CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 14 October 2026 at 6.00pm

Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations Strategy

Approved Executive 1 paper

AI summaryCabinet recognised APCOA as Travel Hub operator and approved an operations strategy with parking and other charges [D]. The facility is expected to open in Autumn 2026, with annual operating costs of approximately £300,000.00 [9.2, 8.11].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAPCOA's operator role was acknowledged [2.1]
Moneyapproximately £300,000.00 operating cost [8.11]Annual cost, with subsidy if charges absent [3.2, 8.11]
What happens nextAutumn 2026 opening [9.2]APCOA to complete mobilisation before opening [1.5]
Who it affectsTravel Hub users [2.3]Parking, electric vehicle charging, cycle storage and season tickets [2.3, 8.8, 8.9, 8.10]

What was decided

Cabinet recognised APCOA Parking (UK) Limited, Company number 02572947, as the appointed third party operator for the Travel Hub [D].

Cabinet approved the operations strategy needed to support the Travel Hub opening [D].

Cabinet approved parking charges and other charges, and agreed the parking price schedule set out in Section 8 [D].

Why

The building is practically complete and now belongs to the Council, so an operating strategy is needed to support public opening once APCOA is fully mobilised [3.1]. Report 3.1

Charging should generate income and cover APCOA's operating costs. Without charges, the Council would need to subsidise the facility by approximately £300,000 per annum [3.2]. Report 3.2

The chosen pricing follows current Bury town centre charges as closely as possible and was presented as the best value option, including meeting APCOA's annual operating costs [4.3]. Report 4.3

What happens next

APCOA is to implement the approved charges and price schedule during mobilisation, before the Travel Hub opens [P51]. Report P51

The Travel Hub is expected to open in Autumn 2026 after APCOA completes mobilisation [9.2]. Report 9.2

APCOA will collect usage and price data monthly, and Cabinet will receive a further report at the six month stage after implementation [P54]. Report P54

The money

  • approximately £300,000.00 per annum Travel Hub operating costs [8.11] Report 8.11
  • approximately £300,000 per annum Council subsidy needed if charges are not introduced [3.2] Report 3.2
  • £52,388 Expected net surplus in Year 1 [8.11] Report 8.11
  • £203,412.00 per annum Expected net surplus thereafter [8.11] Report 8.11
  • £1.00; £2.40; £2.70; £3.20; £4.30; £6.00; £16.00; £1.50 Parking charges for one hour, two hours, three hours, four hours, five hours, five to 12 hours, 12 to 24 hours, and Sunday all day. The five to 12 hour and 12 to 24 hour rates are slightly higher to reflect the secure building [P43, 8.6] Report P43, 8.6
  • £0.64 per kWh Recommended electric vehicle charging charge, in keeping with the Bury Council Market car park [8.8] Report 8.8
  • £1 per entry Cycle storage management charge [8.9] Report 8.9
  • £60.00; £3.00 per day Monthly season ticket and its stated daily equivalent, based on 48 weeks of five day usage [8.10] Report 8.10

Options considered

  • Chosen: Pricing based on Bury town centre charges. The report says it has as much parity as possible with current town centre charges, represents best value and is intended to meet APCOA's annual operating costs [1.7, 4.3, 8.4]. Report 1.7, 4.3, 8.4
  • Rejected: Do not agree the operations strategy. The Travel Hub would be prevented from opening [4.1]. Report 4.1
  • Rejected: Do not introduce charges and a parking price schedule. The Council could not generate income to cover the third party operator's costs [4.2]. Report 4.2
  • Rejected: Other modelled parking price options. The recommended option was judged best value and aligned with town centre charges where possible [4.3]. Report 4.3

Implications

  • Financial: The charges are forecast to cover operating costs and produce £52,388 net surplus in Year 1, followed by £203,412.00 per annum thereafter [8.11]. Report 8.11
  • Financial: Any surplus income must be ring fenced for specific transport and community uses under the Road Traffic Regulation Act 1984 and the Traffic Management Act 2004 [18.3]. Report 18.3
  • Legal: Cabinet must act reasonably, consider all relevant matters and comply with the Equality Act 2010. Subject to implementation under the APCOA contract and regulatory requirements, there are no direct legal implications from the recommendations [17.2, 17.3]. Report 17.2, 17.3
  • Equalities: There are no outstanding equalities concerns or considerations at this stage [14.2]. Report 14.2
  • Climate: The Travel Hub will support active travel and provide electric vehicle charging, which can provide additional income [7.2, 8.8]. Report 7.2, 8.8
  • Risk: Usage and income are difficult to predict before opening. Actual income may fall below forecast, so income must be closely monitored and variances reported to Cabinet. Charges will be monitored and APCOA's marketing plan will promote usage [8.11, 18.2, P75, P76]. Report 8.11, 18.2, P75, P76
  • Staffing: APCOA will initially provide 12 hours of staffing each day, usually between 6:00 and 18:00, with flexible times. Monitoring of cars via CCTV will operate 24 hours a day, and the Council's Emergency Response Team will be connected for out of hours emergencies [7.6, 7.8]. Report 7.6, 7.8
  • Other: Payments will be cashless, reducing theft risk and removing the cost of secure cash collection [7.5]. Parking will be free from 18:00 to 24:00 to support the evening and nighttime economy, with charges from 00:00 for overnight parking. Other Prestwich car parks will remain free, except Longfield, which will be out of use during site investigation works [8.7, P53]. Report 7.5, 8.7, P53

