Transport & Connectivity Policy Committee, Thursday 14 May 2026 at 5.00pm

Capital Investment into Bristol City Council Highway Infrastructure

Approved Committee 4 papers

AI summaryBristol's Transport and Connectivity Committee approved spending £21.725m of capital funding on highway infrastructure over 2026 to 2031, covering road maintenance, bridge and culvert repairs, retaining walls, vehicle safety systems and electrical upgrades.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCommittee approved Full Council capital allocation and delegated contract awards
Money£21.725m capitalFunded from existing approved Capital Programme and MTFP 2026/27 to 2030/31
What happens nextProcurement through existing frameworksHighways Asset Management and Civils Framework 2025-2029 and electrical assets term contract
Who it affectsHighway users and Bristol residentsRoads, bridges, culverts, retaining walls, street lighting and event electrical supply

What was decided

The committee approved the spend of the Full Council capital allocation set out in the report's table of nine workstreams running from 2026/27 to 2030/31. Report P5, P6

The committee authorised the Executive Director of Growth and Regeneration, in consultation with the committee chair, to procure and award the various contracts, which may be over the key decision threshold, through the named highways frameworks. Report P7

The committee authorised the Executive Director to invoke any subsequent extensions or variations defined in the awarded contracts, up to the maximum budget envelope in the report. Report P8

Why

The projects are critical to the council's decarbonisation and transport strategies, and maintain essential infrastructure such as statutory bridge and culvert inspections, legal safety requirements and flood risk assets. Report P14, P25

Officers say timely delivery reduces the risk of asset failure, third-party claims and higher future capital and revenue costs, while offering strong opportunities to reduce long-term financial exposure. Report P25, P26, P28

The investment aligns with the council's priorities on safe neighbourhoods, maintaining essential city infrastructure, and making travel easier, greener and safer. Report P10, P11, P12

What happens next

Procurement will use the Highways Asset Management and Civils Framework 25-29, which includes social value requirements, and the Highway electrical assets term contract. Report P7, P17

Scheme-specific Equality Impact Assessments will be carried out before delivery to mitigate any negative environmental or equalities impacts, particularly during construction. Report P16, P37, P38

Finance advice calls for robust cost monitoring, early procurement engagement and clear prioritisation to deliver within the approved capital envelope, with expenditure profiled to delivery plans and milestones. Report P26, P28

The money

  • £ 21,775 Total capital programme in table (figures shown in £'000) Report P6
  • £21.725m Capital cost stated in finance section, funded from BCC capital funding Report P22, P24
  • £ 10,325 Annual road maintenance programme total, £'000 Report P6
  • £ 3,000 Frome culvert structural inspections and repairs total, £'000 Report P6
  • £ 3,000 Repairs to New cut walls, 2026/27 only, £'000 Report P6
  • £ 1,400 Netham Lock bridges repairs, 2026/27 only, £'000 Report P6
  • £ 1,250 Bridge inspections programme total, £'000 Report P6
  • £ 1,000 Repairs to highway retaining walls total, £'000 Report P6

Options considered

  • Rejected: Other proposals for different highway assets or works. Not as serious a health and safety risk, not urgent, alternative funding available, or team already under resource pressure such as signals delivery for the CRSTS programme Report P1
  • Chosen: Spend the Full Council capital allocation as set out in the report's table. Considered by senior technical officers as the highest critical elements for funding given the limited corporate funding available Report P1, P5, P6

Implications

  • Financial: Fully funded from existing approved Capital Programme and MTFP 2026/27 to 2030/31, with no direct revenue implications, though revenue resources may be reallocated to capital funding when applicable. Report P22, P26
  • Legal: Procurement must comply with the Procurement Act 2023 and the council's own procurement rules; legal services will advise on the process and resulting contracts. Report P30
  • Equalities: Potential negative equalities impacts during construction, to be mitigated through scheme-specific Equality Impact Assessments before delivery. Report P16, P37
  • Climate: Projects are critical to the council's decarbonisation strategy and support active travel by enhancing cycling and walking routes through proactive maintenance. Report P12, P14
  • Risk: Officers flag risks around scope uncertainty and market conditions; without approval, risk of unplanned emergency works, higher lifecycle costs and third-party claims would increase. Report P25, P26, P28
  • Staffing: HR advice states there are no HR implications evident from the report. Report P34

Who and where

  • Road users, pedestrians and cyclists in Bristol using the affected routes and structures Report P10, P12, P14
  • Residents near construction works on bridges, culverts, retaining walls and New cut walls Report P6, P16
  • Event organisers and attendees at Queens Square, affected by the electrical upgrade Report P6
  • Bristol City Council as owner of the highway asset base, including statutory inspection regimes Report P25

Timeline

  • 12 February 2026: Full Council allocated the capital funding as part of budget setting Report P20
  • 23 February 2026: Legal advice provided by Husinara Jones, Team Manager and Solicitor Report P31
  • 3 March 2026: Finance advice signed off by Vivi Sargioti, Finance Business Partner for Growth and Regeneration Report P29
  • 14 May 2026: Transport and Connectivity Policy Committee took the decision

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a government funding programme for transport schemes
  • MTFP: Medium Term Financial Plan, the council's multi-year budget planning document
  • EqIA: Equality Impact Assessment, used to assess and mitigate equalities effects of a scheme
  • EIA: Environmental Impact Assessment, used to assess environmental effects
  • Highways Asset Management and Civils Framework 2025-2029: A pre-arranged procurement framework through which the council can award highway and civils works contracts
  • Vehicle Restraint Site: Locations with safety barriers or similar systems alongside the highway
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

