Cabinet: 1. Approved the use of the YPO Energy Framework Agreement to administer the purchase and supply of the Council’s corporate electricity contract for the period 1 April 2023 to 31 March 2027 (at an annual cost of circa £7m per annum). The total estimated contract value will be circa £28m over a four-year period, with options to extend to 2029 and 2031. (The annual and total contract value may change significantly as current energy prices have been significantly affected by the conflict in Ukraine); 2. Approve the use of YPO’s appointed framework supplier, Npower Business Solution, for the supply of electricity through the framework duration; and 3. Provide delegated authority to the Executive Director of Operations and Executive Director of Finance, in consultation with the portfolio lead for Corporate Affairs and HR, to award the contract and facilitate the execution, implementation, and operation of the contract.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Procurement Outcome Report Framework 1100 – Electricity and Ancillary Services
Purpose
This document provides customers with information regarding the recent retendering of YPO’s Electricity and Ancillary Services.
Details contained in this report provide background information regarding the procurement activity and outcomes and can assist customers in securing any internal approvals to proceed. Additionally, next steps are identified to assist customers with accessing the contract.
Framework Information
The Framework is for the Supply of Electricity and Ancillary Services for use by any public sector or not-for- profit organisation. It is designed to meet the needs of YPO and other Contracting Authorities by establishing a lead agreement between YPO and the successful supplier; with the Contracting Authority electing to call off this agreement with themselves and the successful supplier.
Contracting Authorities will have a choice of a Flexible contract with selected purchasing strategies, Fixed Price (Wholesale price fixed, Metering and transportation on pass through) and Fully Fixed (Commodity and Non- Commodity charges are fixed).
This procurement activity establishes the YPO Framework Agreement 1100 Supply of Electricity and Ancillary Services which replaces YPO Framework 791 Flexible Procurement and Supply of Electricity.
This is an eight-year framework with Npower for the period 1st April 2023 - 31st March 2031. There will be an initial framework duration of four years with two additional two-year extension options. The commercial approach to establish a longer-term contractual arrangement with the successful supplier is to ensure deeper support for Contracting Authorities Net Zero programmes, as one of the biggest contributors to carbon emissions is energy consumption. Power Purchase Agreements (PPAs) will form part of this framework, to get the maximum benefit from this type of agreement.
Additionally, Wholesale electricity prices are currently at the highest ever and having a longer-term contractual arrangement, will allow for YPO to operate an enhanced trading strategies that reflect the changing world economic climate and minimise the risk of sleeving complexity to another provider.
The procurement activity was designed to appoint a supplier around a year in advance of the end of the current framework to allow for prompt Contracting Authority sign up and for YPO to run effective wholesale trading procurement strategies.
The Framework has one lot and appointed a sole supplier – Npower, who is also the existing supplier. There is no requirement for eligible customers to take part in a further competition and direct award is the method of appointment.
Procurement Activity
1 The procurement activity commenced in Winter 2021 with customer involvement through the Energy Initiatives Steering Group (EISG). Supplier engagement commenced shortly afterwards with suppliers invited to present to YPO. Topics the suppliers presented on included customer service, trading, billing, social value and corporate social responsibility and functionality of their web portal.
The Invitation to Tender was issued on 25/02/2022, with prospective suppliers given a 6-week response window to submit their responses through the YPO Proactis e-tendering portal. The closure date for tender submissions was originally set as 04/04/2022, however this was extended until 06/04/2022 following clarifications.
The tender consisted of the following sections:
Standard Selection Questionnaire (SQ) and Additional Selection Questions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.