DECISION:- · Cabinet approve the award of a contract to the winning bidder AB Electrical and Building Ltd for the initial period to 31 March 2025 with the option to extend for a further 12 months until March 2026 at a value of £920,000. · Cabinet delegate finalisation of the terms of the contract to the Director of Law and Democratic Services in consultation with the Executive Director (Strategy & Transformation). Reasons for recommendation(s): Tenders were received from six contractors through the Procure Plus electrical framework, the tender was on a price and quality basis, it was procured through a mini competition. The winning bidder scored highest overall in the evaluation process. The evaluation of the tenders was carried out on a 70:30 price and quality/social value basis. Corporate Procurement, (via STAR Procurement) has reviewed and is satisfied with the approach taken and the outcome.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Date: 25 September Report to: Cabinet 2024 Subject: Procurement of LD2 smoke alarms in relation to FRA compliance works. Report of Cabinet Member for Housing Services
Summary The purpose of this report is to seek formal approval of a contract award recommendation following completion of the competition exercise carried out through the Procure Plus framework, the Capital Programme was approved in July 2024 with FRA works being identified within the programme. The regulator requires the stock to be upgraded in line with current regulations, Pennington Choices Limited carried out a full review of general needs and sheltered blocks which identified a range of works necessary to ensure compliance, the LD2 smoke detection upgrade works are within the scope to complete.
The works will be carried out to flats within the 270 blocks, owned and managed by Bury Council, the contract will be managed through Sustainability and Investment team.
Recommendation(s) Cabinet is asked to: 1. Approve the award of a contract to the winning bidder AB Electrical and Building Ltd for the initial period to 31 March 2025 with the option to extend for a further 12 months until March 2026 at a value of £920,000. 2. Delegate finalisation of the terms of the contract to the Director of Law and Democratic Services in consultation with the Executive Director (Strategy & Transformation).
Reasons for recommendation(s) Tenders were received from six contractors through the Procure Plus electrical framework, the tender was on a price and quality basis, it was procured through a mini competition. The winning bidder scored highest overall in the evaluation process. The evaluation of the tenders was carried out on a 70:30 price and quality/social value basis.
Corporate Procurement, (via STAR Procurement) has reviewed and is satisfied with the approach taken and the outcome. Alternative options considered and rejected 1. Do nothing: Due to the nature of the works (compliance work as identified by the FRA reports), the works need to be completed to ensure Burys general needs stock is compliant with the current regulations. 2. Deliver Inhouse: The works were originally offered to the in house contractor but they were unable to deliver due to lack of capacity. 3. Open Tender: This option was considered and is possible, however this would involve significantly more time and costs in the procurement process as a whole and for no real benefit. The use of this framework is free and ensures that all suppliers have been evaluated and approved based on their capabilities, expertise, and compliance within required criteria along with pre- negotiated terms and conditions. Further competition exercise enabled the council to tailor the service requirements to the Council’s specific needs. There is little or no benefits to going out to open tender over using this framework and as a result this option was dismissed. _________________________________________________________ Report Author and Contact Details: Name: Neil Higson Position: Home Improvement Manager Department: Sustainability and Investment E-mail: [email protected] ________________________________________________________________ Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.