Bury Metropolitan Borough Council
Cabinet, Wednesday 15 October 2025 at 6.00pm

Prestwich Village Regeneration Scheme: Phase 1A (Travel Hub) – procurement of a third-party operator to manage the Travel Hub

Approved Executive 1 paper

AI summaryBury Cabinet approved hiring an external operator to run the new Prestwich Travel Hub, with the contract likely worth over £500,000 over at least three years, and a soft market testing exercise starting within weeks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyOver £500,000
What happens nextSoft market testingEngagement to begin after Cabinet, full procurement expected to take 4-6 months
Who it affectsPrestwich Village users and wider schemeTravel Hub underpins Prestwich regeneration, including over 200 new homes

What was decided

Cabinet approved using an external, specialist travel hub operator to manage the Prestwich Travel Hub, rather than running it in-house. Report 2.1, 3.1

Cabinet approved a two-stage procurement: an initial soft market testing exercise, followed by a competitive process likely using a procurement framework. Report 2.2, 5.12, 5.14

Cabinet placed the Travel Hub within the Council's commercial asset portfolio, overseen by the Land & Property Service with support from Parking Services, and delegated the choice of procurement route to the Director of Regeneration & Project Delivery. Report 2.3, 2.4, 3.4

Why

An external operator is expected to provide a more responsive 24/7 service, established supply chain, and specialist handling of anti-social behaviour, areas where the Council currently has limited capability. Report 5.9, P32

An operator needs to be appointed within about four months so they can shape the final car park and facilities design and avoid abortive work; the building is due to complete in July 2026. Report 3.3, 5.17, 5.25

What happens next

Soft market engagement will begin after the Cabinet meeting, supported by a parking consultant and the Council's Procurement service, to identify the best route to market. Report 5.12, 5.13, 5.15, 5.21

Indicative timetable: soft market testing and route to market approval 2-3 months; tender documents 1-2 months; tender release and evaluation 2-3 months; award and mobilisation 1-2 months. Report 5.22

A further Cabinet report will be brought back to approve the appointment of the chosen operator once the procurement process is complete. Report 1.8

The money

  • £500,000 Estimated minimum total contract value over at least three years, triggering Key Decision status Report 1.2
  • £173k Annual operating cost difference in favour of an external operator Report 5.6
  • £14 million Approved capital cost envelope for the Travel Hub delivery, including fit-out for an operator Report 5.17
  • 120 Modelled annual direct labour cost with an external operator (£000s) Report P27
  • 266 Modelled annual direct labour cost if run in-house (£000s) Report P27

Options considered

  • Chosen: Appoint an external specialist travel hub operator under a management agreement. Modelled £173,000 a year cheaper, gives 24/7 cover, mature supply chain, and lets the Council vary requirements without recruiting new staff Report 1.4, 5.6, 5.7, 5.11, P23
  • Rejected: Manage the Travel Hub in-house within Parking Services. Higher cost, no existing experience of off-street car parks of this scale, would require about 5 FTE and new infrastructure Report 4.2, 5.7, 5.9, P24

Implications

  • Financial: No direct cost to the Council at this stage: operator costs will be recovered from Travel Hub parking income, with any surplus going to the Highways (Parking) Service. Report 5.8, P72
  • Legal: Procurement must comply with the Public Contract Regulations 2015 and the Procurement Act 2023, which came into force on 24th February 2025; legal will be consulted on terms if needed. Report 3.2, 7.2, P71
  • Risk: A delay in appointing an operator could cause abortive design work and put the July 2026 opening at risk; soft market testing will test supplier interest. Report 3.3, P70
  • Staffing: An in-house option would have required about 5 FTE plus security response cover; the external option removes that recruitment need. Report 5.7, 5.9
  • Equalities: An Equality Impact Assessment found a neutral effect on all groups with protected characteristics.
  • Climate: The wider Prestwich scheme is designed to be low and net zero carbon, with a target of more than 40% biodiversity uplift on the site. Report 8.2, P67, P68

Who and where

  • Users of Prestwich Village and the new Travel Hub, including drivers using over 300 car parking spaces
  • Bury Council's Land & Property Service and Parking Services team, who will oversee the operator Report 2.3, 3.4, 5.10
  • Future residents of the wider Prestwich Village scheme, who will be allocated designated spaces in the hub Report 5.9
  • The Highways (Parking) Service, which will receive any surplus parking income Report 5.8
  • External travel hub and car park operators in the regional market, who may bid for the contract Report 5.12

Timeline

  • 16th July 2024: Earlier Cabinet approved capital funding for the Prestwich Travel Hub Report 1.1, P74
  • 4th December 2024: Earlier Cabinet approved appointment of the main contractor Report 1.1, P75
  • 24th February 2025: Procurement Act 2023 came into force, governing this procurement Report 7.2
  • 24th March 2025: Construction of the Travel Hub started on site Report 5.25
  • 15th October 2025: Cabinet decision to approve the external operator model and two-stage procurement Report 1.5
  • Post-Cabinet: Soft market engagement expected to begin Report 5.21
  • July 2026: Expected completion of the Travel Hub building Report 5.25

Plain English for the jargon

  • Prestwich Regeneration LLP: Joint venture company of Bury Council and Muse Places Ltd delivering the Prestwich Village Regeneration scheme.
  • Framework: An agreement with pre-approved suppliers, with set terms and legal protections, used to procure goods and services.
  • Soft market testing: Engaging with potential suppliers before a formal tender to test interest, scope, and commercial models.
  • Third-party operator: An outside company brought in to manage or operate a service (here, the Travel Hub) on the Council's behalf.
  • FTE: Full-time equivalent staff, counted as 37 hours per week.
  • KPI: Key Performance Indicator, used to measure contract performance.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.53

Resolved

Cabinet: 1. Approved the recommended operations management model for the Prestwich Travel Hub. This is the use of an external, specialist travel hub operator; 2. Approved the undertaking of a two-stage procurement process for appointment of an external operator for the Travel Hub covering an initial soft market testing process followed by an external competitive procurement in-keeping with the Council’s Contract Procedure Rules. This will likely include the use of a relevant procurement Framework. 3. Approved the management of the Prestwich Travel Hub asset within the Bury Council Commercial Asset Portfolio by the Land & Property Service, with support from Parking Services; and 4. Approved the Director of Regeneration & Project Delivery in consultation with the Council’s Procurement service to agree the preferred route to market.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1Cabinet approved capital funding to deliver the Prestwich Travel Hub facility on Fairfax Road on the 16th July 2024. Permission to appoint a main contractor to deliver the project was secured from Cabinet on the 4th December 2024. Following consideration of available options for managing the Travel Hub once built; officers now seek approval for a recommended operating model and strategy for procurement to acquire a Travel Hub operator.

1.2Following consideration of appropriate options, officers recommend the procurement of an external travel hub operator to manage the Prestwich Village Travel Hub. Subject to further soft market testing, the Council will need to enter into at least a three-year management agreement. Over this period, it is estimated that the contract will exceed £500,000 which constitutes a Key Decision.

1.3The report outlines estimated costs of the two available operating models for management of the Prestwich Travel Hub. These include the use of an external third-party operator or the management of the hub internally within the Council structures.

1.4The report outlines that the use of an external operator represents better value for money to the Council. This is because the operation of off-street car parking facilities of the scale proposed at Prestwich is not currently a core function of the Council. The Authority does not currently operate similar facilities and as such, will need to invest in the relevant staffing and infrastructure to deliver this new model. Given that private sector external operators operate numerous similar facilities at greater scale, external advice suggests that they are able to secure a lower unit cost of operation and a more responsive service.

1.5Officers recommend a two-stage process for acquisition of a travel hub operator. This would entail a process of initial soft market testing by way of an Expression of Interest to ascertain level of interest and compare commercial management models in further detail. The process will also identify the most effective procurement route to market which will likely include use of a recognised procurement framework.

1.6The Prestwich Travel Hub building will be owned by Bury Council as a commercial asset. Under the current Council structure, this asset will be managed via the Land & Property Service within the Place Directorate alongside the wider commercial portfolio. 1.7 The Prestwich Travel Hub is under construction and completion of the building is expected July 2026. It is essential that an operator for the facility is sourced in the next 4 months to enable them to contribute to the final car park and facilities specification and prevent abortive activity.

1.8Upon completion of a procurement process to acquire an external operator, officers will bring a further report before Cabinet to approve the appointment.

Recommendation(s) It is recommended that Cabinet:

2.1Approves the recommended operations management model for the Prestwich Travel Hub. This is the use of an external, specialist travel hub operator.

2.2Approves the undertaking of a two-stage procurement process for appointment of an external operator for the Travel Hub covering an initial soft market testing process followed by an external competitive procurement in-keeping with the Council’s Contract Procedure Rules. This will likely include the use of a relevant procurement Framework.

2.3Approves the management of the Prestwich Travel Hub asset within the Bury Council Commercial Asset Portfolio by the Land & Property Service, with support from Parking Services.

2.4Approves the Director of Regeneration & Project Delivery in consultation with the Council’s Procurement service to agree the preferred route to market.

Reasons for recommendation(s)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prestwich Village Regeneration Scheme: Phase 1A (Travel Hub): procurement of a third-party operator to manage the Travel HubDecisions 628 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 24 attended
EO
Councillor Eamonn O'BrienChair, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, apologies
ST
Councillor Sean ThorpeCommittee Member, apologies
SA
Councillor Shahbaz ArifCommittee Member, in attendance
RB
Councillor Russell BernsteinCommittee Member, in attendance
CB
Councillor Carol BirchmoreCommittee Member, in attendance

All 24 on the meeting page

On this subject at Bury

Search all
  1. Prestwich Village Regeneration Scheme: Phase 1A (Travel Hub) – procurement of a third-party operator to manage the Travel HubThis decision
  2. Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved
  3. Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding RequestApproved
  4. Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part AApproved
  5. Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)Approved
  6. Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part AApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open