Resolved
RESOLVED that the bid to Capital Ambition on web development be endorsed.
Improvement and Efficiency Sub-Committee decided this item on Tuesday 1 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the bid to Capital Ambition on web development be endorsed.
Report No. London Borough of Bromley CEO1059 PART 1 - PUBLIC
Decision Maker: Improvement & Efficiency Sub Committee
Date: 1st June 2010 Decision Type: Non-Urgent Non-Executive Non-Key
Title: PARTNERSHIP WORKING - WEB DEVELOPMENT
Contact Officer: Richard Hills, Programme Manager Tel: 020 8313 4393 E-mail: [email protected]
Chief Officer: Chief Executive
Ward: All wards
1. Reason for report
To bring Members up to date with the work of the Organisational Improvement Team to secure funding for web development as a key piece of work aimed at achieving the corporate outcomes set out in our Corporate Operating Principles model (COP):
Reduction in processing costs Reduction in avoidable contact High volume transactional services available online
________________________________________________________________________________
2. RECOMMENDATION(S)
Members are asked to endorse the bid to Capital Ambition on web development, as working in partnership with Bexley to share investment costs allows us the opportunity to tackle an area of service improvement that would otherwise be very costly for Bromley, especially given the current financial climate.
1 Corporate Policy 1. Policy Status: N/A. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost Total cost £1 million (£500k Capital Ambition, £250k Bromley, £250k Bexley) Bromley already has £240k set aside in the capital programme awaiting a business case - code 936451 called 'Joint Web Platform' 2. Ongoing costs: Recurring cost. Although the bulk of costs is capital expenditure there would be some recurring cost in terms of software licences and maintenance. 3. Budget head/performance centre: Customer Contact Centre (Sheila Bennett) & Bromley Knowledge (Jim Grainger) 4. Total current budget for this head: £Customer Contact Centre £1,385,300 (£976,330 controllable budget) & Bromley Knowledge £222,330 (£114,720 controllable budget) 5. Source of funding: Split £500k Capital Ambition, £250k Bexley, £250k Bromley ________________________________________________________________________________ Staff 1. Number of staff (current and additional): Out of additional staff resource. Bid put together by the Organisational Improvement Team with assistance from Heads of Service 2. If from existing staff resources, number of staff hours: Estimate one working week (36 hours) drawn from various officers ________________________________________________________________________________ Legal 1. Legal Requirement: No statutory requirement or Government guidance. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): All customers should be considered potential beneficaries. ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A. 2. Summary of Ward Councillors comments:
2 3. COMMENTARY
3.1Development of the Bromley website has been an ambition for some time and when the new Organisational Improvement Team was set up in Oct 2009 it was quickly made one of the team’s key priorities to investigate.
3.2Since then a specification document has been created and some initial high level (and alarming quotes) have been obtained. A partnership opportunity was also investigated with Lewisham and Newham but their budgets were very sizeable and the business partners’ early quotations were considered to be very high. Too high to be able to put a business case together that worked effectively as an ‘invest to save’ and it would have been more an ‘invest to improve’ business case with some efficiency savings more as an aside given the payback period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
IE-Sub-010610-10-Partnership Working Web Development App 1Appendix | 377 KB | Download |
PDF |
PARTNERSHIP WORKING: WEB DEVELOPMENTReport | 132 KB | DownloadRead as text |
Follow Improvement and Efficiency Sub-Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2013 | Minutes of the meeting held on 3rd october 2012RESOLVED that the minutes of the meeting held on 3 rd October 2012 be agreed. | Agreed | Open |
| 19 Feb 2013 | Matters arising from previous meetingsRESOLVED that matters arising be noted. | Noted | Open |
| 19 Feb 2013 | Analysis of staff leaversRESOLVED that the analysis of staff leavers be noted. | Noted | Open |
| 19 Feb 2013 | Environment improvement post completion report (lpsa reward grant)RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted. | Noted | Open |
| 19 Feb 2013 | Invest to saveRESOLVED that the progress of Invest to Save Schemes be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.