DECISION:- · Cabinet approved the direct award of a contract to through the Crown Commercial Services (CCS) G-Cloud 13 framework for the continued use of the Enterprise Resource Planning (ERP) Financial Management System for a period of three years from 1st January 2025 with the option to extend for a further period of one year at the discretion of the Council. · Cabinet delegated finalisation of the terms of the direct award including any clarifications to the Director of Law and Democratic Services in consultation with the Director of Finance and the Cabinet Member for Finance and Transformation. Reasons for recommendation(s): The Council has a legal obligation to have in place a financial management system to ensure that appropriate accounting records, management accounting functions and financial controls are in place so that finances are kept under review on a regular basis.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Date: 25 September Report to: Cabinet 2024 Subject: Unit 4 Contract Report of Cabinet Member for Finance and Transformation
Summary 1. The Council’s current Enterprise Resource Planning (ERP) Financial Management system is supplied by Unit 4 (formerly Agresso Business World Software). The initial contract was signed back in 2004 and implemented for use by the Council from April 2006 onwards.
2. In October 2023, Unit 4 wrote to inform all customers of their strategic decision to provide only a SaaS (Software as a Service) solution with effect from 1 January 2025. Additionally, existing on-premises solutions will only remain fully supported by Unit 4 until 31 December 2024, unless the Council informs Unit 4 by 31 December 2024 of their intention to move to the Cloud, in which case a 2-year grace period will be given to enable the Council to transition to the Cloud, subject to the Council renewing their existing contract before 31 December 2024.
3. Following initial discussions with the Unit 4 Account Manager on the options available to the Council and future pricing, it was decided to undertake an ‘Optimisation Review’ of the current system, this required bringing on-board a strategic partner to provide consultancy support to undertake the ‘Optimisation Review’.
4. The move to a new cloud-based Unit 4 ERP Financial Management System is a key part of the Council’s transformation and improvement journey, building on improvements already made through the adoption of Let’s do it principles and implementation of the digital strategy, including the roll-out of Microsoft 365 council wide, the upgrade of I-Trent and rationalisation of applications and migration. Some of the anticipated benefits of the Unit 4 upgrade are outlined in the report and will both directly support and enable the transformation of the finance service as well as providing much more efficient and effective ways of working for the council as a whole, with the detailed business case in the process of being completed.
Recommendation(s)
5. Cabinet is asked to:
Approve the direct award of a contract to Unit 4 through the Crown Commercial Services (CCS) G-Cloud 13 framework for the continued use of the Unit 4 Enterprise Resource Planning (ERP) Financial Management System for a period of three years from 1st January 2025 with the option to extend for a further period of one year at the discretion of the Council.
Delegate finalisation of the terms of the direct award including any clarifications to the Director of Law and Democratic Services in consultation with the Director of Finance and the Cabinet Member for Finance and Transformation.
Reasons for recommendation(s)
6. The Council has a legal obligation to have in place a financial management system to ensure that appropriate accounting records, management accounting functions and financial controls are in place so that finances are kept under review on a regular basis.
Alternative options considered and rejected
7. Alternative options were considered but rejected as follows: The ‘do nothing’ option, is not an option due to Unit 4 not supporting the current on-premises solution from 1 January 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.