Who and where

  • Travel Hub users [2.3, P28] Report 2.3, P28
  • APCOA Parking (UK) Limited [2.1] Report 2.1
  • Corporate Assets & Facilities Management service [6.3] Report 6.3
  • Bury Council [3.2, 6.3] Report 3.2, 6.3
  • Electric vehicle users [8.8] Report 8.8
  • Cyclists [7.7] Report 7.7
  • Commuters and season ticket users [8.10] Report 8.10
  • Users of other Prestwich car parks [P53] Report P53

Timeline

  • 13th October 2021: Cabinet approved the Council and Muse Places Limited forming the Prestwich Regeneration LLP to deliver the project [5.4]. Report 5.4
  • 15th October 2025: Cabinet approved a third party operator as the preferred operating management model [1.3, 7.1]. Report 1.3
  • 11th March 2026: Cabinet gave senior officers delegated authority to complete procurement and award the contract [1.4]. Report 1.4
  • 8th July 2026: An update on Phase 1A and the third party operator was reported [P25]. Report P25
  • 25th September 2026: Phase 1A reached practical completion and was handed to the Council as building owner [1.2]. Report 1.2
  • 14 October 2026: Cabinet took the Travel Hub operations strategy decision [D, P2]. Report P2
  • Autumn 2026: The Travel Hub is expected to open after APCOA completes mobilisation [9.2]. Report 9.2
  • six month stage post implementation: Cabinet will receive a further report on usage, charging effects and possible changes [P54]. Report P54

Plain English for the jargon

  • Prestwich Regeneration LLP: Joint venture company comprising Bury Council and Muse Places Ltd, established to deliver the Prestwich Village Regeneration Project [P92].
  • APCOA: The car park operator [P92].
  • PARCS: Parking Access and Revenue Control System, an automated system for vehicle entry, parking duration and payments [P93].
  • EVCI: Electric Vehicle Charging Infrastructure [P93].
  • ANPR: Automatic Number Plate Recognition [P94].
  • Spokesafe: Company that manages safe and secure parking spaces for bikes [P95].
  • Parking Matters: Specialised parking consultancy advising on parking strategies, operations and innovation [P95].
  • kWh: Kilowatt hour [P95].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.90

Resolved

Decision(s) Cabinet: · Acknowledged APCOA Parking (UK) Limited (Company number 02572947) as the appointed third-party operator for the Travel Hub. · Approved the operations strategy to facilitate the opening of the Travel Hub. · Approved the introduction of parking charges and other charges in the new Prestwich Travel Hub and subsequent agreement to the implementation of a tariff structure as set out in Section 8 of this report. Reasons for recommendation(s) · To successfully facilitate the Travel Hub opening to the public (once APCOA is fully mobilised) now construction of the building is practically complete and is within the Council’s ownership. · To enable the Travel Hub to have an operations strategy including a charging and parking tariff structure in place to generate income and cover APCOA’s operational costs for managing the facility. Opening the Travel Hub without implementing charging would mean that the Council would need to subsidise the facility by approximately £300,000 per annum. Alternative options considered and rejected · Not agreeing to the operations strategy but this would prevent the Travel Hub from opening. · Not introducing a charges and parking tariff structure but this would prevent the Council from generating income to be able to cover the costs of a third-party operator managing the Travel Hub. · Various parking tariff options have been considered and financially modelled, but the recommended option is in keeping (as much as possible) with the current parking tariffs within Bury Town Centre (noting the differences between the operation of a surface-level car park and a building) and overall, represents best value for money, including meeting the annual operating costs of APCOA.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 14 October 2026 Prestwich Village Regeneration Project: Phase 1A (Travel Hub) – Subject: Operations Strategy Report of Cabinet Member for Regeneration and Growth

Summary 1.1 The Prestwich Village Regeneration Project will deliver a comprehensive re- development of the Prestwich Village site including the Longfield Centre. The Council has formed a Joint Venture (the JV) with Muse Places Limited (Company number 02717800), referred to as Muse to deliver this activity. The project will deliver a new village centre and contribute to the Council’s strategic aims (Bury 2030) and ‘Let’s Do It’ Strategy.

