Resolved
Cabinet approved the re-procurement of Gas Compliance, Repairs and Maintenance services for the Council.
AI summaryBury Cabinet approves re-procurement of gas servicing contract, extending the current deal with Sureserve by three months to 31 March 2027 so a new contract can start on 1 April 2027 outside the winter peak.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Cabinet approved the re-procurement of Gas Compliance, Repairs and Maintenance services for the Council.
This report seeks Cabinet approval to proceed with procurement for Gas Compliance, Repairs and Maintenance services for the Council (“Service Provision”), and sets out the governance, current position, key objectives and route-to-market considerations. The purpose is to provide senior leadership with a clear and comprehensive set of options, including associated benefits, risks, and implications, enabling them to review, agree, and approve the preferred route to market. The procurement this Service Provision will be undertaken in accordance with: Procurement Act 2023 principles: fairness, transparency, value for money, and accountability. Bury Council’s Contract Procedure Rules. Social Value Act requirements and Bury Council’s Social Value Policy. Assurance from Legal, Finance, Procurement, and relevant service leads.
A decision on the preferred route to market and how the scope of works is packaged will be made by the Senior Leadership Team. Recommendation(s) Cabinet is requested to approve the re-procurement of Gas Compliance, Repairs and Maintenance services for the Council. Reasons for Recommendation(s) To maintain compliance with The Gas Safety (Installation and Use) Regulations 1998 and statutory obligations of the Procurement Act 2023 and ensures principles of fairness, transparency, value for money, and accountability. Bury Council is currently in contract with ‘Sureserve Compliance North West’ until 31 December 2026, and who are currently delivering the Gas Compliance, Repairs and Maintenance for the Council. This contract is due to end on 31st December 2026, and whilst the contract does not provide a contractual right to extend, it is proposed that it be extended by a further period of 3 months to 31st March 2027. Alternative options considered and rejected
All procurement options listed below are being considered: Route to Market Key Features
Direct Procurement – A full tender issued under the Procurement Public Advertisement Act 2023 regime, with Bury Council designing lots to reflect service needs and publicly Option 1 advertising the contract. Contractors may self-deliver or subcontract to local SMEs
Third-Party Public Use of compliant external frameworks such Sector Framework as Procurement Hub, ProcurePlus, Fusion21. Option 2 Contractors are pre-qualified and call-offs may be via direct award or mini competitions.
Dynamic Purchasing A live system where suppliers can join at any Option 3 System (DPS) point, ideal for trade-based repairs like gas engineers. Supports open SME access
Term Service Long-term contract (3–5 years) suitable for Option 4 Contract / Measured reactive repairs and cyclical maintenance Term Contract (MTC) using SOR frameworks.
Bury Council establishes its own multi-lot Multi Provider Local Option 5 framework, allowing several suppliers for Authority Framework each category.
Rejected: None. _________________________________________________________ Report Author and Contact Details: Name: Ben Tunnicliffe Position: Head of Housing Compliance Department: Corporate Core – Housing Services E-mail: [email protected] ________________________________________________________________ Background
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Procurement for Gas Compliance, Repairs and Maintenance FrameworkDecisions | 484 KB | DownloadRead as text |
Follow Cabinet at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... | Approved | Open |
| 14 Oct 2026 | Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... | Approved | Open |
| 14 Oct 2026 | New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... | Approved | Open |
| 14 Oct 2026 | Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... | Approved | Open |
| 14 Oct 2026 | Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.