CAPITAL PROGRAMME MONITORING Q3 2012/13 AND ANNUAL CAPITAL REVIEW 2013 TO 2017

Agreed Scrutiny 2 papers

Environment and Community Services Policy Development and Scrutiny Committee agreed this item on Tuesday 5 March 2013. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

RESOLVED that the changes agreed by the Executive on 6 th February 2013 be noted.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Environment and Community Services Policy Development and Scrutiny Committee

Recommendation

The Committee is asked to note the changes agreed by the Executive on 6th February.

1 Corporate Policy 1. Policy Status: Existing Policy: Capital Programme monitoring and review is part of the planning and review process for all services. The capital review process requires Chief Officers to ensure that bids for capital investment provide value for money and match Council plans and priorities. 2. BBB Priority: Excellent Council; Quality Environment ________________________________________________________________________________ Financial 1. Cost of proposal: Not Applicable 2. Ongoing costs: Not Applicable 3. Budget head/performance centre: N/A (Capital Programme) 4. Total current budget for this head: £31.9m for the Environment Portfolio over five years 2012/13 to 2016/17 5. Source of funding: Capital grants, capital receipts and earmarked revenue contributions ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 0.25 fte 2. If from existing staff resources, number of staff hours: 9 hours per week ________________________________________________________________________________ Legal 1. Legal Requirement: Non-Statutory - Government Guidance 2. Call-in: Not Applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): N/A ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No 2. Summary of Ward Councillors comments: N/A

2 3. COMMENTARY

Capital Expenditure

3.1A revised Capital Programme was approved by the Executive on 6th February, following a detailed monitoring exercise carried out after the 3rd quarter of 2012/13. The Executive also considered and approved new capital schemes supported by Council Directors in the annual capital review process. This report identifies changes relating to the Environment Portfolio and the table in paragraph 3.2 summarises the overall position following the Executive meeting.

Capital Monitoring – variations agreed by the Executive on 6th February 2013

3.2The base position prior to the 3rd quarter’s monitoring exercise was the revised programme approved by the Executive on 24th October 2012, as amended by variations approved at subsequent Executive meetings. Changes to the Environment Portfolio Programme approved by the Executive in February are shown in the table below and further details are included in paragraphs 3.3 to 3.5. The revised Programme for the Environment Portfolio is attached as Appendix A and detailed comments on individual schemes are included at Appendix B.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING Q3 2012/13 AND ANNUAL CAPITAL REVIEW 2013 TO 2017Report 187 KB DownloadRead as text
PDF
Enc. 1 for CAPITAL PROGRAMME MOMITORING Q3 2012/13 & ANNUAL CAPITAL REVIEW 2013 TO 2017Report 64 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING Q3 2012/13 AND ANNUAL CAPITAL REVIEW 2013 TO 2017This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. Capital programme monitoring - quarter 1 2026/27Decided
  4. 2026/27 q1 capital programme monitoringNoted
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 1 2026/27Decided

More from Bromley Environment and Community Services Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
17 Jun 2026 MINUTES OF THE MEETING HELD ON 17th MARCH 2026RESOLVED that the minutes of the meeting that took place on 17 th March 2026 be noted and agreed as a correct record. Noted Open
17 Jun 2026 Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding... Noted Open
17 Jun 2026 Update from the portfolio holder for transport, highways and road safetyRESOLVED that the update from the Portfolio Holder for Transport, Highways and Road Safety be noted. Noted Open
17 Jun 2026 Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a... Noted Open
17 Jun 2026 Draft Air Quality Action Plan 2026-2031: Consultation and Implementation (TO FOLLOW)RESOLVED that: 1) The draft AQAP 2026-2031 be subject to public and stakeholder consultation for a period of six week... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies