CAPITAL PROGRAMME MONITORING Q3 2013/14 & ANNUAL CAPITAL REVIEW 2014 TO 2018

Noted Executive 2 papers

Executive noted this item on Wednesday 12 February 2014. Below is the council's own wording, with the papers it was decided on.

Item294

Resolved

RESOLVED that: (1) Report FSD14015 be noted, including the re-phasing of a total of £12,447k from 2013/14 into later years (see paragraph 3.3.7 of the report) and a revised Capital Programme agreed; (2) the following amendments to the Capital Programme be approved – ( i ) addition of a total of £42,302k in respect of DfE Basic Need capital grant allocations for 2015/16 and 2016/17 (see para 3.3.1 of Report FSD14015); (ii) addition of £387k in 2014/15 for new DfE Free School Meals capital grant (see para 3.3.2 of Report FSD14015); (iii) reduction of £843k in 2013/14 to reflect revised grant support from Transport for London for highway schemes (see para 3.3.3 of Report FSD14015); (iv) deletion of £21k in 2013/14 in respect of the completed Station Road Car Park scheme (see para 3.3.4 of Report FSD14015); (v) addition of £1,232k in respect of the revenue-funded Bromley MyTime Investment Fund (see para 3.3.5 of Report FSD14015); (vi) addition of £110k in 2014/15 for the refurbishment of the Newstead Wood Tennis Centre, funded by a virement from the underspend on the Pavilion Leisure Centre scheme (£50k) and contributions of £30k from both the LTA and Newstead Wood School (see para 3.3.6 of Report FSD14015); and (3) Council be recommended to include the new scheme proposals supported by Chief Officers (listed at Appendix C to Report FSD14015) in the ... view the full minutes text for item 294.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Recommendations

The Executive is requested to: (a) Note the report, including the rephasing of a total of £12,447k from 2013/14 into later years (see paragraph 3.3.6) and agree a revised Capital Programme; (b) Approve the following amendments to the Capital Programme: (i) Addition of a total of £42,302k in respect of DfE Basic Need capital grant allocations for 2015/16 and 2017/18 (see para 3.3.1);

(ii) Addition of £387k in 2014/15 for new DfE Free School Meals capital grant (see para 3.3.2);

1 (iii) Reduction of £843k in 2013/14 to reflect revised grant support from Transport for London for highway schemes (see para 3.3.3);

(iv) Deletion of £21k in 2013/14 in respect of the completed Station Road Car Park scheme (see para 3.3.4);

(v) Addition of £1,232k in respect of the revenue-funded Bromley MyTime Investment Fund (see para 3.3.5);

(vi) Addition of £110k in 2014/15 for the refurbishment of the Newstead Wood Tennis Centre, funded by a virement from the underspend on the Pavilion Leisure Centre scheme (£50k) and contributions of £30k from both the LTA and Newstead Wood School (see para 3.3.6); and

(c) Recommend to Council that the new scheme proposals supported by Chief Officers (listed in Appendix C) be included in the Capital Programme, subject to a fully costed feasibility study on one scheme (the Upgrade/replacement of SharePoint Productivity Platform) being approved by the Resources Portfolio Holder.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING Q3 2013/14 & ANNUAL CAPITAL REVIEW 2014 TO 2018Report 168 KB DownloadRead as text
PDF
Exec 120214 Part 1 Capital Monitoring-Review AppendicesReport 98 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING Q3 2013/14 & ANNUAL CAPITAL REVIEW 2014 TO 2018This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. Capital programme monitoring - quarter 1 2026/27Decided
  4. 2026/27 q1 capital programme monitoringNoted
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 1 2026/27Decided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies