CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 15 October 2025 at 6.00pm

Sureserve Compliance Northwest Contract Extension

Approved Executive 1 paper

AI summaryBury Cabinet approved a 12-month extension of the Sureserve compliance contract to 1 January 2027, valued at an estimated £1,591,800, to allow an options appraisal on future gas services delivery.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSureserve contract extended to 1 January 2027
Money£1,591,800 estimatedValue for extended period, includes 5% annual uplift
What happens nextOptions appraisal on gas servicesTo be carried out during the extension period
Who it affectsCouncil housing tenants and HRA budgetPlus Facilities Management for corporate buildings

What was decided

Cabinet approved a twelve-month extension of the existing Sureserve Compliance Northwest Compliance Ltd Contract until 1 January 2027. Report P4

The extension keeps in place the delivery of landlord statutory compliance services, including gas servicing, repairs, smoke detector testing and capital boiler works. Report P1, P4, P5

Facilities Management will continue to use the contract's call-off option for works in corporate buildings. Report P2

Why

The council must meet its obligations under the Gas Safety (Installation and Use) Regulations 1998, and failing to extend would hinder delivery of those statutory duties. Report P16

Current performance is strong, with 99.99% gas compliance, KPIs met, and no significant issues found in 10% physical audits over the past 18 months. Report P9, P10, P11

Re-procurement was rejected because the time and capacity are not yet in place while the Building Safety, Repairs and Property restructure is ongoing. Report P6

What happens next

An options appraisal will be carried out on the future delivery of gas services during the extension period. Report P5

An additional £0.140m will need to be provided for in the HRA revenue repairs budget for 2026-27, and circa £0.425m in the 2026-27 HRA Capital programme for boiler replacement works. Report P17

In-year pressure in 2025-26 from the first three months of the 2026 extension will be met from existing HRA budgets, the HRA Capital Plan and reserves. Report P18

The money

  • £1,591,800 Estimated value of the extension period, including 5% annual uplift Report P3
  • £1.594m Estimated full-year cost of the contract extension Report P17
  • £1.171m Core elements of the contract met from the HRA revenue repairs budget Report P17
  • £0.140m Increase in current budgets to be provided for in the HRA 2026-27 Report P17
  • £0.425m Capitalised boiler replacement works to be provided for in 2026-27 HRA Capital programme Report P17

Options considered

  • Chosen: Extend the existing Sureserve contract for 12 months to 1 January 2027. Allows time for an options appraisal on future gas services delivery; contract already includes the extension option Report P4, P5, P7
  • Rejected: Re-procure the gas compliance contract. Time and capacity not yet in place due to the Building Safety, Repairs and Property restructure Report P6

Implications

  • Financial: HRA revenue repairs budget must rise by £0.140m in 2026-27, with a further circa £0.425m added to the 2026-27 HRA Capital programme for boiler replacement works. Report P17
  • Financial: Some in-year pressure in 2025-26 from the early months of the 2026 extension will be met from existing HRA budgets, the HRA Capital Plan and reserves. Report P18
  • Equalities: No additional equality impacts identified, as this is a contract extension. Report P13
  • Climate: No additional environmental impacts overall, though newer boilers installed under the contract are more efficient and reduce carbon emissions. Report P14
  • Risk: Failing to extend would hinder the council in fulfilling statutory duties under the Gas Safety (Installation and Use) Regulations 1998. Report P16
  • Other: Sureserve is expected to continue contributing to social value through estate action days, skips and similar initiatives during the extension. Report P19

Who and where

  • Council housing tenants receiving gas servicing, repairs, smoke detector testing and boiler works Report P1, P9, P12
  • The council's Housing Revenue Account (revenue and capital budgets) Report P17, P18
  • Facilities Management, using the call-off option for works in corporate buildings Report P2

Timeline

  • January 2022: Current Sureserve contract commenced for 4 years with a 1-year extension option Report P7
  • 7th November 2023: Cabinet approved novation of the contract to Bury Council as part of the Strategic Housing Review Report P7
  • February 2024: Contract novated from Six Town Housing Limited to Bury Council Report P7
  • 2025-26: In-year pressure from the first three months of the 2026 extension to be covered by HRA budgets, Capital Plan and reserves Report P18
  • 2026-27: HRA revenue repairs uplift of £0.140m and circa £0.425m of capitalised boiler works to be budgeted Report P17
  • 1st January 2027: Extended contract end date Report P4

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account for income and spending on council housing
  • KPI: Key Performance Indicator, a measure of contract performance
  • Novation: Transfer of a contract from one party to another, here from Six Town Housing Limited to Bury Council
  • Procure Plus Framework: A procurement framework used to award the contract
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.60

Resolved

Cabinet approved the extension of the existing Sureserve Compliance Northwest Compliance Ltd Contract for twelve months until 1st January 2027.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1. This report seeks approval to extend the existing Contract for the delivery of Gas Compliance, Repairs, Smoke Detector Testing and Capital Boiler works within Housing Services.

2. There is also a call off option within the Contract being utilised by Facilities Management for the delivery of services in Corporate Buildings.

3. The value for the extended period is estimated to be £1,591,800 plus call off ad hoc call off works provided to Facilities Management. This includes an annual uplift of 5% which is the upper limit of current negotiations.

Recommendation(s) 4. That the Cabinet approves the extension of the existing Sureserve Compliance Northwest Compliance Ltd Contract for twelve months until 1 st January 2027. Reasons for recommendation(s) 5. The contract delivers Landlord Statutory Compliance Services on behalf of the Council.

6. The extension is required to allow time for an options appraisal to be carried out on the future delivery of gas services. Alternative options considered and rejected

7. Re-procurement has been considered; however, due to the Building Safety, Repairs and Property restructure this was rejected as the time and capacity required are not yet in place. _________________________________________________________ Report Author and Contact Details: Name: Ben Tunnicliffe Position: Head of Building Safety Department: Housing Services email: [email protected] ______________________________________________________________ Background

8. The current Contract commenced 1 st January 2022 for a period of 4 years with the option of a further 1-year extension. The Contract was tendered and awarded by Six Town Housing Limited and novated to Bury Council in February 2024. The novation of the contract was approved by Cabinet on 7th November 2023 as part of the Strategic Housing Review which approved the transfer of housing back to the Council from Six Town Housing.

9. The Contract was awarded via the Procure Plus Framework.

10. The Council is currently at 99.99% compliance for servicing of its gas assets and there are no concerns regarding current performance on gas servicing.

11. Sureserve meet all its KPIs in relation to the delivery of repairs in line with KPIs set out in the contract.

12. A 10% physical audit takes place for all Sureserve’s gas compliance activities and no significant issues have been identified in the past 18 months. _________________________________________________________ Links with the Corporate Priorities:

13. Local – ensuring that tenants are kept safe and live in properties they can be proud of, increasing life chances of residents in our most deprived areas. 14. Together – respect for our tenants by ensuring their voices are heard and respected. _________________________________________________________ Equality Impact and Considerations: 15. As this is a contract extension, there are no additional impacts or equalities concerns identified

Environmental Impact and Considerations:

16. There are no additional environmental impacts. 17. Newer boilers installed are more efficient and reduce carbon emissions. 18. There are no biodiversity considerations.

Assessment and Mitigation of Risk: Risk / opportunity Mitigation

The Council is required to meet its Failing to extend the existing contract obligations under The Gas Safety would hinder the Council in fulfilling its (Installation and Use) Regulations 1998. statutory duties. _________________________________________________________ Legal Implications: 19. There are no legal issues with the 1-year extension as this contract was entered in to on a 4-year term with an option to extend for 1-year.

Financial implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sureserve Compliance Northwest Contract ExtensionDecisions 272 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 24 attended
EO
Councillor Eamonn O'BrienChair, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, apologies
ST
Councillor Sean ThorpeCommittee Member, apologies
SA
Councillor Shahbaz ArifCommittee Member, in attendance
RB
Councillor Russell BernsteinCommittee Member, in attendance
CB
Councillor Carol BirchmoreCommittee Member, in attendance

All 24 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open