1.2Extensive progress continues to be made on the development and delivery of the project. The first phase (Phase 1A Travel Hub) is practically complete and was handed over to the Council as building owner on 25th September 2026.

1.3Approval was sought from Cabinet (15th October 2025) to procure a third-party operator to manage the Travel Hub. A Public Contracts Regulations 2015 compliant procurement process is complete, and APCOA Parking (UK) Limited (Company number 02572947) referred to as APCOA has been appointed and is now in contract.

1.4The appointment of APCOA was enabled by previous approval at Cabinet (11th March 2026) with delegated authority for senior officers to approve the procurement process once complete and award the contract.

1.5APCOA is currently working with the Council to prepare the Travel Hub for opening in Autumn 2026.

1.6Alongside the above, work has been undertaken to determine the correct operating strategy that will include the introduction of parking charges for the facility and other charges as set out in this report. This report is therefore seeking approval for the strategy, charging and tariff structure to enable the Travel Hub to be open and fully operational within the required timeline.

1.7The recommended parking tariff structure is modelled on and has as much parity as possible with the current Bury Council Town Centre parking charges, notwithstanding the differences between the management of a surface-level car park and an operational building (that is the Travel Hub). Recommendation(s) It is recommended that Cabinet:

2.1Acknowledge APCOA Parking (UK) Limited (Company number 02572947) as the appointed third-party operator for the Travel Hub.

2.2Approves the operations strategy to facilitate the opening of the Travel Hub.

2.3Approves the introduction of parking charges and other charges in the new Prestwich Travel Hub and subsequent agreement to the implementation of a tariff structure as set out in Section 8 of this report.

Reasons for recommendation(s)

3.1To successfully facilitate the Travel Hub opening to the public (once APCOA is fully mobilised) now construction of the building is practically complete and is within the Council’s ownership.

3.2To enable the Travel Hub to have an operations strategy including a charging and parking tariff structure in place to generate income and cover APCOA’s operational costs for managing the facility. Opening the Travel Hub without implementing charging would mean that the Council would need to subsidise the facility by approximately £300,000 per annum.

Alternative options considered and rejected

4.1Not agreeing to the operations strategy but this would prevent the Travel Hub from opening.

4.2Not introducing a charges and parking tariff structure but this would prevent the Council from generating income to be able to cover the costs of a third-party operator managing the Travel Hub.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prestwich Village Regeneration Project: Phase 1A (Travel Hub): Operations StrategyDecisions 288 KB DownloadRead as text

At this meeting

Whole meeting
CA.74Public Question TimeOn the agenda CA.76MinutesOn the agenda CA.78Review and amendments to Bury Council's Housing Allocations PolicyApproved CA.79Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Approved CA.80New Persona Shareholder Agreement - PART AApproved CA.81Extension of Lease for St Monica's - Part AApproved CA.82Objections to the proposed disposal of Public Open Space - Land on the North Side of Milton Road, Radcliffe, BuryOn the agenda CA.83New Ash Grove Additional Provision AcademyOn the agenda CA.84Proposed creation of an End-to-End Greater Manchester Fostering HubNoted CA.85Families First Partnership Programme - Part AApproved CA.8610-year occupational Lease - 6b & 6c Bridge Trading EstateApproved CA.87Highways Capital Programme - Highway Maintenance Funding 2026/27Approved CA.88Live Well Implementation in the BoroughNoted CA.89Draft 2027/28 BudgetOn the agenda
CA.90Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyThis decision
CA.91Parking and Bus Lane Enforcement ServicesNoted CA.92Minutes Of Association Of Greater Manchester Authorities / Greater Manchester Combined AuthorityOn the agenda CA.94Exclusion of Press and PublicDecided CA.95New Shareholder Agreement with Persona PART B - October Cabinet 2026Approved CA.96Extension of lease for St Monica's - Part BApproved CA.97Families First Partnership Programme - Part BApproved

Who was there

0 of 17 attended
EO
Councillor Eamonn O'BrienChair, expected
AA
Councillor Ayesha ArifCommittee Member, expected
RG
Councillor Richard GoldCommittee Member, expected
GM
Councillor Gavin McGillCommittee Member, expected
CM
Councillor Charlotte MorrisCommittee Member, expected
LS
Councillor Lucy SmithCommittee Member, expected
TT
Councillor Tamoor TariqCommittee Member, expected
ST
Councillor Sean ThorpeCommittee Member, expected
SW
Councillor Sandra WalmsleyCommittee Member, expected
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyThis decision
  2. Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding RequestApproved
  3. Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part AApproved
  4. Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)Approved
  5. Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part AApproved
  6. Prestwich Village Regeneration Project: Phase 1B and 2 Development StrategyApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies