Bury Metropolitan Borough Council
Cabinet, Wednesday 14 October 2026 at 6.00pm

Highways Capital Programme - Highway Maintenance Funding 2026/27

Approved Executive 4 papers

AI summaryBury Metropolitan Borough Council Cabinet approved £12.917m of highway capital investment for 2026/2027, with some schemes continuing into 2027/28 [D] [6.1] [1.1]. Work covers carriageways, structures, footways, drainage, lighting, road safety, signs and public rights of way [1.1] [P28].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRoad safety programme detail was noted [2.4]
Money£12.917m available funding [6.1]Combined CRSTS, ITB, Network North and Mayor’s Pothole Fund [6.1]
What happens nextHighway delivery with delegated changes [2.5]Partners deliver works, with amendments kept within budget [9.1] [2.5] [P44]
Who it affectsHighway assets and users [1.1]Condition, resilience, accessibility and connectivity [1.1] [8.1] [7.3]

What was decided

The Highways Capital Investment Programme and its associated funding allocation were approved.

The asset management and prioritisation method was approved. The proposed culvert and structure works were approved, and the previously approved road safety programme detail was noted. Report 2.2, 2.3, 2.4

Authority was delegated to the Executive Director of Place, in consultation with the Deputy Leader and the Cabinet Member for Environment, Climate Change and Operations, to amend the programme and prioritisation method in response to changing asset condition, emerging risks, funding opportunities and delivery considerations. Amendments must remain within the approved budget and follow the Council’s Constitution and Scheme of Delegation. Report 2.5, P44

Why

The Council has a statutory duty to maintain the public highway and associated infrastructure, including structures deemed publicly maintainable. The risk based approach targets safety, asset condition, network resilience and long term value for money. Report 3.1, P43

Prioritisation uses condition surveys, network performance information and professional engineering judgement. It directs resources towards interventions with the greatest network benefit and considers coordination with other planned works. Report 5.3, 7.1, 7.3

Approval allows external funding to be used within the conditions and delivery timescales attached to it. The recommended programme was considered the most effective use of available funding based on condition, risk, deliverability and strategic need. Report 3.3

What happens next

Schemes will be delivered by partners under the Framework Agreement for highway related services and works. The agreement includes commitments on sustainable employment, support for local business and communities, and carbon emission reductions. Report 9.1

The Council must meet external funding conditions, timescales and reporting requirements. Procurement must follow the Contract Procedure Rules and applicable procurement legislation. Report P45

Individual activities will remain under review for equalities impacts. The Executive Director of Place may amend the programme and method under the approved delegation as conditions change. Report P37, 2.5

The money

  • £12.917m Total available funding for the 2026/2027 programme Report 6.1
  • £4.374m Additional Mayor’s Pothole Fund allocation Report 5.2, 6.1, P20

Options considered

  • Chosen: Risk based asset management and prioritisation programme. Funding is directed by condition, risk, network need and deliverability, with engineering checks confirming scheme suitability, treatment, costs and deliverability. Report 5.3, 7.1, 7.3
  • Rejected: Alternative investment approaches. The recommended programme was considered the most effective use of available funding based on condition, risk, deliverability and strategic need. Report 4.0

Implications

  • Legal: The programme supports the Council’s duty under section 41 of the Highways Act 1980 to maintain highways at public expense. Report P43
  • Risk: Approval is intended to reduce further highway deterioration and make funding available for safety related reactive maintenance repairs. Report P41
  • Financial: The allocations are within the approved capital programme, and there are no additional financial implications. Report P47
  • Financial: Failure to commit funding through an approved programme could delay delivery and affect spend profiles. It could also reduce the Council’s ability to gain the most from available investment within required funding periods. Report 3.3
  • Legal: Works using external funds must meet funding conditions, timescales and reporting requirements. Procurement must follow the Contract Procedure Rules and applicable procurement legislation. Report P45
  • Climate: Construction materials, plant and transport will contribute to carbon emissions. Preventative and timely work is intended to extend asset life, reduce carbon intensive reconstruction and limit reactive maintenance. Report P38
  • Equalities: Initial screening found no equalities concerns for the programme. Individual activities will remain under review as delivery progresses. Report P37
  • Staffing: Framework partners are committed to sustainable employment, support for local business and communities, and carbon emission reductions. Report 9.1

Who and where

  • Borough residents and highway users Report 1.1, P28, P35
  • People accessing employment, education, healthcare and local services Report P35
  • Local businesses and the wider local economy Report 9.1, P35
  • The Council in its role as highway authority Report 3.1, P43
  • Regeneration, utility and active travel projects needing coordination Report 7.3
  • Framework Agreement partners delivering highway works Report 9.1

Timeline

  • 2026/2027: Funding allocations are committed during the programme, which covers management, maintenance and improvement of highway assets. Report 1.1
  • 2027/28: Delivery of some schemes extends into this period. Report 1.1
  • 22/23 to 26/27: CRSTS Core and CRSTS KRN funding periods. Report P17, P18
  • 2022/23 to 2026/27: Original CRSTS Core fund period, including approved schemes, Incentive fund and prior underspend. Report P17
  • 2026/2027: ITB funding supports local highway and road safety improvements. Report P21
  • recently announced: The Mayor’s Pothole Fund allocation of £4.374m was announced. Report 5.2, 6.1

Plain English for the jargon

  • CRSTS: City Regional Sustainable Transport Settlement [P51]
  • ITB: Integrated Transport Block [P51]
  • KRN: Key Route Network, the most important roads across GM in terms of connectivity and economic activity [P51]
  • HIS4: Highway Investment Strategy, Tranche 4 [P51]
  • Mayor’s Pothole Fund: Additional funding allocated for highway maintenance and network improvements [P20]
  • Network North (HS2): High Speed Rail 2 redistribution remaining funds [P19]
  • Framework Agreement: The agreement through which partners deliver highway related services and works [9.1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.87

Resolved

Decision(s) Cabinet · Approved the Highways Capital Investment Programme and associated funding allocation set out in Table 2. · Approved the proposed asset management and prioritisation approach used to determine investment priorities across the highway network, as detailed in Appendix 1. · Approved the proposed works on culverts and structures detailed Appendix 2. · Noted the previously approved road safety programme detail in Appendix 3. · Delegated authority to Executive Director of Place, in consultation with Deputy Leader of the Council, Councillor Smith Cabinet Member for Environment, Climate Change and Operations to approve amendments to the programme of work and prioritisation method where required, to respond to changing asset condition, emerging risks, funding opportunities and delivery considerations. Reasons for Decision(s) · The Council, as the Highway Authority for Bury, has a statutory duty to maintain the public highway and associated infrastructure, including structures deemed to be publicly maintainable. The proposed programme provides a balanced and risk-based approach to managing the borough's highway assets, ensuring investment is targeted towards those interventions that deliver the greatest benefit in terms of safety, asset condition, network resilience and long-term value for money. · The programme has been developed using asset management principles to prioritise investment based on condition, risk and network need, helping to manage deterioration across the network, protect previous investment and reduce future maintenance liabilities. It supports the Council's wider priorities for economic growth, connectivity, thriving communities and resilient public infrastructure. · Approval of the programme will also enable the Council to utilise external funding allocations within the conditions and delivery timescales attached to those funding streams, including the Mayor's Pothole Fund, CRSTS and Integrated Transport Block funding. Failure to commit funding through an approved programme risks delaying delivery, affecting spend profiles and reducing the Council's ability to maximise the benefits of available investment within the required funding periods. Alternative Options Considered and Rejected · Alternative investment approaches have been considered. However, the recommended programme represents the most effective use of available funding based on asset condition, risk, deliverability and strategic need. The proposed approach ensures investment is prioritised transparently and consistently in accordance with the Council's Highway Asset Management Plan and the requirements of external ... view the full minutes text for item CA.87
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1This report seeks approval for the Council's Highways Capital Investment Programme for the period 2026/2027, and the associated investment priorities that will guide the management, maintenance and improvement of the borough's highway assets. The programme brings together a range of funding sources to support investment across carriageways, footways, structures, drainage systems, street lighting, highway signs, road safety infrastructure and public rights of way. Whilst funding allocations will be committed during 2026/27, delivery of some schemes will extend into 2027/28. This phased approach supports effective programme management, maximises value for money and enables coordination with other planned investment and network activities. 2.0 Recommendations 2.1 Approve the Highways Capital Investment Programme and associated funding allocation set out in Table 2.

2.2Approve the proposed asset management and prioritisation approach used to determine investment priorities across the highway network, as detailed in Appendix 1.

2.3Approve the proposed works on culverts and structures detailed Appendix 2.

2.4Note the previously approved road safety programme detail in Appendix 3.

