Cabinet: 1. Approved the funding of indicative costs as set out in Part B of this report, to meet the Council’s financial obligations, to be met from the Children’s Services schools capital programme; and 2. Delegated approval of the finalised costs to the Executive Director of Finance.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1On the 13 th July Cabinet received a report setting out the Council’s financial obligations in respect of the delivery of the new secondary school in Radcliffe. At that meeting, Members agreed to the recommendation to fund works from the schools capital budget to allow the project to proceed. In July Cabinet agreed to delegate approval to the Executive Director of Finance, once final costs where known, based on the indicative co sts provided by the Department for Education (DfE).
1.2Since the report to cabinet in July we have been informed by the DFE that there are additional costs which were not identified in that report It has subsequently become evident that the indicative costs provided by the DfE did not include all of the elements that would ordinarily fall to the Council.
1.3A condition of the Government’s Free School Programme is that local authorities meet the cost of any additional site-specific costs necessary to deliver the project. These costs were omitted from the initial submission from the DfE.
1.4The DfE commissioned a feasibility study in respect of the Spring Lane site to determine indicative costs of delivery of the overall project, and high- level designs. This study determined to full cost of the project, the majority of which will be met by the DfE, but included additional costs relating to the provision of an access road, and the remediation of the site, including demolition of the existing buildings. These latter two elements were subject to the report to Cabinet on the 13 th July.
1.5The study also identified a number of site-specific costs in relation to the development of the site, largely relating to the existence of former coal mine workings in the area, which impact on the construction of the building. The Council was not initially notified about these costs but accepts that they should be met by the Council, -
1.6A detailed breakdown of these additional costs has been provided by the DfE. These costs have been reviewed by officers, and confirm these costs will be subject to further scrutiny as soon as final tender costs are available. 1.7 The Council is required to commit to meet those costs before the scheme can proceed to the next phase. The next phase will see detailed design work undertaken.
1.8As costs will remain indicative until detailed tender submissions are received by DfE, approval is sought from Cabinet to those indicative costs, and to requests that Member delegate authority to the Executive Director of Finance to agree finalised costs once determined.
1.9The additional indicative costs falling to the Council are set out in Part B to this report.
1.10Provision has been made within the Children’s Service schools capital programme to meet these financial obligations. The costs already identified in the report to Cabinet on the 13 th July, together with these additional costs are in line with the provisional sum identified for the project from the outset.
1.11The DfE has provided further detail of its programme for delivery of the project, with work ongoing to select a contractor, and formal appointment of the preferred contractor expected by end of October 2022.
1.12Detailed design will then follow, including stakeholder engagement in the design process, leading to a start on site in July 2023.
1.13As previously reported, this start on site date will require DfE to be provided with access to the full Spring Lane site, including land currently occupied by the Pupil Referral Unit (Spring Lane School), and the Radcliffe Leisure Centre.
1.14At its meeting on 7 th September 2022, Cabinet will also receive a report setting out the arrangements to facilitate the relocation of the Pupil Referral Unit, and seeking financial approval to those arrangements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.