Cabinet: 1. Accepted the tender report recommendation that Vinci Construction undertake this main works package at the contract sum set out in Part B of this report, subject to the agreement of the contract amendments and clarifications; and 2. Delegated finalisation of contract amendments and clarifications to the Director of Law and Governance in consultation with the Executive Director of Place.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1The purpose of this report is to advise Cabinet of the works packages that, in accordance with the Radcliffe Hub project programme, now need to be instructed via the Main Works Contract. The relevant drawings and programme that inform these works are appended to Part B of this paper.
1.2Works included within the proposed Main Works Contract, have been market tested and independently verified, and a copy of the tender report is appended to Part B of this paper.
1.3The Main Works Contract will encompass and supersede the Enabling Works Contract which was given Cabinet approval in April 2023.
1.4This proposal aligns with the cashflow spending commitments outlined in the Levelling Up Fund MOU, and ensures the project is complaint with the stipulation that all monies awarded from the fund are fully defrayed by March 2025.
1.5Since confirmation of the Levelling Up funding award in October 2021, the project has been subject to a quarterly reporting cycle to the Department of Levelling Up, Housing & Communities (DLUHC). The proposed cashflow forecast, programme and risk management plan outlined in these returns, has consistently reflected a construction programme phased to enable preparatory works to be delivered under a separate contract, with works commencing in May 2023. Recommendation(s)
It is recommended that Cabinet: 2.1 Accept the tender report recommendation that Vinci Construction undertake this main works package at the contract sum set out in Part B of this report, subject to the agreement of the contract amendments and clarifications.
2.2Delegate finalisation of contract amendments and clarifications to the Director of Law and Governance in consultation with the Executive Director of Place. Reasons for recommendation(s)
3.1Approval of the main contract is required in order for the Radcliffe Hub and Market Chambers project to progress to a construction phase. Key considerations within this document have informed both the scope and methodology for carrying out construction works alongside the phasing of the construction programme. Alternative options considered and rejected. 4.1 Delay instructing the Main Works Contract: This would delay the overall Radcliffe Hub completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would increase the period that leisure services would be housed in temporary accommodation within Radcliffe, attracting additional costs. It would also delay occupation of commercial units within the Market Chambers and trading within these refurbished spaces; further disrupting businesses and reducing commercial income to the Council. Furthermore, the delay incurred would erode confidence in the town that the project is being delivered as a key strategic priority for the Council. Any delay to the overall project critical path increases the risk that LUF monies will not be defrayed in line with agreements made between Bury Council and the DLUHC.
4.2The main works scheduled to progress on site on completion of the enabling contract works, thus delay in transition from one package into the other will result in downtime on site and attract additional preliminary costs.
________________________________________________________ Report Author and Contact Details:
Name: Ian D’Arcy Position: Major Projects Manager Department: Business Growth and Infrastructure E-mail: [email protected]
Name: Robert Summerfield Position: Assistant Director: Regeneration Delivery Department: Business Growth and Infrastructure E-mail: [email protected] ________________________________________________________________ Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.