Resolved
RESOLVED that the progress made on the first phase projects within the Organisational Improvement Programme be noted.
Improvement and Efficiency Sub-Committee noted this item on Tuesday 1 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the progress made on the first phase projects within the Organisational Improvement Programme be noted.
Appendix 1
Organisational Improvement Programme Management Highlight Report
Highlight Report Overall RAG Status AMBER
To I&E sub-committee
Project / Programme nd th Organisational Improvement Programme Reporting Period 22 Apr 10 To 6 June 10 Name
Report Author(s) Organisational Improvement Team Stage / Status Definition
Start Date Oct 09 Proposed End Date
Management Summary
Both COE and the I&E Sub Committee have approved the creation of a single Organisational Improvement Programme, aimed at bringing together 3 key strands of work; Customer Access; Office Accommodation and Flexible Working and Back Office reform in order to deliver both efficiencies and improvements across the council.
The main project areas have been signed off by COE and the I&E Sub-Committee. A summary of these projects is below. Organisational Improvement Programme Management Highlight Report
Key progress during reporting Risks and issues to be raised for Tasks planned for next period RAG status Period information or escalated
Work Stream: Office Accommodation
Project 1: Business case and Main Issues: implementation planning for office accommodation project Direction of workstream dependent on Short term priorities: strategic decisions on property by Briefed external consultants to advise on Members. Work with consultants to deliver overall property strategy. Proposal No funding approved pending above evalution of strategic options to received w/c 18 May so all actions on minimal basis Members as soon as possible Current projects do not release Jo Progress PCT accommodation plan. Confirmed working assumptions on PCT – Lanc or Ann Springman. Work with ESD working group on 50 – 60 staff in 6 - 9 months from April. flexible working. Aim to reduce space Risks: in St Blaise by 50% for PCT occupation. St Blaise solution agreed by Programme Progress storage reduction through AMBER Board 22 April PCT staff numbers still uncertain working with ESD and generally. CYP teams need to be together – Started Capital Ambition project with ESD need to ensure enough space in St Once overall strategy is agreed: on flexible working to achieve 50% Blaise/PCT planning. reduction in office space. Workstyle Future accommodation/equipment Re-plan if necessary and workshops held 13 May Liaise with departments on allocation solutions are not attractive to colleagues/partners of space/location to enable building Working with ESD organisational Final decisions on one stop shop and ICT infrastructure works to be improvement group on storage issues and concept, remit and location could commissioned and detailed staff move extending to all departments on civic site, require some adjustment in this plans to be developed. and linked in with storage project. workstream. Organisational Improvement Programme Management Highlight Report
Work stream: Self-service and ICT
Website upgrade Issues: Work planned:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
IE-Sub-010610-08-Organisational Improvement Programme App1Report | 150 KB | DownloadRead as text |
PDF |
ORGANISATIONAL IMPROVEMENT PROGRAMMEReport | 103 KB | Download |
Follow Improvement and Efficiency Sub-Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2013 | Minutes of the meeting held on 3rd october 2012RESOLVED that the minutes of the meeting held on 3 rd October 2012 be agreed. | Agreed | Open |
| 19 Feb 2013 | Matters arising from previous meetingsRESOLVED that matters arising be noted. | Noted | Open |
| 19 Feb 2013 | Analysis of staff leaversRESOLVED that the analysis of staff leavers be noted. | Noted | Open |
| 19 Feb 2013 | Environment improvement post completion report (lpsa reward grant)RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted. | Noted | Open |
| 19 Feb 2013 | Invest to saveRESOLVED that the progress of Invest to Save Schemes be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.