AI summaryBristol Transport Committee approved applying for up to £2.875 million plus indexation of Section 106 funding from South Gloucestershire Council for the Cribbs Patchway New Neighbourhood project, with £250,000 for design and £488,837 for dropped kerbs.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedFive authorisations covering S106 application, two drawdowns, procurement and variations
MoneyNot stated
What happens nextFurther committee report on CPNN designsBrought to committee once design development is complete
Who it affectsA38 and A37/A4018 corridor usersPedestrians, cyclists and bus users between Filton and Horfield
What was decided
The Executive Director for Growth and Regeneration, in consultation with the committee chair, is authorised to apply to South Gloucestershire Council for Section 106 funding relating to Cribbs Patchway New Neighbourhood, to a maximum of £2.875 million plus indexation. Report P25
The same officer is authorised to accept and draw down £250,000 for design development of the CPNN project, and to accept and draw down £488,837 for delivery of A37/A4018 Work Package 4 (Dropped Kerbs). Report P26, P27
The officer is also authorised to procure and award contracts for the A37/A4018 Work Package 4, and to invoke any extensions or variations defined in those contracts, up to the maximum budget envelope in the report. Report P28, P29
Why
Moving A37/A4018 Work Package 4 from City Region Sustainable Transport Settlement funding to Cribbs Patchway New Neighbourhood Section 106 contributions relieves pressure on the CRSTS budget. Report P4, P12
The funding supports the strategic goal of facilitating sustainable travel on the A38 corridor and adjoining roads between Filton and Horfield, by improving pedestrian, cycle and public transport provision. Report P7, P37
An option to delay the funding application was rejected because it would delay the associated benefits and risk them not being delivered in time to mitigate the effects of the Cribbs Patchway New Neighbourhood housing development. Report P22
What happens next
Submit the funding application to South Gloucestershire Council, then draw down £250,000 to begin design development of the CPNN project. Report P2, P3, P11
Procure and award contracts for A37/A4018 Work Package 4 (Dropped Kerbs) up to £488,837, and draw down that amount for delivery. Report P5, P14
Once CPNN designs are produced, bring a further report to the Transport and Connectivity Committee to approve delivery, and carry out consultation with members, ward councillors, stakeholders and the public. Report P3, P11, P44
The money
£2,875,000 plus indexation Maximum Section 106 application to South Gloucestershire Council for the CPNN project Report P2, P50
£250,000 Drawdown from the CPNN allocation for design development Report P3, P26
£488,837 Drawdown for delivery of A37/A4018 Work Package 4 (Dropped Kerbs) Report P4, P14, P16, P27
£365,151 Construction cost within the A37/A4018 Work Package 4 total Report P16
£53,686 Engineering design fees within the A37/A4018 Work Package 4 total Report P16
£25,000 Project management within the A37/A4018 Work Package 4 total Report P16
£45,000 Contingency (10%) within the A37/A4018 Work Package 4 total Report P16
approximately £1.7 million CRSTS allocation for delivery of work package 4 of the Stockwood to Henbury Corridor, of which the £488,837 forms a part Report P54
Options considered
Chosen: Apply now to South Gloucestershire Council for the Cribbs Patchway New Neighbourhood Section 106 funding. Avoids delaying benefits and mitigates effects of the Cribbs Patchway New Neighbourhood housing development Report P22, P25
Rejected: Delay the funding application to a future year. Would delay the associated benefits and risk them not being delivered in time to mitigate the effects of the Cribbs Patchway New Neighbourhood housing development Report P22
Implications
Financial: No revenue cost; all costs are fully capital funded through external Section 106 contributions. The remainder of the Section 106 contributions, if received, will be held for draw down later. Report P50, P53, P54
Legal: If the funding bid is successful, the procurement process must be conducted in line with the Procurement Act 2023 and the council's own procurement rules, with legal services advising on contractual arrangements. Report P56
Equalities: The Equality Impact Assessment and Environmental Impact Assessment for the funding application have been completed as No Impact; updated assessments will be produced once the CPNN project is developed. Report P18
Staffing: No HR implications have been identified. Report P60
Other: No implications on IT are identified. Report P58
Who and where
Pedestrians, cyclists and public transport users on the A38 corridor and adjoining roads between Filton and Horfield Report P7
Users of the A37, A4018, A38 (Gloucester Road) and B4056 (Southmead Road) corridors where Work Package 4 dropped kerbs will be delivered Report P17, P43
Future residents of the Cribbs Patchway New Neighbourhood housing development Report P22
South Gloucestershire Council, which manages the Cribbs Patchway New Neighbourhood Section 106 funding pot Report P7, P9
Timeline
8 October 2024: Golden motion to make Bristol the most accessible city in the UK approved at Full Council Report P48
October 2025: Template for the report approved Report P7
4 December 2025: A37/A4018 Work Package 4 (Dropped Kerbs) approved at Transport and Connectivity Committee and circulated to Ward Councillors Report P43, P49
January 2026: CRSTS re-baselining exercise proposed funding A37/A4018 Work Package 4 via CPNN Section 106 contributions rather than Department for Transport CRSTS funding Report P12
February 2026: CRSTS Change Request approved at Committee, moving A37/A4018 Work Package 4 into CPNN funding Report P12
4 February 2026: HR advice provided by the HR Business Partner Report P61
