Cabinet: 1. Approved £367,000 match funding from Council budgets plus an agreement to meet the £78,577 shortfall bringing the total Council contribution to £445,577 in order to secure £1,270,423 of UKSPF funding towards the development of Radcliffe Enterprise Centre; 2. Noted the timescale constraints and the options being considered for the temporary relocation of the library and Radcliffe Integrated Neighbourhood Team; and 3. Noted the legal position regarding the positive covenants affecting the use of the current library building and the mitigation measures proposed.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Date: 06 September Report to: Cabinet 2023 Subject: Radcliffe Enterprise Centre – UKSPF Project Delivery (E22) Report of Leader and Cabinet Member for Strategic Growth
Summary 1. Bury Council submitted a bid to GM’s UKSPF SME (Small and Medium Size Enterprises) Workspace Fund (E22) to turn Radcliffe Library into an enterprise centre. Following evaluation of all bids, GMCA have confirmed the overall funding ask from all 10 GM authorities exceeds the level of funding available and have therefore revised the funding allocation for Bury to £1,270,423 or 92.4% of the total project cost of £1,716,000. The total project cost includes match funding from the Council of £367,000. 2. Revised timescales requiring project completion by March 2025 present a number of issues around the temporary relocation of the library and Radcliffe Integrated Neighbourhood Team who currently operate from the first floor of the building. Several options are currently being considered to resolve and mitigate these risks. Full details are outlined below. Recommendations
It is recommended that Cabinet: 3. Confirm £367,000 match funding from Council budgets plus an agreement to meet the £78,577 shortfall bringing the total Council contribution to £445,577 in order to secure £1,270,423 of UKSPF funding towards the development of Radcliffe Enterprise Centre. 4. Note the timescale constraints and the options being considered for the temporary relocation of the library and Radcliffe Integrated Neighbourhood Team. 5. Note the legal position regarding the positive covenants affecting the use of the current library building and the mitigation measures proposed. Reasons for Recommendation 6. Given the reduced timescales it is now imperative that this project moves forward. GMCA require confirmation of match funding in order to issue the grant funding agreement. Whilst a number of key approvals for expenditure have been undertaken at risk whilst the GFA is prepared (the appointment of a Project Manager and additional consultancy resource). The agreement must be in place by September 2023 to enable the project to move into RIBA Stage 2 - Concept design. Alternative options considered and rejected
7. Return the allocation of £1.4m to the GMCA to be spent elsewhere in Greater Manchester - Not recommended.
This option would have the benefit of the Council not having to find an immediate capital contribution for the facility and would allow the library to move into the Hub in a seamless manner. It is fully recognised that the Council is having to prioritise its capital programme, and this constitutes a further call on scarce resources, and, at the present time, there is no agreed solution for the temporary library provision (although there are options for consideration). However, The Council would be left holding the library as an empty building once the Hub is activated and would remain liable for the costs of securing the building, such as installing steel sheets to the windows and doors. The Council would also have to maintain a security regime. The costs of this, based on similar buildings, is likely to be between £30k and £50k per-annum, with escalating costs for maintaining the structure as wind and waterproof. 8. Re-allocate funding to an alternative project/use - Not a viable option
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.