities impacts during construction, to be mitigated through scheme-specific Equality Impact Assessments before delivery. Report P16, P37
Climate: Projects are critical to the council's decarbonisation strategy and support active travel by enhancing cycling and walking routes through proactive maintenance. Report P12, P14
Risk: Officers flag risks around scope uncertainty and market conditions; without approval, risk of unplanned emergency works, higher lifecycle costs and third-party claims would increase. Report P25, P26, P28
Staffing: HR advice states there are no HR implications evident from the report. Report P34
Who and where
Road users, pedestrians and cyclists in Bristol using the affected routes and structures Report P10, P12, P14
Residents near construction works on bridges, culverts, retaining walls and New cut walls Report P6, P16
Event organisers and attendees at Queens Square, affected by the electrical upgrade Report P6
Bristol City Council as owner of the highway asset base, including statutory inspection regimes Report P25
Timeline
12 February 2026: Full Council allocated the capital funding as part of budget setting Report P20
23 February 2026: Legal advice provided by Husinara Jones, Team Manager and Solicitor Report P31
3 March 2026: Finance advice signed off by Vivi Sargioti, Finance Business Partner for Growth and Regeneration Report P29
14 May 2026: Transport and Connectivity Policy Committee took the decision
Plain English for the jargon
CRSTS: City Region Sustainable Transport Settlement, a government funding programme for transport schemes
MTFP: Medium Term Financial Plan, the council's multi-year budget planning document
EqIA: Equality Impact Assessment, used to assess and mitigate equalities effects of a scheme
EIA: Environmental Impact Assessment, used to assess environmental effects
Highways Asset Management and Civils Framework 2025-2029: A pre-arranged procurement framework through which the council can award highway and civils works contracts
Vehicle Restraint Site: Locations with safety barriers or similar systems alongside the highway
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
The Committee for Transport and Connectivity: 1. Approved the spend of the Full Council allocation as set out in the table 1 of the report. Contractual: 1. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of Transport and Connectivity Committee to procure and award the various contracts (which may be over the key decision threshold) through the Highways Asset Management and Civils Framework 2025-2029 and Highway electrical assets term contract, in-line with the procurement routes and maximum budget envelopes outlined in this report. Authorised the Executive Director of Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Committee Report
KEY DECISION OR FOR INFORMATION: Key decision over £500k spend/save & impacts more than 2 wards
COMMITTEE: Transport and Connectivity Committee
DATE: 14 May 2026
TITLE: Capital Investment into Bristol City Council (BCC) Highway Infrastructure
Ward(s): Citywide
Officer presenting the report: Patsy Mellor Director Management of Place and Shaun Taylor Head of Highways
Committee Chair: Councillor Ed Plowden
Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report: To seek approval to procure and spend capital investment into Highway Infrastructure awarded as part of the Full Council meeting 12 February 2026.
Evidence Base
1. The list of capital pressures in table 1 have been developed from the Health and Safety pressures and lifecycle modelling for the various asset’s areas in the Highways and Traffic department. The detail and business case of why these assets are need of capital funding is set out Appendix A.
2. To finance the new 2026/27 capital priorities £93m on the 2026/27 budget report finance put aside an element of Strategic CIL Fund of £15m for this purpose alongside the additional Prudential Borrowing & some Cap receipts internal funding resources. It is proposed that Frome Culvert, New Template approved October 25
OFFICIAL Cut Walls and Netham Lock Bridges are to be funded by the agreed SCIL allocation with the remaining projects funded by prudential borrowing or capital receipts.
3. Detailed below is a brief description of each of the requirements:
Brief Descriptions:
a) Annual road maintenance programme: Following national guidance and best practice, the annual road maintenance programme focuses on preventative maintenance, to stop or slow down the wear and tear of the road. The plan includes both routine repairs and full replacement at key locations. Annual conditions surveys are undertaken of the entire network which informs a full network carriageway lifecycle model. The lifecycle model outputs a 1, 3 and 5 year programme of works which is based on asset need but is also prioritised by bus routes, cycle routes, and essential infrastructure (hospitals, schools etc). This work is essential to meet the council’s legal duty to maintain safe roads.
b) Netham Lock bridges repairs: The council has a legal responsibility to look after and maintain the lock bridges which play an important role in Bristol’s flood defences. Following an inspection, one of the bridges may need to be fully replaced, along with further structural repairs to the adjacent other bridge, highlighting the need for investment in both these structures.
c) Frome culvert structural inspections and repairs: A full inspection of the Frome culvert structure sites is needed as there are likely to be a number of areas in need of substantial repair. The culverts of the River Frome form large, culverted tunnels under the centre of Bristol. Following national statutory guidance, culverts of this size need to have a thorough inspection once every 6 years. The inspection will involve confined spaced, concrete, masonry and brickwork reconstruction and repair.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.