Bury Metropolitan Borough Council
Cabinet, Wednesday 7 September 2022 at 6.00pm

Secondary School Provision in Radcliffe - Financial approval to Council's funding obligations - additional site costs - Part A

Approved Executive 1 paper

Cabinet approved this item on Wednesday 7 September 2022. Below is the council's own wording, with the papers it was decided on.

ItemCA.52

Resolved

Cabinet: 1. Approved the funding of indicative costs as set out in Part B of this report, to meet the Council’s financial obligations, to be met from the Children’s Services schools capital programme; and 2. Delegated approval of the finalised costs to the Executive Director of Finance.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1On the 13 th July Cabinet received a report setting out the Council’s financial obligations in respect of the delivery of the new secondary school in Radcliffe. At that meeting, Members agreed to the recommendation to fund works from the schools capital budget to allow the project to proceed. In July Cabinet agreed to delegate approval to the Executive Director of Finance, once final costs where known, based on the indicative co sts provided by the Department for Education (DfE).

1.2Since the report to cabinet in July we have been informed by the DFE that there are additional costs which were not identified in that report It has subsequently become evident that the indicative costs provided by the DfE did not include all of the elements that would ordinarily fall to the Council.

1.3A condition of the Government’s Free School Programme is that local authorities meet the cost of any additional site-specific costs necessary to deliver the project. These costs were omitted from the initial submission from the DfE.

1.4The DfE commissioned a feasibility study in respect of the Spring Lane site to determine indicative costs of delivery of the overall project, and high- level designs. This study determined to full cost of the project, the majority of which will be met by the DfE, but included additional costs relating to the provision of an access road, and the remediation of the site, including demolition of the existing buildings. These latter two elements were subject to the report to Cabinet on the 13 th July.

1.5The study also identified a number of site-specific costs in relation to the development of the site, largely relating to the existence of former coal mine workings in the area, which impact on the construction of the building. The Council was not initially notified about these costs but accepts that they should be met by the Council, -

1.6A detailed breakdown of these additional costs has been provided by the DfE. These costs have been reviewed by officers, and confirm these costs will be subject to further scrutiny as soon as final tender costs are available. 1.7 The Council is required to commit to meet those costs before the scheme can proceed to the next phase. The next phase will see detailed design work undertaken.

1.8As costs will remain indicative until detailed tender submissions are received by DfE, approval is sought from Cabinet to those indicative costs, and to requests that Member delegate authority to the Executive Director of Finance to agree finalised costs once determined.

1.9The additional indicative costs falling to the Council are set out in Part B to this report.

1.10Provision has been made within the Children’s Service schools capital programme to meet these financial obligations. The costs already identified in the report to Cabinet on the 13 th July, together with these additional costs are in line with the provisional sum identified for the project from the outset.

1.11The DfE has provided further detail of its programme for delivery of the project, with work ongoing to select a contractor, and formal appointment of the preferred contractor expected by end of October 2022.

1.12Detailed design will then follow, including stakeholder engagement in the design process, leading to a start on site in July 2023.

1.13As previously reported, this start on site date will require DfE to be provided with access to the full Spring Lane site, including land currently occupied by the Pupil Referral Unit (Spring Lane School), and the Radcliffe Leisure Centre.

1.14At its meeting on 7 th September 2022, Cabinet will also receive a report setting out the arrangements to facilitate the relocation of the Pupil Referral Unit, and seeking financial approval to those arrangements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Secondary School Provision in Radcliffe: Financial approval to Council's funding obligations: additional site costs: Part ADecisions 478 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 22 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, apologies
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
GL
Geoff LittleChief Executive, in attendance
SE
Sam EvansOfficer, in attendance
JD
Jacqui DennisOfficer, in attendance
PB
Philippa BraithwaiteOfficer, in attendance

All 22 on the meeting page

On this subject at Bury

Search all
  1. Secondary School Provision in Radcliffe - Financial approval to Council's funding obligations - additional site costs - Part AThis decision
  2. Delivery of a new SEMH Secondary Special School - Land proposal to Department for Education (DfE) & Oak Learning PartnershipApproved
  3. Proposals to alter the upper age range at Manchester Mesivta Secondary SchoolNoted
  4. Changes to Admission Arrangements for Secondary SchoolsApproved
  5. Secondary School Provision in Radcliffe - Financial approval to Council's funding obligations - Part ANoted
  6. Changes to Admission Arrangements for Secondary SchoolsApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies