Cabinet: 1. Approved the proposed scope of the enabling works to be undertaken by Vinci Construction; 2. Accepted the tender report recommendation that Vinci Construction undertake this works package at the contract sum set out in Part B of this report; 3. Delegated finalisation of the contract amendments and clarifications to the Director of Law and Governance; and 4. Approved the contingency allowances (set out in Part B) to account for potential cost increases.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1The purpose of this report is to advise Cabinet of the works packages that, in accordance with the Radcliffe Hub project programme, now need to be instructed via an enabling works contract. The relevant reports, drawings and programme that inform these works are appended to Part B of this paper.
1.2In order for the Council and Vinci Construction to transition from the Pre- Construction Service Agreement (PCSA) into the Main Contract, an enabling works period is proposed to facilitate the delivery of various preparatory works, thus ensuring the site is ready for development.
1.3Works included within the proposed enabling works contract, have been market tested and independently verified, and a copy of the tender report is appended to Part B of this paper.
1.4This proposal aligns with the cashflow spending commitments outlined in the previously agreed Levelling Up Fund Memorandum of Understanding (MOU), and ensures the project is complaint with the stipulation that all monies awarded from the fund are fully defrayed by March 2025.
1.5Since confirmation of the Levelling Up funding award in October 2021, the project has been subject to a quarterly reporting cycle to the Department of Levelling Up, Housing & Communities (DHLUHC). The proposed cashflow forecast, programme and risk management plan outlined in these returns, has consistently reflected a construction programme phased to enable preparatory works to be delivered under a separate contract, with works commencing in May 2023.
2. Recommendation(s)
2.1Cabinet to recommend to:
Approve the proposed scope of the enabling works to be undertaken by Vinci Construction. Accept the tender report recommendation that Vinci Construction undertake this works package at the contract sum set out in Part B of this report Delegate finalisation of the contract amendments and clarifications to the Director of Law and Governance. Approve the contingency allowances (set out in Part B) to account for potential cost increases.
3. Reasons for recommendation(s)
3.1Development Site The development site identified for the Hub project in Radcliffe town centre, includes several assets that will need to be demolished and cleared, and remedial works undertaken, in order for the main construction and refurbishment work to be carried out. Whilst the delivery of a vacant possession strategy will ensure that the South Block and Market Chambers buildings are no longer occupied and all units are empty by April 2023, Radcliffe Market will remain operational throughout the proposed construction period.
These key considerations have informed both the scope and methodology for carrying out the works, and the phasing of the construction programme and including the enabling period.
3.2Programme The project programme has been informed by four core elements:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.