Non-key Decision Committee Report
PURPOSE: Non-key decision update report
COMMITTEE: Homes and Housing Delivery Committee
DATE: 29 May 2026
TITLE: Q4 2025/26 Corporate Risk Report Officer presenting the report: David McNulty Title: Executive Director: Housing
Committee Chair: Councillor Barry Parsons. Executive Director lead: David McNulty, Executive Director: Housing Purpose of Report: The report provides an update on current significant strategic risks, relevant to the Homes and Housing Delivery Committee, to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q4 2025-26.
Figure 1 – Q4 Corporate Risk Register Q3 Q4 Corporate Risk Owner Score Direction Score Direction CRR60 Failure of HRA stock to meet Interim 28 28 landlord statutory obligations, the Director - decent homes standard and Transformatio consumer standards n and Building Safety Q4 Comment Joint review by Housing & Consumer Standards Programme Lea and Interim Director: Transformation & Building Safety. Agreed to reinstate likelihood to ‘Almost Certain’ (after reducing to ‘Likely’ mid-Q3 on 30/10/25) and this will be reviewed post HCSP Milestone 2 when mitigation measures have been tested and high risk backlog programmes have been completed
CRR52 Failure to manage and Interim 21 21 evidence compliance with the Director - Building Safety Act 2022 obligations Transformatio in HRA stock n and Building Safety Q4 Comment 1
OFFICIAL Environmental impact reduced now that FRAEWs complete and external wall composition known.
CRR37 Failure to successfully Director - 15 15 implement the Tackling Housing & Homelessness Programme Landlord Services Q4 Comment The programme achieved its savings target for 24/25, and is forecasting to achieve its overall savings target for 25/26. However, some individual work streams are not delivering and are being mitigated by other work streams that are over-delivering. There is a risk that the work streams that are under-delivering may slip further, and that there won't be enough over-delivery elsewhere to mitigate this. For this reason, the risk score remains at 15. Figure 2 Risk Direction Key Direction Description The risk rating has improved from the previous quarter, having reduced in its severity. The risk rating has deteriorated from the previous quarter, having increased in its severity.
The risk rating has not changed from the previous quarter.
Evidence Base / Context
1. The Corporate Risk Report (CRR) is a key document in the council’s approach to the management of risk; it captures strategic risks set out in the Corporate Strategy 2025-2030. It also provides a context on how Directorates perform their high-level risk assessments and is used to inform business planning, budget setting, transformation, and service delivery.
2. Ensuring Service Risk Registers (SRR), Directorate Risk Reports (DRR) and Corporate Risk Reports (CRR) are soundly based helps council to demonstrate it is anticipating and managing key risks and to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
3. The registers and reports are a management tool. They need regular review to ensure that the occurrence of obstacles or events that may put individual’s safety at harm, impact upon service delivery and the council’s reputation are minimised, opportunities are maximised and when risks happen, they are managed effectively to minimise the impact.
OFFICIAL Summary of Corporate Risks:
4. Housing Executive Directorate members reviewed their all their risks on 9th March 2026 to form the current CRR. The H&HD committee is asked to accept the attached CRR as a working summary report of the critical and significant risks from the Service Risk Registers.
5. The Homes and Housing Delivery Committee Q4 2025/26 Corporate Risk Report 10th March 2026 contains 3 risks:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q4 Corporate Risk Report 2025/26Report | 261 KB | DownloadRead as text |
Follow Homes and Housing Delivery Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2026 | Q1 (P03) Finance UpdateThe Committee | Decided | Open |
| 18 Sep 2026 | Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. | Noted | Open |
| 18 Sep 2026 | Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... | Noted | Open |
| 18 Sep 2026 | Asset Management StrategyThe Committee (unanimously) | Decided | Open |
| 18 Sep 2026 | Annual Cladding Remediation UpdateThe Committee | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.