The Cabinet: 1. Award Rethink Mental Illness a 3-year contract for the mental health supported living tender for the Topping Mill scheme. 2. Enter a 3-year arrangement (July 2025 to Jun 2028), with an option to extend for +1 year and +1 year, subject to performance and review. 3. Delegate finalisation and sealing of this contract, including any clarification, to the Director of Law and Democratic Services in consultation with the Executive Director for Health and Care. Reason for the decision: The Bury Housing with Additional Needs Strategy and Market Position Statement analysed the existing provision of mental health supported accommodation services and predicted the growth needed to meet future demands. The Market Position Statement indicates that an extra 86 units of mental health supported accommodation is needed by 2025. Our commissioning intentions are to increase the provision of self-contained supported accommodation and reduce the number of units offering shared supported accommodation. The proposed scheme at Topping Mill offers ‘own front door’ apartments. The proposed model for Topping Mill will offer medium term support for up to 5 years, supporting people to develop person-centred recovery towards greater independent living. The scheme will improve wider system flow creating accommodation and support options for people who are clinically ready for discharge from hospital, the scheme will offer 24/7 supported living and will fill a deficit in local provision. A competitive procurement process has been completed to identify the most suitable care provider for this new scheme. Other options considered and rejected: The Public Procurement Contracts Regulations 2015 do not allow for light touch or direct award in this case.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1. Following the Topping Mill Supported Living Cabinet report dated 7 November 2023, approval was given to the Community Commissioning Division to engage in a competitive procurement process to appoint a provider for the provision of mental health support at Topping Mill, Topping St, Bury, BL9 6DR. After review and procurement, this report requests the approval for the Division to award a contract to a care provider.
2. The mental health supported living scheme will provide high specification accommodation for 14 people (18+ years) in self-contained apartments with support 24/7 from a team of staff to support their mental health and individual goals. Recommendation(s)
3. The recommendation is for Cabinet to:
(a) Award Rethink Mental Illness a 3-year contract for the mental health supported living tender for the Topping Mill scheme. (b) Enter a 3-year arrangement (July 2025 to Jun 2028), with an option to extend for +1 year and +1 year, subject to performance and review. (c) Delegate finalisation and sealing of this contract, including any clarification, to the Director of Law and Democratic Services in consultation with the Executive Director for Health and Care. Reasons for recommendation(s) 4. The Bury Housing with Additional Needs Strategy and Market Position Statement analysed the existing provision of mental health supported accommodation services and predicted the growth needed to meet future demands. The Market Position Statement indicates that an extra 86 units of mental health supported accommodation is needed by 2025.
5. Our commissioning intentions are to increase the provision of self-contained supported accommodation and reduce the number of units offering shared supported accommodation. The proposed scheme at Topping Mill offers ‘own front door’ apartments. 6. The proposed model for Topping Mill will offer medium term support for up to 5 years, supporting people to develop person-centred recovery towards greater independent living. The scheme will improve wider system flow creating accommodation and support options for people who are clinically ready for discharge from hospital, the scheme will offer 24/7 supported living and will fill a deficit in local provision.
7. A competitive procurement process has been completed to identify the most suitable care provider for this new scheme. Alternative options considered and rejected
8. The Public Procurement Contracts Regulations 2015 do not allow for light touch or direct award in this case. _________________________________________________________ Report Author and Contact Details: Name: Ahmed Ajmi Position: Integrated Strategic Lead Department: Health and Adult Social Care E-mail: [email protected]
Name: Jannine Robinson Position: Commissioning Manager Department: Community Commissioning E-mail: [email protected] ________________________________________________________________ Background 9. Following approval of the Topping Mill Supported Living Report by Cabinet on 7 November 2023, the Community Commissioning Division has engaged in a competitive procurement process to appoint a care provider for the new mental health supported living scheme at Topping Mill.
10. Topping Mill was a former industrial mill constructed in the mid to late 1800s. The building was originally occupied by the confectioners Scott & Rosse before they vacated in the 1960s. The property has been vacant for several years. It is currently being re-developed by the St David Group, the building work commenced in 2024, with expected completion in June / July 2025. See Appendix 1 for photographs of the site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.