The Committee for Transport and Connectivity: 1. Approved the spend of the Full Council allocation as set out in the table 1 of the report. Contractual: 1. Authorised the Executive Director of Growth and Regeneration in consultation with the Chair of Transport and Connectivity Committee to procure and award the various contracts (which may be over the key decision threshold) through the Highways Asset Management and Civils Framework 2025-2029 and Highway electrical assets term contract, in-line with the procurement routes and maximum budget envelopes outlined in this report. Authorised the Executive Director of Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Committee Report

KEY DECISION OR FOR INFORMATION: Key decision over £500k spend/save & impacts more than 2 wards

COMMITTEE: Transport and Connectivity Committee

DATE: 14 May 2026

TITLE: Capital Investment into Bristol City Council (BCC) Highway Infrastructure

Ward(s): Citywide

Officer presenting the report: Patsy Mellor Director Management of Place and Shaun Taylor Head of Highways

Committee Chair: Councillor Ed Plowden

Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: To seek approval to procure and spend capital investment into Highway Infrastructure awarded as part of the Full Council meeting 12 February 2026.

Evidence Base

1. The list of capital pressures in table 1 have been developed from the Health and Safety pressures and lifecycle modelling for the various asset’s areas in the Highways and Traffic department. The detail and business case of why these assets are need of capital funding is set out Appendix A.

Table 1 2026/27 2027/28 2028/29 2029/30 2030/31 Overall Budget Title £'000 £'000 £'000 £'000 £'000 Impact £'000 Annual road maintenance programme £ 3,325 £ 1,750 £ 1,750 £ 1,750 £ 1,750 £ 10,325 Netham Lock bridges repairs £ 1,400 £ - £ - £ - £ - £ 1,400 Frome culvert structural inspections and repairs £ 1,000 £ 500 £ 500 £ 500 £ 500 £ 3,000 Repairs to highway retaining walls £ - £ 250 £ 250 £ 250 £ 250 £ 1,000 Bridge inspections £ - £ 250 £ 250 £ 500 £ 250 £ 1,250 Vehicle Restraint Site repairs £ 475 £ 250 £ - £ - £ - £ 725 Highway electrical asset upgrades £ 500 £ 250 £ - £ - £ - £ 750 Electrical upgrade for Queens Square events £ 325 £ - £ - £ - £ - £ 325 Repairs to New cut walls £ 3,000 £ - £ - £ - £ - £ 3,000 Total £ 21,775

2. To finance the new 2026/27 capital priorities £93m on the 2026/27 budget report finance put aside an element of Strategic CIL Fund of £15m for this purpose alongside the additional Prudential Borrowing & some Cap receipts internal funding resources. It is proposed that Frome Culvert, New Template approved October 25

OFFICIAL Cut Walls and Netham Lock Bridges are to be funded by the agreed SCIL allocation with the remaining projects funded by prudential borrowing or capital receipts.

3. Detailed below is a brief description of each of the requirements:

Brief Descriptions:

a) Annual road maintenance programme: Following national guidance and best practice, the annual road maintenance programme focuses on preventative maintenance, to stop or slow down the wear and tear of the road. The plan includes both routine repairs and full replacement at key locations. Annual conditions surveys are undertaken of the entire network which informs a full network carriageway lifecycle model. The lifecycle model outputs a 1, 3 and 5 year programme of works which is based on asset need but is also prioritised by bus routes, cycle routes, and essential infrastructure (hospitals, schools etc). This work is essential to meet the council’s legal duty to maintain safe roads.

b) Netham Lock bridges repairs: The council has a legal responsibility to look after and maintain the lock bridges which play an important role in Bristol’s flood defences. Following an inspection, one of the bridges may need to be fully replaced, along with further structural repairs to the adjacent other bridge, highlighting the need for investment in both these structures.

c) Frome culvert structural inspections and repairs: A full inspection of the Frome culvert structure sites is needed as there are likely to be a number of areas in need of substantial repair. The culverts of the River Frome form large, culverted tunnels under the centre of Bristol. Following national statutory guidance, culverts of this size need to have a thorough inspection once every 6 years. The inspection will involve confined spaced, concrete, masonry and brickwork reconstruction and repair.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(1)Appendix A 150 KB Download
PDF
EQIA Capital InvestmentAppendix B 262 KB Download
PDF
Environmental Impact Assessment Capital Investment into BCC Highways (1)Appendix C 375 KB Download
PDF
Capital Investment into Bristol City Council Highway InfrastructureReport 192 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
EP
Councillor Ed PlowdenChair, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
SR
Councillor Serena RalstonCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
TW
Councillor Toby WellsCommittee Member, present
MW
Councillor Mark WestonCommittee Member, present
JS
John SmithOfficer, expected
AH
Alex HearnOfficer, expected
PM
Patsy MellorOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Capital Investment into Bristol City Council Highway InfrastructureThis decision
  2. Complex Needs Open Children's Homes Capital Investment Grant Bid – BNSSG ConsortiumNoted
  3. Education Capital Update and Capital Investment DecisionDecided
  4. Harbour Infrastructure Improvements and Technologies - Capital Investment ProgrammeApproved
  5. Market and Docks Capital Investment ProgrammeApproved

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open