5 February 2026: Legal advice provided by the Legal Team Manager Report P57
10 February 2026: IT advice provided by the Lead Enterprise Architect Report P59
3 March 2026: Finance advice provided by the Finance Business Partner Report P55
14 May 2026: Decision taken by the Transport and Connectivity Policy Committee
After design development: A further report will be brought to committee to approve delivery of the CPNN project designs, and consultation will be carried out with members, ward councillors, stakeholders and the public Report P3, P11, P44
Plain English for the jargon
Section 106 (S106): Planning obligation funding paid by developers, here managed by South Gloucestershire Council, ringfenced for measures such as enhancing pedestrian, cycle and public transport provision on the A38 corridor and adjoining roads between Filton and Horfield
CPNN: Cribbs Patchway New Neighbourhood, the housing development to which the Section 106 funding relates
CRSTS: City Region Sustainable Transport Settlement, a Department for Transport capital funding programme
A37/A4018 Work Package 4 (Dropped Kerbs): Work package 4 of the Stockwood to Henbury Corridor, originally approved at the Transport and Connectivity Committee on 4 December 2025, now proposed to be funded via CPNN Section 106 contributions
JLTP: Joint Local Transport Plan
LCWIP: Local Cycling and Walking Infrastructure Plan, here the West of England version
Indexation: An uplift applied to the funding amount to reflect changes in prices over time
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
The Committee for Transport and Connectivity: Authorised the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Committee, to apply to South Gloucestershire Council for Section 106 funding relating to Cribbs Patchway New Neighbourhood to a maximum value of £2.875 million plus indexation. Authorised the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Committee, to accept and draw down £250,000 for the design development of the CPNN project. Authorised the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Committee, to accept and draw down £488,837 for the delivery of A37/A4018 Work Package 4 (Dropped Kerbs). Authorised the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Committee, to procure and award contracts for the delivery of A37/ A4018 Work Package 4, in line with the procurement routes and maximum budget envelopes outlined in this report. Authorised the Executive Director for Growth and Regeneration, in consultation with the Chair of the Transport and Connectivity Committee, to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
To seek approval to:
1. Apply to South Gloucestershire Council for Section 106 funding to develop a new project related to Cribbs Patchway New Neighbourhood (CPNN) to a maximum value of £2.875 million plus indexation.
2. Accept and draw down £250,000 of the total £2.875 million, to fund design development for the new CPNN project. Once the designs have been produced, a further report will be brought to committee to approve delivery of those designs.
3. Accept and draw down £488,837 of the total £2.875 million, to fund the delivery of A37/A4018 Work Package 4 (Dropped Kerbs). This project was developed as part of CRSTS, and was approved by Committee in December 2025, but it is proposed to move delivery into CPNN, to relieve pressure on the CRSTS budget.
4. Procure and award contracts up to the value of £488,837 for the delivery of A37/A4018 Work Package 4 (Dropped Kerbs).
Evidence Base:
1. Cribbs Patchway New Neighbourhood funding is a pot of Section 106 funding for the “Provision of measures to enhance pedestrian, cycle and public transport provision on the A38 corridor and adjoining roads between Filton and Horfield.” Template approved October 25
OFFICIAL 2. A copy of the original headline specification is included below. This was produced over 10 years ago and the timescales have changed considerably since this was produced.
3. The funding is managed by South Gloucestershire Council and Bristol City Council’s allocation is £2.875 million plus indexation.
4. The main purpose of this report is to seek approval to apply to South Gloucestershire Council for this funding to develop a new project, related to Cribbs Patchway New Neighbourhood (CPNN).
5. If the funding is approved, this report is seeking approval to draw down £250,000 of the total £2.875 million, to fund design development for the new project. Once the designs have been produced, a further report will be brought to committee to approve delivery of those designs. 6. In addition to this, it is proposed to move another project into the scope of the CPNN project. A37/A4018 Work Package 4 (Dropped Kerbs) was originally developed as part of CRSTS and was approved at Committee in December 2025. The Committee Report is here: A37/A4018 Work Package 4 (Dropped Kerbs) Committee Report December 2025
7. As part of the CRSTS re-baselining exercise in January 2026, it was proposed that A37/A4018 Work Package 4 (Dropped Kerbs) be funded via CPNN Section 106 contributions, rather than Department for Transport CRSTS funding. This was included in the Change Request submitted as part of the CRSTS Committee Report approved in February 2026. The Committee Report is here: City Region Sustainable Transport Settlement Committee Report February 2026
Template approved October 25
OFFICIAL 8. If the funding is approved, this report is seeking approval to draw down £488,837 of the total £2.875 million, to fund the delivery of A37/A4018 Work Package 4 (Dropped Kerbs). It is also seeking approval to procure and award contracts up to this value.
9. The cost breakdown for A37/A4018 Work Package 4 (Dropped Kerbs) is as follows:
Construction Cost £365,151 Engineering Design Fees £53,686 Project Management £25,000 Contingency (10%) £45,000 TOTAL £488,837
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.