2.5Delegate authority to Executive Director of Place, in consultation with Deputy Leader of the Council, Councillor Smith Cabinet Member for Environment, Climate Change and Operations to approve amendments to the programme of work and prioritisation method where required, to respond to changing asset condition, emerging risks, funding opportunities and delivery considerations.

3.0Reasons for Recommendation(s)

3.1The Council, as the Highway Authority for Bury, has a statutory duty to maintain the public highway and associated infrastructure, including structures deemed to be publicly maintainable. The proposed programme provides a balanced and risk-based approach to managing the borough's highway assets, ensuring investment is targeted towards those interventions that deliver the greatest benefit in terms of safety, asset condition, network resilience and long-term value for money. 3.2 The programme has been developed using asset management principles to prioritise investment based on condition, risk and network need, helping to manage deterioration across the network, protect previous investment and reduce future maintenance liabilities. It supports the Council's wider priorities for economic growth, connectivity, thriving communities and resilient public infrastructure.

3.3Approval of the programme will also enable the Council to utilise external funding allocations within the conditions and delivery timescales attached to those funding streams, including the Mayor's Pothole Fund, CRSTS and Integrated Transport Block funding. Failure to commit funding through an approved programme risks delaying delivery, affecting spend profiles and reducing the Council's ability to maximise the benefits of available investment within the required funding periods.

4.0Alternative Options Considered and Rejected 4.1 Alternative investment approaches have been considered. However, the recommended programme represents the most effective use of available funding based on asset condition, risk, deliverability and strategic need. The proposed approach ensures investment is prioritised transparently and consistently in accordance with the Council's Highway Asset Management Plan and the requirements of external funding providers.

______________________________________ Report Author and Contact Details: Name: Jon R O’Connor Position: Group Manager – Network & Asset Management Department: Place E-mail: [email protected] ________________________________________________________________ 5.0 Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Resurfacing MethodologyAppendix 1 26 KB Download
PDF
Structures PrioritiesAppendix 2 113 KB Download
PDF
Road Safety PrioritiesAppendix 3 106 KB Download
PDF
Highways Capital Programme: Highway Maintenance Funding 2026/27Decisions 207 KB DownloadRead as text

At this meeting

Whole meeting
CA.74Public Question TimeOn the agenda CA.76MinutesOn the agenda CA.78Review and amendments to Bury Council's Housing Allocations PolicyApproved CA.79Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Approved CA.80New Persona Shareholder Agreement - PART AApproved CA.81Extension of Lease for St Monica's - Part AApproved CA.82Objections to the proposed disposal of Public Open Space - Land on the North Side of Milton Road, Radcliffe, BuryOn the agenda CA.83New Ash Grove Additional Provision AcademyOn the agenda CA.84Proposed creation of an End-to-End Greater Manchester Fostering HubNoted CA.85Families First Partnership Programme - Part AApproved CA.8610-year occupational Lease - 6b & 6c Bridge Trading EstateApproved
CA.87Highways Capital Programme - Highway Maintenance Funding 2026/27This decision
CA.88Live Well Implementation in the BoroughNoted CA.89Draft 2027/28 BudgetOn the agenda CA.90Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved CA.91Parking and Bus Lane Enforcement ServicesNoted CA.92Minutes Of Association Of Greater Manchester Authorities / Greater Manchester Combined AuthorityOn the agenda CA.94Exclusion of Press and PublicDecided CA.95New Shareholder Agreement with Persona PART B - October Cabinet 2026Approved CA.96Extension of lease for St Monica's - Part BApproved CA.97Families First Partnership Programme - Part BApproved

Who was there

0 of 17 attended
EO
Councillor Eamonn O'BrienChair, expected
AA
Councillor Ayesha ArifCommittee Member, expected
RG
Councillor Richard GoldCommittee Member, expected
GM
Councillor Gavin McGillCommittee Member, expected
CM
Councillor Charlotte MorrisCommittee Member, expected
LS
Councillor Lucy SmithCommittee Member, expected
TT
Councillor Tamoor TariqCommittee Member, expected
ST
Councillor Sean ThorpeCommittee Member, expected
SW
Councillor Sandra WalmsleyCommittee Member, expected
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Highways Capital Programme - Highway Maintenance Funding 2026/27This decision
  2. Highways Capital Programme UpdateApproved
  3. Highways Capital Programme - Highway Maintenance Funding 2023/24 to 2026/27 and Integrated Transport Block 22/23Agreed
  4. Highways Capital Programme - Highway Maintenance Funding 2023/24 to 2026/27 and Integrated Transport Block 22/23Approved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies