CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 15 April 2026 at 6.00pm

Procurement for Repairs and Maintenance Framework

Approved Executive 1 paper

AI summaryBury Council Cabinet approved a new Repairs and Maintenance Framework for housing, with procurement to conclude by July 2026. The £4-5 million, 4-year framework replaces ad-hoc arrangements and is split into general building and specialist services lots.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor housing repairs and maintenance service
Money£4-5 millionEstimated spend over 4-year framework life
What happens nextProcurement to conclude July 2026Followed by Cabinet award report
Who it affectsHousing repairs contractors and tenantsReplaces existing ad-hoc arrangements

What was decided

Cabinet approved the procurement and development of the Repairs and Maintenance Framework for housing repairs and maintenance. Report P4

The framework will be structured into two lots: a General Building Lot for 1 to 2 main contractors, and a Specialist Services Lot split into 7 sub-lots covering electrical, aids and adaptations, drainage, glazing, painting, pest control and scaffolding. Report P1

Cabinet rejected using external frameworks, citing 2-3% management fees of around £100,000 to £150,000 and low SME representation. Report P8, P9

Why

To comply with the Procurement Act 2023 and uphold principles of fairness, transparency, value for money and accountability. Report P5

The council says it must urgently reduce uncontrolled spending in repairs and maintenance budgets and get better cost, quality and lifecycle value. Report P6

A full publicly advertised tender will accommodate incumbent suppliers and give fair opportunities for local and regional contractors. Report P7

What happens next

Procurement is scheduled to conclude in July 2026, followed by a Cabinet Award Report seeking approval to award the framework. Report P2

Procurement officers will develop a detailed implementation plan, timetable, resource plan, procurement documentation and governance papers. Report P2

The money

  • circa £4-5 million Projected total spend over the 4-year framework life Report P2
  • around £1.6m Current annual spend on repairs and maintenance arrangements
  • approximately £100,000 - £150,000 Management fee cost avoided by not using an external framework, based on 2-3% of £5 million Report P9
  • 2-3% Typical management fee applied by external framework providers Report P9

Options considered

  • Chosen: Develop and run a council-owned Repairs and Maintenance Framework with a full public tender. Avoids external management fees, gives control over terms and pricing, and supports SME participation Report P1, P4, P7, P9
  • Rejected: Use external Frameworks to source the council's requirements. Would incur an estimated £100,000 to £150,000 in management fees on a £5 million framework, with limited influence over terms and low SME representation Report P8, P9

Implications

  • Legal: Supports the council's statutory duties to maintain housing stock under section 11 of the Landlord and Tenant Act 1985 and the Housing Act 2004, and its Best Value duty under the Local Government Act 1999. Report P15, P16
  • Financial: Estimated costs have been provided for in the recently approved HRA budget and business plan. Report P17
  • Equalities: Providers must comply with the Equality Act 2010 and the Public Sector Equality Duty, including policies and data reporting on protected characteristics. Report P10, P11
  • Climate: Framework is expected to have a manageable environmental impact; specifications can require low-carbon practices, sustainable materials, and biodiversity protection, aligned with the council's Net Zero ambitions. Report P14
  • Risk: Key risks are non-compliance with the Procurement Act 2023 and uncontrolled repairs spending; mitigation is a compliant full tender process. Report P15

Who and where

  • Council housing tenants receiving repairs and maintenance services Report P16
  • Incumbent repairs and maintenance suppliers Report P7
  • Local and regional contractors, including SMEs Report P1, P2, P7

Timeline

  • 2026-04-15: Cabinet approves procurement and development of the framework
  • July 2026: Procurement process scheduled to conclude Report P2
  • After July 2026: Cabinet Award Report to be presented seeking approval to award the framework Report P2
  • 4 years: Duration of the framework once awarded Report P2

Plain English for the jargon

  • Procurement Act 2023: UK law in force from February 2025 that replaces previous EU-derived procurement regulations, aiming to simplify and add transparency to public procurement.
  • Framework: An agreement between a contracting authority and one or more suppliers setting terms for future contract awards under it.
  • SME: Small and Medium-sized Enterprises.
  • HRA: Housing Revenue Account, the ring-fenced account landlords use for income and spending on council housing.
  • Best Value: Duty under the Local Government Act 1999 requiring councils to deliver economy, efficiency and effectiveness in services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.8

Resolved

Cabinet: Approved the procurement and development of the Repairs and Maintenance Framework for housing repairs and maintenance service. Reasons for decision: To maintain compliance with statutory obligations of the Procurement Act 2023 and ensures principles are fairness, transparency, value for money, and accountability. Bury Council must urgently prioritise value for money in the repairs and maintenance budgets by significantly reducing uncontrolled spending. In doing so seeks the best balance of cost, quality, long-term performance and lifecycle value for repairs and maintenance works. A full tender issued with Bury Council designing lots to reflect service needs and then publicly advertising the contract. This is to accommodate incumbent suppliers and give fair opportunities for local and regional contractors to tender. Alternative options considered and rejected: Use external Frameworks to source Bury’s requirements Rejected: Framework providers typically apply a minimum 2-3% management fee. On a projected framework value of £5 million, this would amount to approximately £100,000 - £150,000, a cost the Council would avoid by delivering the framework directly. In addition, such Frameworks have limited influence over framework terms and pricing models, and SME representation at framework level is often low. </AI8> Councillor M. Smith queried how local SME’s could be attracted if they had no previous dealings and where would they find these contracts. In response, the Cabinet Member for Housing Services described the procurement pathways available with more engagement making partnership working better which included medium sized enterprises.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks Cabinet approval to proceed with a full procurement to establish the Council’s own Framework for Repairs and Maintenance services (“Repairs and Maintenance Framework”), in compliance with the Procurement Act 2023. The Repairs and Maintenance Framework will be structured into two broad Repairs and Maintenance Lots. This package is designed to have less lots with 1 to 2 main repairs and maintenance contractors delivering a wider range of services under a ‘General Building’ Lot. The second lot is for ‘Specialist Services’ and is broken down into 7 individual sub lots covering electrical repairs, aids & adaptations, drainage, glazing, painting, pest control and scaffolding.

The Repairs and Maintenance Framework is projected to have an estimated spend of circa £4-5 million over the life of the framework which is 4 years. The framework will have a greater emphasis on social value outcomes and SME participation. The procurement is scheduled to be concluded in July 2026. Following this, a subsequent Cabinet report accompanied by an Award Report providing a full audit on the tender process will be presented to seek approval for awarding the Repairs and Maintenance Framework.

Recommendation(s)

Cabinet is requested to approve the procurement and development of the Repairs and Maintenance Framework for housing repairs and maintenance service. Reasons for Recommendation(s)

To maintain compliance with statutory obligations of the Procurement Act 2023 and ensures principles are fairness, transparency, value for money, and accountability.

Bury Council must urgently prioritise value for money in the repairs and maintenance budgets by significantly reducing uncontrolled spending. In doing so seeks the best balance of cost, quality, long-term performance and lifecycle value for repairs and maintenance works.

A full tender issued with Bury Council designing lots to reflect service needs and then publicly advertising the contract. This is to accommodate incumbent suppliers and give fair opportunities for local and regional contractors to tender. Alternative options considered and rejected

Use external Frameworks to source Bury’s requirements

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement for Repairs and Maintenance FrameworkDecisions 406 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, apologies
ST
Councillor Sean ThorpeCommittee Member, apologies
LR
Lynne RidsdaleOfficer, present
JD
Jacqui DennisOfficer, present
SG
Sian GrantOfficer, present

All 14 on the meeting page

On this subject at Bury

Search all
  1. Procurement for Repairs and Maintenance FrameworkThis decision
  2. Procurement for Gas Compliance, Repairs and Maintenance FrameworkApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies