Cabinet: 1. Approved the proposed route to tender for the construction of the Enterprise Centre via the North West Construction Hub (NWCH) framework. 2. Noted that a further report will be brought back to the September Cabinet meeting to approve the appointment of the preferred contractor. Reasons for decision(s): This a UKSPF funded project and is subject to strict timescales for completion. The project is progressing through the RIBA Stages and is currently on track. However, a delay in appointment of a contractor could significantly impact on progress leading to a failure to complete on schedule, bringing financial and reputational risk to the Council. Alternative options considered and rejected Classification: 1. Delaying the decision to appoint a contractor has been discounted as this will significantly impact on the construction programme and risk non completion within the funding timescales.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
This report seeks permission to tender for a contractor to undertake the construction works required for the conversion of Radcliffe Library into an Enterprise Centre as part of the GM’s UKSPF (UK Shared Prosperity Fund) SME (Small and Medium Size Enterprises) Workspace Fund (E22). The contractor will be appointed via the North West Construction Hub (NWCH) framework.
Stage 3 designs are now under review and planning application for change of use and internal remodelling have been submitted. Should 3 or more objections be made the matter will go to Planning committee on 26 th June 2024.
Initial project costings suggest a construction cost in the region of £1.4m. (This excludes professional fees, surveys, inflation, etc). This is within the funding envelope although final costs will not be known until stage 4 designs have been evaluated and the work has been issued for tender.
Construction is due to commence in September 2024 in accordance with the funding requirements, must be completed by 31st March 2025. Should the Council fail to spend the funding before the 31st March 2025 there is a risk the Council will be liable for full project costs due to a clawback clause within the funding agreement.
Recommendation(s)
1. That Cabinet approve the proposed route to tender for the construction of the Enterprise Centre via the North West Construction Hub (NWCH) framework. A further report will be brought back to the September Cabinet meeting to approve the appointment of the preferred contractor.
Reasons for recommendation(s) 2. This a UKSPF funded project and is subject to strict timescales for completion. The project is progressing through the RIBA Stages and is currently on track. However, a delay in appointment of a contractor could significantly impact on progress leading to a failure to complete on schedule, bringing financial and reputational risk to the Council. Alternative options considered and rejected 3. Delaying the decision to appoint a contractor has been discounted as this will significantly impact on the construction programme and risk non completion within the funding timescales. _________________________________________________________ Report Author and Contact Details: Name: Sarah Porru Position: Assistant Director of Regeneration (Business & Economy) Department: Business, Growth & Investment E-mail: [email protected] ________________________________________________________________ Background 4. In 2022, Bury Council submitted a bid to GM’s UKSPF SME (Small and Medium Size Enterprises) Workspace Fund (E22) to turn Radcliffe Library into an enterprise centre.
4.1The project aims to convert Radcliffe Library, located within Radcliffe Town Centre and adjacent to the Levelling Up regeneration activity (part of the Radcliffe Regeneration Framework) to a flexible, multi-functional Enterprise Centre. The space will provide a range of private offices and bookable hot desks to facilitate up to 100 occupiers and will be managed by a third-party operator.
4.2The UKSPF funding allocation for Bury to £1,270,423 or 92.4% of the total project cost of £1,716,000. The total project cost includes match funding of £445,577. This commitment from the Council was agreed by the Regeneration Board on 27th October 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.