ORGANISATIONAL IMPROVEMENT PROGRAMME UPDATE

Noted Committee 2 papers

Improvement and Efficiency Sub-Committee noted this item on Wednesday 20 April 2011. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

RESOLVED that the progress made to date on projects led by the Organisational Improvement Programme be noted.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Improvement and Efficiency Sub-Committee, 6 pages

Report No. London Borough of Bromley CEO1169 PART 1 - PUBLIC

Decision Maker: Improvement and Efficiency Sub-Committee

Date: 20th April 2011 Decision Type: Non-Urgent Non-Executive Non-Key

Title: ORGANISATIONAL IMPROVEMENT PROGRAMME UPDATE

Contact Officer: Chris Spellman, Assistant Director, Organisational Improvement Tel: 020 8461 7942 E-mail: [email protected]

Chief Officer: Doug Patterson, Chief Executive

Ward: Borough-wide

1. Reason for report

1.1To update Members on the progress of the Organisational Improvement Programme.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1Note the progress made to date on projects led by the Organisational Improvement Programme

1 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: N/A No additional costs at this stage 2. Ongoing costs: N/A. Opportunity cost of Organisational Improvement Team. No additional

ongoing costs at this stage. Any business cases for future projects will include ongoing costs. 3. Budget head/performance centre: Organisational Improvement Team 4. Total current budget for this head: £ 5. Source of funding: Existing revenue budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 5 FTE 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: Non-statutory - Government guidance. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Beneficiaries will be identified

as part of business cases developed through the programme. Potentially all customers and

staff are beneficiaries of this improvement programme. ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A. 2. Summary of Ward Councillors comments: N/A

2 3. COMMENTARY

3.1Since last reporting to I&E Sub-Committee, several of the projects within the programme have progressed significantly.

3.2More detail on the precise progress, risks, issues and planned work is shown in the Programme Highlight report in Appendix 1. A very brief summary of the major workstreams’ progress is given below for convenience.

Civic centre accommodation

3.3Work on refurbishing North Block has commenced and teams from ESD are starting to move out into decant space

3.4An operational group has been set up to work on the design of receptions and interview rooms in ground floor Stockwell and North Block. Meetings are taking place between the Head of Customer Services and representatives of each relevant service area to determine and coordinate their requirements.

3.5A Records and Retention Policy has been agreed by Chief Officers and is currently being implemented by targeting as a priority those areas impacted by the accommodation changes. The policy stipulates that generally information, both hard copy and electronic, will only be kept for as long as legally required. A process to allow for exceptions to this policy to be accommodated, such as where there is a clear business need to retain information or records that have historical value, has been built into the process of implementation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IE Sub 200411 Organisational Improvement Programme Update Appendix AAppendix 173 KB Download
PDF
ORGANISATIONAL IMPROVEMENT PROGRAMME UPDATEReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. ORGANISATIONAL IMPROVEMENT PROGRAMME UPDATEThis decision
  2. Organisational improvement programme updateNoted
  3. Organisational improvement programme updateNoted
  4. Organisational improvement programmeNoted

More from Bromley Improvement and Efficiency Sub-Committee

All decisions
MeetingDecisionOutcome
19 Feb 2013 Minutes of the meeting held on 3rd october 2012RESOLVED that the minutes of the meeting held on 3 rd October 2012 be agreed. Agreed Open
19 Feb 2013 Matters arising from previous meetingsRESOLVED that matters arising be noted. Noted Open
19 Feb 2013 Analysis of staff leaversRESOLVED that the analysis of staff leavers be noted. Noted Open
19 Feb 2013 Environment improvement post completion report (lpsa reward grant)RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted. Noted Open
19 Feb 2013 Invest to saveRESOLVED that the progress of Invest to Save Schemes be noted. Noted Open