The Cabinet: 1. Approved the appointment of the successful architect Ellis Williams Architects Limited and the project cost in its entirety, to undertake the design of a phased refurbishment of the Town Hall. The contract award will be for all RIBA work stages, subject to two individual break clauses to be exercised at the discretion of the Council at the close of RIBA stage 2 and 4. 2. Authorised the Director of Law and Democratic Services in consultation with the Cabinet Member for Strategic Growth to finalise the terms of the contract appointing the architect. 3. Approved the additional budget of £649,628 to proceed with actions below, ensuring on going compliance of the Town Hall building and progress the refurbishment project including: a. Appointment of Architect and LK b. Town Hall Project Manager c. Asbestos removal d. Compliance of the Town Hall e. Refurbishment of the Town Hall
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1In June 2024, Capital Board approved funding for proposals to deliver a phased approach to the Town Hall refurbishment, and the works required to mitigate the risks associated with health and safety concerns highlighted in a Structural Inspection Report issued in March 2024. It was approved to progress the development of design works up to Royal Institute of British Architects (RIBA) stage 2
1.2This report seeks cabinet approval to appoint the successful architect / design team for the Town Hall Project lifecycle following a mini tender process, via the Constellia framework, and additional budget approval to proceed with the next steps to ensure on going compliance of the Town Hall building and progress the refurbishment project.
1.3Over the project lifecycle, there are two proposed break clauses within the project, to allow pause and consideration of financial commitments and progress.
1.4This report seeks budget approval to recruit a project manager /construction manager to oversee all aspects of the project from its inception to completion
2. Recommendation(s)
That Cabinet: 2.1 Approve the appointment of the successful architect Ellis Williams Architects Limited and the project cost in its entirety, to undertake the design of a phased refurbishment of the Town Hall. The contract award will be for all RIBA work stages, subject to two individual break clauses to be exercised at the discretion of the Council at the close of RIBA stage 2 and 4.
2.2Authorise the Director of Law and Democratic Services in consultation with the Cabinet Member for Strategic Growth to finalise the terms of the contract appointing the architect.
2.3Approve the additional budget of £649,628 to proceed with actions below, ensuring on going compliance of the Town Hall building and progress the refurbishment project.
Appointment of Architect and LK Town Hall Project Manager Asbestos removal Compliance of the Town Hall Refurbishment of the Town Hall
Reasons for recommendations
3.1The recommendations represent the next stage in the delivery of a phased refurbishment of the Town Hall up to RIBA stage 2 and the phased exiting from leased premises at 3 and 6 Knowsley Place, reducing the size and cost of the administrative estate.
3.2Mitigate any health and safety concerns within the Town Hall that have been raised during the process so far.
3.3Creation of a higher quality office space in the Town Hall.
3.4Potential to create future income generation and increase town centre footfall through the sub lease of ground floor space and opportunities, as well as a desire to provide contemporary workplace and office design to reflect new agile working practises and promote staff wellbeing.
Alternative options considered
4.1Do not commence appointment of the architect and continue to repair any ad hoc repairs on the Town Hall.
4.2Remain in 3KP five-storey block at 3 Knowsley Place until 2035, and remain in lease for the six-storey block 6 Knowsley Place, which is in lease in place until 2036 with a break clause in 2031 _________________________________________________________ Report Author and Contact Details: Name: Roger Frith Position: Head of Land and Property Department: Place E-mail: [email protected] ________________________________________________________________ 5. Background
5.0A cross-party Task Force was formed in January 2022 with the objective of identifying a preferred plan for the future of Bury Town Hall. In December 2023. a strategy of refurbishing the Town Hall on a phased basis, funded by the exiting of at least one significant commercial tenancy, was broadly agreed. This was identified as a ‘preferred option’ and since that time further work has been undertaken to find a means to exit a commercial lease with the focus on 3KP (the largest building the Council leases) and 6KP and progress the redesign of the Town Hall
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.