CAPITAL PROGRAMME MONITORING Q3 2011/12 AND ANNUAL CAPITAL REVIEW 2012 TO 2016

Approved Executive 2 papers

Executive, Resources and Contracts Policy Development and Scrutiny Committee approved this item on Wednesday 4 April 2012. Below is the council's own wording, with the papers it was decided on.

Item147a

Resolved

RESOLVED that the Resources Portfolio Holder be recommended to endorse the changes to the Resources Capital programme approved by the Executive.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive, Resources and Contracts Policy Development and Scrutiny Committee

Report No. London Borough of Bromley Agenda RES12054 Item No. PART 1 - PUBLIC

Decision Maker: Resources Portfolio Holder

For pre-decision scrutiny by the Executive & Resources PDS Committee on 4th April 2012 Date: 4th April 2012 Decision Type: Non-Urgent Non-Executive Non-Key

Title: CAPITAL PROGRAMME MONITORING Q3 2011/12 & ANNUAL CAPITAL REVIEW 2012 TO 2016

Contact Officer: Martin Reeves, Principal Accountant (Technical & Control) Tel: 020 8313 4291 E-mail: [email protected]

Chief Officer: Director of Resources

Ward: All

1. Reason for report

On 1st February, the Executive received a report summarising the current position on capital expenditure and receipts following the 3rd quarter of 2011/12 and presenting for approval the new capital schemes supported by Chief Officers in the annual capital review process. The Executive agreed a revised Capital Programme for the five year period 2011/12 to 2015/16. This report highlights in paragraphs 3.1 to 3.5 changes agreed by the Executive in respect of the Capital Programme for the Resources Portfolio. The revised programme for this portfolio is set out in Appendix A and detailed comments on individual schemes are included at Appendix B.

____________________________________________________________________________

2. RECOMMENDATION(S)

The Portfolio Holder is asked to endorse the changes approved by the Executive on 1st February.

1 Corporate Policy 1. Policy Status: Existing policy. Capital Programme monitoring and review is part of the planning and review process for all services. The capital review process requires Chief Officers to ensure that bids for capital investment provide value for money and match Council plans and priorities. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost N/A 2. Ongoing costs: N/A. 3. Budget head/performance centre: N/A (Capital Programme) 4. Total current budget for this head: £6.4m for the Resources Portfolio over five years 2011/12 to 2015/16 5. Source of funding: Capital grants, capital receipts and revenue contributions ________________________________________________________________________________ Staff 1. Number of staff (current and additional): N/A 2. If from existing staff resources, number of staff hours: N/A ________________________________________________________________________________ Legal 1. Legal Requirement: No statutory requirement or Government guidance. 2. Call-in: Call-in is not applicable. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): N/A ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments: N/A

2 3. COMMENTARY

Capital Expenditure

3.1A revised Capital Programme was approved by the Executive on 1st February, following a detailed monitoring exercise carried out after the 3rd quarter of 2011/12. The Executive also considered and approved new capital schemes supported by Chief Officers in the annual capital review process. This report identifies changes relating to the Resources Portfolio and the table in paragraph 3.2 summarises the overall position following the Executive meeting.

Capital Monitoring – Q3 variations approved by the Executive on 1st February 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING Q3 2011/12 AND ANNUAL CAPITAL REVIEW 2012 TO 2016Report 139 KB DownloadRead as text
PDF
ER PDS 040412 Capital Monitoring AppendicesReport 42 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING Q3 2011/12 AND ANNUAL CAPITAL REVIEW 2012 TO 2016This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. Capital programme monitoring - quarter 1 2026/27Decided
  4. 2026/27 q1 capital programme monitoringNoted
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 1 2026/27Decided

More from Bromley Executive, Resources and Contracts Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Matters outstanding and work programmeThat the report be noted. Noted Open
14 Sep 2026 Capital programme monitoring - quarter 1 2026/27That the recommendations be supported. Decided Open
14 Sep 2026 Pre-decision scrutiny of executive reportsThat the recommendations be supported. (6) CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27 Report FSD26037 The repor... Noted Open
14 Sep 2026 Corporate contracts registerThat the report be noted. Noted Open
14 Sep 2026 Risk registersThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies